03 FEB 2021 6:38PM by PIB Delhi
Indian Railways set to complete 56 key existing projects in the Feb-Mar 21 & FY 2021-22

To boost Rail Infrastructure and make the Indian Railways network future ready, Indian Railways has identified 56 projects all across the country in various zones to be completed by Feb-Mar,21 and the FY 2021-22.

Indian Railways has highest ever total Plan capex of Rs. 2,15,058 Crores this year out of which Rs. 1,07,100 Crores for capital expenditure has been  allocated in the General Budget, This time onwards, in a paradigm shift, Railways has focussed on the completion of existing projects quickly as well besides simultaneity working on the new projects announced.    

As far as new big projects are concerned, Rs 40932 Crores have been allocated for New Lines, Rs 26116  Crores for Doubling, Rs 5263 Crores for Traffic Facilities & Rs 7122 Crore for ROBs/RUBs. Traffic Facilities have seen  a whopping  156% jump in allocation while New Lines have got  52% increase in allocation as compared to Last Year.

Other than these major projects, for the convenience of Public, Railways is set to complete more than 1200 Road Over Bridge(ROB), Road Under Bridges (RUB), Subways this year. These ROBs/RUBs are of vital importance for public in cities and other areas where railway  lines are passing through.Over and above these existing projects, an  additional Rs 7122 Crores have been allocated for construction of new ROB/RUBs this year. It may be noted that total Number of existing ROB/RUBs in the country is 14000.

The thrust of Annual Plan 2021-22 is on infrastructure development, throughput enhancement, development of terminal facilities, augmentation of speed of trains, signaling systems, improvement of passengers/users’ amenities, safety works of road over/under bridges etc.

The following plan heads have been allotted highest ever outlays in BE 2021-22 –

(₹in cr)

Planhead

BE 2020-21

BE 2021-22

Increase over BE 2020-21

New Lines

26971

40932

52%

Doubling

21545

26116

21%

Traffic Facilities

2058

5263

156%

ROB/RUBs

6204

7122

15%

 

The list of 56 Railway Projects to be completed in Feb-Mar 21 FY 2021-22 is as under:

Important New Line, gauge Conversion and Doubling  projects targeted to be commissioned in Feb-Mar 21 FY 2021-22

S.No.

Name of Project

Length of Project (Km)

Month/Year of commissioning

 

Hansdiha-Godda New Line

32

Feb-21

 

Omalur-Metturdam Patch Doubling

29

Feb-21

 

Netravati-Mangalore

2

Feb. 21

 

Nirmali - Saraigarh New line including Kosi Bridge

22

Mar-21

 

Ahmedabad-Botad

170

Mar-21

 

Pilibhit-Shahjahanpur Gauge Conversion

83

Mar-21

 

Utretia – Raebarelli

66

Mar-21

 

Ghazipur-Aunihar

40

Mar-21

 

Bhusawal-Jalgaon 3rd line

24

Mar-21

 

Ambari-Falkata doubling

38

Mar-21

 

Ambalapuzha-Haripad

18

Mar-21

 

Tambram-Chengalpattu
Gauge Conversion

30

Mar-21

 

Ajmer-Bangurgram Doubling

47

Mar-21

 

New Mynaguri-Gumanihat

52

Apr-21

 

Jayanagar – Bijalpura

52

May-21

 

Dhasa – Jetalsar GC

104

May-21

 

Bangurgram-Guriya Patch DL

47

May-21

 

Hajipur-Bachwara doubling

72

May-21

 

Kankanadi-Panambur

19

May-21

 

Raibarelli-Amethi  doubling

60

May-21

 

Pendra Road-Anuppur - 3rd line

50

May-21

 

Daund-Gulburga  doubling

225

Jun-21

 

Khurda Rd-Bararng

32

Jun-21

 

Katereah-Kursela patch doubling

7

Jun-21

 

Bandel Boinchi 3rd line

31

Jun-21

 

Mathura-Palwal 4th line

80

Jun-21

 

Jallandhar-Pathankot-Jammu Tawi doubling

209

Jun-21

 

Manoharpur-Bondamunda 3rd line

30

Jun-21

 

Kharagpur-Narayanagarh 3rd line

24

Jun-21

 

Arsikere-Tumkur doubling

96

 June 21

 

Raibareilly-Amethi Doubling

60

Jun-21

 

Secunderabad-Mehboobnagar doubling

85

Jun-21

 

Yelahanka-Penukonda doubling

123

Jun-21

 

Bhadrachalam Road-Sattupalli

54

Jun-21

 

Vijayawada-Gudiwada-Bhimavaram-Narsapur, Gudiwada-Machlipatnam

221

Jul-21

 

Madurai – Bodinayakkanaur gauge Conversion

90

Sep-21

 

Ahmedabad-Mehsana Gauge conversion

69

Oct. 21

 

Digaru-Hojai doubling

102

Oct. 21

 

Dausa-Gangapur City New Line

93

Nov. 21

 

Sambalpur-Talcher doubling

168

Dec-21

 

Sambalpur-Titlagarh doubling

106

Dec-21

 

Raipur-Titlagarh

203

Dec-21

 

Banspani-Daitari-Tomka-Jakhapura doubling

164

Dec-21

 

Dankuni-Chandanpur 4th line

25

Dec-21

 

Boinchi Shaktigarh 3rd line

26

Dec-21

 

Bhimsen-Jhansi doubling

206

Dec-21

 

Kurruppanthara-Chingavanam doubling

27

Dec. 21

 

Bina-Kota doubling

283

Dec. 21

 

Viramgam-Samakhyali doubling

182

Dec. 21

 

Ayodhya- Varanasi - Railway Electrification

188

28-Feb-22

 

Guwahati-Lumding- - Railway Electrification

180

28-Feb-22

 

Mansi-Saharsa, incl. Saharsa-DauramMadhepura-Purnia& MM Banmakhi- Bihariganj
Gauge Conversion

169

31-Mar-22

 

Palanpur-Makarpura section (WDFC)

308

31-Mar-22

 

Rewari-Dadri section (WDFC)

127

31-Mar-22

 

Palanpur -Kandla port-Mundra port-Bhuj- Railway Electrification

475

31-Mar-22

 

Hospet-Hubli-Vasco - Railway Electrification

341

31-Mar-22

 

*****

DJN/MKV