Sl. No
|
Name
|
States benefited
|
Annual Irrigation (Lakh ha)
|
Domestic & Industrial (MCM)
|
Hydro power
(MW)
|
Year of completion of FR/DPR
|
Status
|
| |
Ken-Betwa link Project (KBLP)
|
Uttar Pradesh (UP) & Madhya Pradesh (MP)
|
10.62 (UP- 2.51 MP. - 8.11)
|
194
|
103 MW (Hydro) & 27MW(Solar)
|
DPR completed in 2018
|
Govt. of India has approved the implementation of KBLP in December 2021 with an estimated cost of Rs 44605 crore (year 2020-21 price level) with central support of Rs 36,290 crore through a Special Purpose Vehicle viz; Ken Betwa Link Project Authority (KBLPA). Honourable Prime Minister has laid the foundation stone for project on 25.12.2024.
The project is to complete by March 2030.
|
| |
Godavari (Inchampalli) -Krishna (Nagarjunasagar) link
|
Telangana
|
2.38
|
232
|
26
|
DPR completed in January, 2024
|
1. DPR for this modified proposal was circulated to party States in January 2024
2. Draft MoA for implementation was circulated among party states in April 2024.
|
| |
Krishna (Nagarjunasagar)- Pennar (Somasila) link
|
Andhra Pradesh (AP)
|
1.71
|
236
|
40
|
DPR completed in January, 2024
|
| |
Pennar (Somasila) - Cauvery (Manimuktha) link
|
AP
|
0.51
|
43
|
|
DPR completed in January, 2024
|
|
Tamil Nadu
|
1.14
|
618
|
|
Puducherry
|
--
|
62
|
| |
Modified Parbati-Kalisindh-Chambal link
|
MP & Rajasthan
|
Benefits as per MoA: MP - 6.11
Rajasthan – 4.03
Total = 10.15 lakh ha
|
Benefits as per MoA:
MP-(71.39 drinking +21.50 industrial) = 92.9
Rajasthan –(1744.16 drinking + 205.75 industrial) = 1949.91
Total = 2043 MCM
|
-
|
MoA for implementation has been signed in year 2024
|
Memorandum of Understanding (MoU) for preparation of DPR was signed by both the States (MP and Rajasthan) on 28.01.2024.
Memorandum of Agreement (MoA) for implementation has been signed in December 2024.
DPRs of components of Rajasthan have been completed and uploaded on e-PAMS Portal of CWC.
|
| |
Krishna (Almatti) – Pennar link
|
Karnataka
|
0.69
|
464.51
|
----
|
DPR Completed in September 2025.
|
|
|
AP
|
1.57
|
10.1-Drinking water
22.3- Industrial
|
----
|
|
| |
Bedti - Varda link
|
Karnataka
|
1.05
|
38
|
----
|
DPR completed in September 2022.
|
Presently, PFR of alternate link has been submitted to State in August 2025.
|
| |
Netravati – Hemavati link
|
Karnataka
|
0.34
|
--
|
--
|
PFR completed in year, 1994
|
Further studies are not taken up since after implementation of Yettinahole project in 2014 by Govt. of Karnataka, no surplus water is available in Netravati basin for diversion through this link.
|
| |
Godavari (SSMP/Inchampalli) -Krishna (Pulichintala) link
|
Telangana & AP
|
TOTAL 4.74
Telangana - 0.36
|
Telangana- 26.8
|
90.0
|
DPR completed in March 2024
|
|
|
AP - 4.38
|
AP - 319.7
|
|
-
|
Godavari (Polavaram) -Krishna (Viayawada) link (Polavaram irrigation project)
|
AP
|
4.36
|
665
|
960
|
DPR was completed in 2005
|
Benefits included here are the total benefit under Polavaram Irrigation project.
|
|
11
|
Krishna (Srisailam) – Pennar link
|
AP
|
1.79
|
58
|
11
|
DPR completed in March 2024
|
|
| |
Kosi-Ghaghra link
|
Bihar, U.P & Nepal
|
Total 8.35
6.05 –Bihar
|
0
|
--
|
FR completed
|
|
|
1.20 – U.P
|
|
Nepal -1.10
|
|
13
|
Gandak - Ganga link
|
U.P & Nepal
|
Total - 34.58
U.P -28.80
Nepal -5.78
|
700
|
4375 (Dam PH) & 180 (Canal PH)
|
FR completed in June 2024
|
|
|
14
|
Yamuna-Rajasthan link
|
Haryana & Rajasthan
|
Haryana - 0.11
|
30
|
1702
|
FR completed in September, 2021
|
|
|
Rajasthan- 2.40
|
|
15
|
Rajasthan-Sabarmati link
|
Rajasthan & Gujarat
|
Total - 11.53
Rajasthan - 11.21
|
102
|
5126
|
FR completed in Feb, 2021
|
|
|
Gujarat-0.32
|
|
16
|
Chunar-Sone Barrage link
|
Bihar & U.P
|
Total - 0.60
Bihar - 0.10
U.P. - 0.49
|
--
|
--
|
FR completed in September, 2025
|
|
|
17.
|
Ganga (Farakka) - Damodar-Subarnarekha link
|
W.B., Odisha& Jharkhand
|
W.B. -11.18
Orissa- 0.39
Jharkhand- 0.73
|
432
|
--
|
FR completed in March 2021
|
|
|
18.
|
Subarnarekha-Mahanadi link
|
W.B. & Odisha
|
Total - 2.16
W.B. - 0.18
Orissa - 1.98
|
198
|
20
|
FR completed in Feb. 2021
|
|