Union Tribal Affairs Minister Shri Jual Oram today laid a statement on the table of the House Rajya Sabha that under Pradhan Mantri Janjati Adivasi Nyaya Maha Abhiyan (PM JANMAN), a total of 4,73,939 houses have been sanctioned of which approximately 2.50 lakh houses (as on 31.12.2025) have been completed.
(b) & (c): The details of progress of multi-purpose centers along with progress of piped water supply, electrification, road connectivity and other interventions converged under PM JANMAN are given in Annexure-I.
(d): To ensure the effective implementation and monitoring of the PM JANMAN, Ministry has been regularly reviewing the implementation with State Governments and District administrations. Besides, for monitoring the progress of the works under PM JANMAN, digital dashboard on PM GatiShakti portal has been developed. A Project Monitoring Unit in the Ministry has also been established for monitoring and coordination with Ministries and States / UT. Further, the State Government is also required to comply with the instructions of Department of Expenditure regarding SNA SPARSH alongwith applicable GFRs.
Annexure-I
Annex referred to in reply to part (b) & (c) of Rajya Sabha Starred Question No.*130 for answer on 11.02.2026 raised by Smt. Sadhna Singh regarding “Implementation of PM-JANMAN Scheme”
The details of progress under PM JANMAN (as on 31.12.2025)*
|
Name of Ministry
|
Activity
|
Mission Target (2023-2026)
|
Sanction details
|
Physical Achievements
|
|
M/o Rural Development
|
Provision of pucca houses
|
4.90 lakh houses
|
473939 houses
|
250374 houses completed
|
|
Connecting roads
|
8000 km road
|
7316.62 km road
|
1196 Km road completed
|
|
M/o Health and Family Welfare
|
Mobile Medical Units
|
1000 MMU (750 MMUs sufficient to cover all)
|
750 MMUs
|
750 MMUs operationalized
|
|
M/o Jal Shakti
|
Piped Water Supply
|
19375 Villages
|
18693 Villages
|
8199 Villages 100% Saturated
|
|
M/o Women and Child Development
|
Construction and running of Anganwadi Centres
|
2500
|
2500 AWCs
|
2251 AWCs made operational.
|
|
M/o Education
|
Construction and running of hostels
|
500
|
500 Hostels
|
8 completed
|
|
M/o Power
|
Energization of unelectrified HHs
|
145083 HHs
|
145083 HHs
|
134995 HHs Electrified
|
|
M/o New and Renewable Energy
|
Households sanctioned under New Solar Power Scheme
|
As per identificaton of beneficiaries eligible for off-grid
|
8823 HHs
|
6154 HHs Electrified
|
|
M/o Communications
|
Installation of mobile towers
|
Coverage of 4543 habitations
|
4084 habitations planned for Coverage
|
3006 Habitations covered
|
|
M/o Tribal Affairs
|
Multipurpose Centers
|
1000
|
1000 MPCs
|
375 completed
|
|
Setting up of VDVKs
|
500
|
539 VDVKs
|
450 VDVKs Business Started
|
* As per information provided by concerned Ministries
*****
RN/