Ministry of Road Transport & Highways

Mumbai-Goa Highway

Posted On: 18 JUL 2017 2:29PM by PIB Delhi

In a written reply to a question in the Rajya Sabha today, the Minster of State for Road Transport & Highways and Shipping, Shri Mansukh L. Mandaviya gave the following information regarding the  Mumbai-Goa Highways construction project:

 

 S.

No.

Description

Length (km)

Estimated Project Cost

(Rs. in cr.)

Mode of financing

Share-holding of partners

Length completed

1

Panvel to Indapur section

from km 0/000 to km 84/000

84.00

942.69

BOT (Toll)

1. M/s Supreme Infrastructure India Ltd. – 26%

2. M/s City Universe Ltd. (100% subsidiary of China State Construction Engineering (Hong Kong) Ltd.) – 26%

3. M/s Mahavir Roads and Infrastructure Private Ltd. – 10%

4. M/s Supreme Infrastructure BOT Private Ltd. – 38%

36 km.

2

Indapur to Wadpale section from km 84/000 to km 108/400

26.75

1202.52

EPC

M/s Chetak Enterprises Ltd. – 70%

M/s APCO Infratech Private Ltd. – 30%

0 km.

3

Veer (Wadpale) to Bhogaon Khurd section from km 108/400 to km 148/0 

38.76

1598.47

EPC

M/s Larsen & Toubro – 100%

0 km.

4

Kashedi Ghat section from km 148/0 to km 161/600

8.96

745.79

EPC

Civil works not awarded

0 km.

5

Khawati to Dhamandevi section from km 161/600 to km 205/400

42.33

1142.62

Hybrid Annuity

M/s Kalyan Toll Infrastructure Ltd. – 100%

0 km.

6

Pedhe Parshuram to Khershet section from km 205/400 to  km 241/300

34.45

983.14

Hybrid Annuity

M/s Chetak Enterprises Limited – 50%

M/s Eagle Infra India Limited – 50%

0 km.

7

Arawali to Kante section from km 241/300 to km 281/300

39.24

1101.58

Hybrid Annuity

M/s MEP Infrastructures Developers Ltd. – 74%

M/s San Jose India Infrastructure & Constructions Pvt. Ltd. – 26%

0 km.

8

Niwali to Waked section from km 281/300 to 332/200

49.15

1230.02

Hybrid Annuity

M/s MEP Infrastructures Developers Ltd. – 74%

M/s San Jose India Infrastructure & Constructions Pvt. Ltd. – 26%

0 km.

9

Watul to Talgaon section from km 332/200 to km 367/200

33.26

1244.75

EPC

M/s KCC Buildcon Pvt. Ltd. – 100 %

0 km.

10

Talgaon to Kalmath section from km 367/200 to km 406/000

38.38

904.7

Hybrid Annuity

M/s KCC Buildcon Pvt. Ltd. – 100 %

0 km.

11

Kalmath to Zarap section from km 406/000 to km 450/170

43.91

1338.13

Hybrid Annuity

M/s Dilip Buildcon Limited – 100%

0 km.

12

Construction of Major/minor bridges and ROBs between Indapur and Zarap

Bridge work

187.79

EPC

M/s Khare & Tarkunde Infra Pvt. Ltd. – 100%

Bridge work

13

Zarap to Patradevi section from km 450/170 to 475/0

21.50

264.05

Item rate

M/s SMS Infrastructure private limited – 100%

21.50 km.

14

Patradevi to Karaswada section from km 475.000 to 502.500

25.50

634.32

EPC

Civil works not awarded

0 km.

15

Mandavi River Bridge (funded by State Govt.)

Bridge work

403.00

Item rate

M/s Larsen & Toubro – 100%

Bridge work

16

Karaswada-Porvorim-Panaji-Bambolim section from km 502.500 to km 514.830 and km 517.880 to km 522.790

17.44

852.665

EPC

M/s Navayuga Engineering Company Limited– 100%

0 km.

 

Total Length

503.63

14776.235

 

 

 

 

The Panvel to Indapur and Zarap to Patradevi sections of Mumbai – Goa (Panjim) Highway have been proposed or constructed as bituminous pavement. For the remaining length of the highway, new 4-lane or 2-lane carriageway has been proposed as cement concrete pavement and wherever existing 2-lane carriageway is retained, bituminous pavement has been proposed.

 

*****             