Ministry of Road Transport & Highways
Status of Key Highway Projects In Himachal Pradesh
Posted On:
28 NOV 2024 6:20PM by PIB Delhi
ANNEXURE REFERRED TO IN REPLY TO PART (a) OF LOK SABHA UNSTARRED QUESTION NO. 660 TO BE ANSWERED ON 28TH NOVEMBER, 2024 ASKED BY SHRI ANURAG SINGH THAKUR REGARDING STATUS OF KEY HIGHWAY PROJECTS IN HIMACHAL PRADESH.
|
Sr.
No.
|
Name of Work
|
Physical Progress
/ Status
|
|
Parwanoo – Solan – Shimla - Dhalli
|
|
1
|
4 Lane, Parwanoo-Solan, NH-5
|
Completed
|
|
2
|
4 Lane, Solan-Kaithalighat, NH-5
|
85.17%
|
|
3
|
4 Lane, Shimla Bypass, Pkg-I (from Kaithlighat to
Shakral), NH-5
|
25%
|
|
4
|
4 Laning of Shimla Bypass, Pkg-2 (from Shakral to
Dhalli) (New NH-5)
|
14%
|
|
Pinjore – Baddi - Nalagarh
|
|
5
|
4 Lane, Pinjore Baddi-Nalagarh, NH-105
|
37%
|
|
Shimla - Mataur
|
|
6
|
4 Lane, Shimla Mataur Pkg-5B (Bhangbar to Kangra
Bypass), NH-303, 503
|
82.64%
|
|
7
|
2 Lane-PS, Shimla Mataur Pkg-4 (Chilbahal to
Bhangbar), NH-03, 303
|
51.11%
|
|
8
|
2 Lane-PS, Shimla Mataur (Hamirpur Bypass), NH-
103, 03
|
54.24|%
|
|
Pathankot – Chakki - Mandi
|
|
9
|
4 Lane, Pathankot - Mandi Pkg-IA (HP/Punjab
Border to Mo), NH-154
|
40.97%
|
|
10
|
4 Lane, Pathankot - Mandi Pkg-1B (Mo to Sihuni),
NH-154
|
98.20%
|
|
11
|
4 Lane, Pathankot - Mandi Pkg-2A (Sihuni to Rajol),
NH-154
|
41.50%
|
|
12
|
Pathankot – Mandi Pkg-2B (Rajol to Thanpuri), NH-
154
|
DPR under
Progress
|
|
13
|
4 Lane, Pathankot-Mandi Pkg-2C (Thanpuri to
|
6.53%
|
|
|
Paror), NH-154
|
|
|
14
|
Pathankot – Mandi Pkg-3 (Paror to Chauntra), NH-
154
|
Fresh DPR to be
initiated
|
|
15
|
Pathankot - Mandi Pkg-4 (Chauntra to Padhar), NH-
154
|
Fresh DPR to be
initiated
|
|
Garamaura – Sawarghat – Mandi - Manali
|
|
16
|
2 Lane+PS/ 4 Lane, Kullu – Manali, NH-03
|
Completed
|
|
17
|
4 Lane, Takoli – Kullu, NH-03
|
Completed
|
|
18
|
4 Lane, Kiratpur – NerChowk (Brown field
alignment), NH-205, 154
|
Completed
|
|
19
|
4 Lane, Balance work of Kiratpur – Nerchowk
(Greenfield)
|
Completed
|
|
20
|
4 Lane, Sundernagar Bypass, NH-154
|
Completed
|
|
21
|
2 Lane Tunnel, Kiratpur – Nerchowk section, NH-
205
|
95.68%
|
|
22
|
4 Lane, Ner Chowk – Pandoh, NH-03
|
92.60%
|
|
23
|
4 Lane, Pandoh Bypass – Takoli, NH-03
|
94.51%
|
There has been delays in completion projects due to delay in pre- construction activities, delay in statutory clearances, contractors financial problems, force majeure events, scarcity of construction materials etc. Government has taken various initiatives for expediting project on National Highways in the country including the state of Himachal Pradesh, like streamlining and expediting of land acquisition, Revamping Parivesh Portal for forest and environment clearances, online approval of General Arrangement Drawing(GAD) of ROB/RUB from Railways, review meetings at various levels with all stake holders including State Governments.
This information was given by the The Union Minister of Road Transport & Highways, Shri Nitin Gadkari in a written reply in Lok Sabha today.
*****
DS/AK