2,360 km length of railway lines commissioned in Maharashtra upto March 2025, expenditure of ₹39,407 crore incurred for it


Commissioning of new railway tracks in Maharashtra increases three times between 2014-25 in comparison to 2009-14

27 Multi-tracking projects of total length 1991 Km. costing approx. Rs. 47,126 crore sanctioned in Maharashtra since 2022-23

Posted On: 01 AUG 2025 5:21PM by PIB Mumbai

: Mumbai, August 1, 2025 

As on 1st April, 2025, 38 projects (11  New Lines, 02 Gauge Conversion and 25 Doubling), of a total length of 5,098 km, costing ₹ 89,780 crore, falling fully or partly in Maharashtra, are sanctioned, out of which 2,360 km length has been commissioned and an expenditure of  ₹39,407 crore has been incurred upto March 2025. The summary is as under:-

Category

No of sanctioned Projects

Total Length

NL/GC/DL

(in Km)

Length Commissioned till Mar'25
(in Km)

Total Exp upto Mar'25

(₹ in Cr)

New Lines

11

1,355

234

10,504

Gauge Conversion

02

609

334

4,286

Doubling / Multitracking

25

3,134

1,792

24,617

Total

38

5,098

2,360

39,407

Budget allocation for Infrastructure projects and safety works, falling fully/ partly in the State of Maharashtra is as under:

Period

Outlay

2009-14

₹ 1,171 crore/year

2025-26

₹ 23,778 crore (More than 20 times)

Commissioning of sections (New Line, Gauge Conversion and Doubling) falling fully/partly in the State of Maharashtra during 2009-14 and 2014-2024 is as under:-

Period

New track Commissioned

Average commissioning of new tracks

2009-14

292 Km

58.4 Km/year

2014-25

2,292 Km

208.36 Km/year (more than 3 times)

Details of some of the recently completed projects falling fully/partly in Maharashtra are as under:

S.No.

Project

Cost

(₹ in crore)

1

Jabalpur-Gondia Gauge Conversion (300 Km)

2,005

2

Chhindwara-Nagpur Gauge Conversion (150 Km)

1,512

3

Panvel-Pen Doubling (35 Km)

263

4

Panvel-Roha Doubling (75 Km)

31

5

Pen-Roha Doubling (40 Km)

330

6

Udhna-Jalgaon Doubling (307 Km)

2,448

7

Mudkhed-Parbhani Doubling (81 Km)

673

8

Bhusawal-Jalgaon 3rd Line (24 Km)

325

9

Jalgaon-Bhusawal 4th line (24 Km)

261

10

Daund-Gulbarga Doubling (225 Km)

3,182

Some of the main projects falling fully/partly in the Maharashtra which have been taken up are as under:

S.No.

Name of the project

Cost ( In crore)

1

Ahmednagar-Beed-Parle Vaijnath New Line (261 Km.)

4,957

2

Baramati-Lonand New Line (64 Km.)

1,844

3

Wardha-Nanded New Line (284 Km.)

3,445

4

Dhule (Borvihir)-Nardana New Line (51  Km.)

1,171

5

Manmad-Indore New Line (309 Km.)

16,321

6

Wadsa-Gadchiroli New Line  (52 Km.)

1,886

7

Jalna -Jalgaon New Line (174 Km.)

5,804

8

Pune-Miraj-Londa  Doubling (466 Km.)

6,463

9

Daund-Manmad  Doubling (236 Km.)

30,376

10

Mudkhed-Medchal & Mahbubnagar-Dhone section Doubling (417 Km.)

4,686

11

Hotgi-Kudgi-Gadag Doubling  (284 Km.)

2,459

12

 Kalyan-Kasara 3rd line (68 Km.)

1,433

13

Wardha-Nagpur 3rd line (76 Km.)

698

14

Wardha-Ballarshah 3rd line (132 Km.)

1,385

15

Itarsi-Nagpur 3rd line (280 Km.)

2,450

16

Manmad-Jalgaon 3rd line (160 Km.)

1,677

17

Kazipet-Ballarshah 3rd line (202 Km.)

3,183

18

Rajnandgaon-Nagpur 3rd line (228 Km.)

3,545

19

Wardha-Nagpur 4th line (79 Km.)

1,137

20

Jalgaon-Manmad 4th Line (160 Km)

2,574

21

Bhusawal-Khandwa 3rd & 4th Line (131 Km.)

3,285

During the last three years i.e FY 2022-23, 2023-24, 2024-25 and the current FY, 27 Multi-tracking  project of total length 1991 Km., costing approx. 47,126 crore falling fully/ partly in the State of Maharashtra, have been sanctioned. 

These multi-tracking projects will enhance line capacity, provide additional passenger and freight traffic, enable faster movement of goods and services, reduce operational bottlenecks, improve logistics efficiency, increase in direct and indirect employment opportunities for the people of the region, develop tourism industry and increase industrial activities in the region.

Further, during  the last three years i.e. FY 2022-23, 2023-24, 2024-25 and the current FY, 94 surveys (26 New Line, 2 Gauge Conversion and 66 Doubling) of total length 7979 Km. falling fully/ partly in the State of Maharashtra have been sanctioned under PM Gati Shakti National Master Plan.

In Maharashtra, entire existing Broad Gauge (BG) network (5,938 Route Km.) has been electrified.  All New Line projects are being sanctioned and constructed with electrification.

Union Minister of Railways, Information & Broadcasting and Electronics & Information Technology, Shri Ashwini Vaishnaw stated this in reply to an unstarred question by Shri  Dhananjay Bhimrao Mahadik in the Rajya Sabha today.

Sriyanka Chatterjee/Priti Malandkar

 