Ministry of Railways
2,360 km length of railway lines commissioned in Maharashtra upto March 2025, expenditure of ₹39,407 crore incurred for it
Commissioning of new railway tracks in Maharashtra increases three times between 2014-25 in comparison to 2009-14
27 Multi-tracking projects of total length 1991 Km. costing approx. Rs. 47,126 crore sanctioned in Maharashtra since 2022-23
Posted On:
01 AUG 2025 5:21PM by PIB Mumbai
: Mumbai, August 1, 2025
As on 1st April, 2025, 38 projects (11 New Lines, 02 Gauge Conversion and 25 Doubling), of a total length of 5,098 km, costing ₹ 89,780 crore, falling fully or partly in Maharashtra, are sanctioned, out of which 2,360 km length has been commissioned and an expenditure of ₹39,407 crore has been incurred upto March 2025. The summary is as under:-
|
Category
|
No of sanctioned Projects
|
Total Length
NL/GC/DL
(in Km)
|
Length Commissioned till Mar'25
(in Km)
|
Total Exp upto Mar'25
(₹ in Cr)
|
|
New Lines
|
11
|
1,355
|
234
|
10,504
|
|
Gauge Conversion
|
02
|
609
|
334
|
4,286
|
|
Doubling / Multitracking
|
25
|
3,134
|
1,792
|
24,617
|
|
Total
|
38
|
5,098
|
2,360
|
39,407
|
Budget allocation for Infrastructure projects and safety works, falling fully/ partly in the State of Maharashtra is as under:
|
Period
|
Outlay
|
|
2009-14
|
₹ 1,171 crore/year
|
|
2025-26
|
₹ 23,778 crore (More than 20 times)
|
Commissioning of sections (New Line, Gauge Conversion and Doubling) falling fully/partly in the State of Maharashtra during 2009-14 and 2014-2024 is as under:-
|
Period
|
New track Commissioned
|
Average commissioning of new tracks
|
|
2009-14
|
292 Km
|
58.4 Km/year
|
|
2014-25
|
2,292 Km
|
208.36 Km/year (more than 3 times)
|
Details of some of the recently completed projects falling fully/partly in Maharashtra are as under:
|
S.No.
|
Project
|
Cost
(₹ in crore)
|
|
1
|
Jabalpur-Gondia Gauge Conversion (300 Km)
|
2,005
|
|
2
|
Chhindwara-Nagpur Gauge Conversion (150 Km)
|
1,512
|
|
3
|
Panvel-Pen Doubling (35 Km)
|
263
|
|
4
|
Panvel-Roha Doubling (75 Km)
|
31
|
|
5
|
Pen-Roha Doubling (40 Km)
|
330
|
|
6
|
Udhna-Jalgaon Doubling (307 Km)
|
2,448
|
|
7
|
Mudkhed-Parbhani Doubling (81 Km)
|
673
|
|
8
|
Bhusawal-Jalgaon 3rd Line (24 Km)
|
325
|
|
9
|
Jalgaon-Bhusawal 4th line (24 Km)
|
261
|
|
10
|
Daund-Gulbarga Doubling (225 Km)
|
3,182
|
Some of the main projects falling fully/partly in the Maharashtra which have been taken up are as under:
|
S.No.
|
Name of the project
|
Cost (₹ In crore)
|
|
1
|
Ahmednagar-Beed-Parle Vaijnath New Line (261 Km.)
|
4,957
|
|
2
|
Baramati-Lonand New Line (64 Km.)
|
1,844
|
|
3
|
Wardha-Nanded New Line (284 Km.)
|
3,445
|
|
4
|
Dhule (Borvihir)-Nardana New Line (51 Km.)
|
1,171
|
|
5
|
Manmad-Indore New Line (309 Km.)
|
16,321
|
|
6
|
Wadsa-Gadchiroli New Line (52 Km.)
|
1,886
|
|
7
|
Jalna -Jalgaon New Line (174 Km.)
|
5,804
|
|
8
|
Pune-Miraj-Londa Doubling (466 Km.)
|
6,463
|
|
9
|
Daund-Manmad Doubling (236 Km.)
|
30,376
|
|
10
|
Mudkhed-Medchal & Mahbubnagar-Dhone section Doubling (417 Km.)
|
4,686
|
|
11
|
Hotgi-Kudgi-Gadag Doubling (284 Km.)
|
2,459
|
|
12
|
Kalyan-Kasara 3rd line (68 Km.)
|
1,433
|
|
13
|
Wardha-Nagpur 3rd line (76 Km.)
|
698
|
|
14
|
Wardha-Ballarshah 3rd line (132 Km.)
|
1,385
|
|
15
|
Itarsi-Nagpur 3rd line (280 Km.)
|
2,450
|
|
16
|
Manmad-Jalgaon 3rd line (160 Km.)
|
1,677
|
|
17
|
Kazipet-Ballarshah 3rd line (202 Km.)
|
3,183
|
|
18
|
Rajnandgaon-Nagpur 3rd line (228 Km.)
|
3,545
|
|
19
|
Wardha-Nagpur 4th line (79 Km.)
|
1,137
|
|
20
|
Jalgaon-Manmad 4th Line (160 Km)
|
2,574
|
|
21
|
Bhusawal-Khandwa 3rd & 4th Line (131 Km.)
|
3,285
|
During the last three years i.e FY 2022-23, 2023-24, 2024-25 and the current FY, 27 Multi-tracking project of total length 1991 Km., costing approx. 47,126 crore falling fully/ partly in the State of Maharashtra, have been sanctioned.
These multi-tracking projects will enhance line capacity, provide additional passenger and freight traffic, enable faster movement of goods and services, reduce operational bottlenecks, improve logistics efficiency, increase in direct and indirect employment opportunities for the people of the region, develop tourism industry and increase industrial activities in the region.
Further, during the last three years i.e. FY 2022-23, 2023-24, 2024-25 and the current FY, 94 surveys (26 New Line, 2 Gauge Conversion and 66 Doubling) of total length 7979 Km. falling fully/ partly in the State of Maharashtra have been sanctioned under PM Gati Shakti National Master Plan.
In Maharashtra, entire existing Broad Gauge (BG) network (5,938 Route Km.) has been electrified. All New Line projects are being sanctioned and constructed with electrification.
Union Minister of Railways, Information & Broadcasting and Electronics & Information Technology, Shri Ashwini Vaishnaw stated this in reply to an unstarred question by Shri Dhananjay Bhimrao Mahadik in the Rajya Sabha today.
Sriyanka Chatterjee/Priti Malandkar