Ministry of Tribal Affairs
azadi ka amrit mahotsav

EMRS IN BUNDWAN, PURULIA OF WEST BENGAL

Posted On: 07 AUG 2025 3:15PM by PIB Delhi

Replying to an un-starred question of Shri Jyotirmay Singh Mahato, the Union Minister of State for Tribal Affairs Shri Durgadas Uikey informed Lok Sabha today that the construction of the Eklavya Model Residential School (EMRS) in Bundwan was delayed due to the State Government’s delay in providing the required land, which was eventually allotted in March 2025. At the request of the State Government, the responsibility for construction has been entrusted to them. However, the work is yet to commence. As per guidelines, the maximum permissible period for construction is 18 months from the date of award of the work.

The ceiling cost for the construction of EMRS Bundwan is ₹37.80 crore. However, since no fund release request has been received from the State Government, no funds have been disbursed so far.

To ensure the timely completion of the EMRS Bundwan project, several steps have been taken by the National Education Society for Tribal Students (NESTS), an autonomous organization established to manage and implement the EMRS scheme in coordination with State EMRS Societies. In response to a request from the State Government, the construction work of EMRS Bundwan has been entrusted to them. NESTS has shared comprehensive construction guidelines, including standard drawings and designs, with the State Government. Additionally, to maintain quality standards, the State Government has been advised to engage a Third-Party Quality Assurance (TPQA) agency. Regular communication is being maintained with the State authorities to expedite the commencement of construction.

More than 20 communications were sent by NESTS and Ministry of Tribal Affairs regarding land allocations, to which the State Government responded on 22.03.2023, 14.03.2024, and 26.06.2024.

State Government vide its letters dated 14.03.2024 and 26.06.2024 requested NESTS to allow construction by State Government, though land was not provided by State Government. State Government provided land on 07.03.2025. Accordingly, formal sanction has been issued by NESTS vide letter dated 17.03.2025.

*****

RN/


(Release ID: 2153519)