Current status of various ongoing Railway projects in Bihar, Rajasthan, Gujarat and Maharashtra

Posted On: 08 AUG 2025 12:37PM by PIB Patna

The status of Railway Projects in the state of Bihar, Rajasthan, Gujarat and Maharashtra is as under:

Bihar:

Budget allocation in the recent years has increased significantly. Budget allocation for infrastructure projects and safety works, falling fully/partly in the State of Bihar is as under:-

Period

Outlay

2009-14

Rs. 1132 Cr./year

2025-26

Rs. 10,066 Cr. (Nearly 9 times)

 

The details of commissioning/ laying of new track falling fully/partly in the State of Bihar is as under:-

Period

New Track Commissioned

Average Commissioning of new tracks

2009-14

318 Km

63.6 Km

  2014-25

1899 Km

172.6 (More than 2.5 times)

As on 01.04.2025, 52 projects(31 New Lines, 01 Gauge Conversions and 20 Doubling), of a total length of 4,663 km, costing Rs.86,107 crore, falling fully/partly in Bihar, are sanctioned, out of which 1,014 km length has been commissioned and an expenditure of Rs.29,353 crore has been incurred upto March’ 2025. The summary is as under:-

Category

No of sanctioned Projects

Total Length

NL/GC/DL

(in Km)

Length Commissioned till Mar'25
(in Km)

Total Exp upto Mar'25

( in Cr)

New Lines

31

2691

516

16814

Gauge Conversion

01

69

52

544

Doubling/Multi-tracking

20

1904

446

11995

Total

52

4663

1014

29353

Details of some of the recently completed projects falling fully/partly in Bihar are as under:-

Sl No

Project

Cost

(In Crores of Rs)

1

Munger Bridge (19 km)

2,774

2

Kosi Bridge (22 Km)

516

3

Patna Bridge  (40 Km)

3,555

4

Hajipur-Bachwara Doubling (72 km)

930

5

Kiul-Gaya Doubling (123 km)

1,200

6

Karota Patner-Mankatha - Surface triangle (8 km)

129

7

Rampurhat-Mandarhill New Line and Rampurhat-Murarai- 3rd line (160 km)

1,500

8

Jaynagar-Darbhanga-Narkatiaganj and Narkatiaganj-Bhikhna Tori Gauge Conversion (295 Km) 

1,193

9

Sakri-Laukaha Bazar-Nirmali & Saharsa-Forbesganj Gauge Conversion (206 Km)

2,113

10

Bakhtiyarpur Flyover (4 Km)

402

11

Katareah-Kursela Patch Doubling incl. bridge on river Kosi (7 km)

222

12

Araria-Galgalia New Line (111 Km)

4, 415

13

Kiul-Tilaiya Railway Electrification (87 kms)

105

14

Valmikinagar-Sugauli-Muzaffarpur and Sugauli-Raxaul Railway Electrification (240 km)

351

The above projects include three important bridges across Ganga and Kosi rivers viz Munger bridge, Patna Bridge and Kosi bridge. These are mega bridges with longer spans requiring expertise of high nature. Therefore, IITs/NITs were engaged for checking the designs and methodology of construction of these bridges.

Though these Bridges were sanctioned long before 2014 but substantial progress in the construction of these bridges could be achieved only after 2014. Proper planning, adoption of efficient execution methodologies and availability of sufficient funds were ensured for expediting these projects in Bihar.

Further, some of the main projects falling fully/partly in Bihar which have been taken up are as under:-

S No.

Project

Cost

(In Crores of Rs)

1

Sitamarhi-Sheohar New Line (28 Km)

567

2

Sakri-Hasanpur New Line (76 Km)

735

3

Khagaria-Kusheshwarsthan New Line (42 Km)

1511

4

Neora-Daniawan–Biharsharif - Barbigha-Shekhpura New Line (166 Km)

2200

5

Koderma-Tilaiya New Line (65 Km)

1626

6

Hajipur-Sagauli New Line (151 Km)

2087

7

Araria-Supaul New Line (96 Km)

1605

8

Vikramshila-Katareah New Line with Bridge over River Ganga(26 Km)

2090

9

Pirpainti-Jasidih New Line (97 Km) excluding Hansdiha-Godda New Line (30 Km)

2140

10

Sonnagar – Patratu multitracking (291 Km)

 

5148

11

Samastipur – Darbhanga Doubling (38 Km)

 

624

12

Rampur Dumra - Tal-Rajendra Pul-Additional bridge and doubling (14 Km)

 

1677

13

Sagauli-Valmiknagar Doubling (110 Km)

 

1280

14

Muzaffarpur-Sagauli Doubling (101 Km)

1465

15

Barauni- Bachwara 3rd & 4th line  (32 Km)

124

Railway infrastructural Projects in the State of Bihar are covered by East Central Railway (ECR), Northeast Frontier Railway (NFR), Eastern Railway (ER), North Eastern Railway (NER) Zone of Indian Railways. Zonal Railway wise details of Railway projects are made available in public domain on Indian Railway’s website.

During last three years (i.e. 2022-2023, 2023-24, 2024-25 and current Financial Year i.e. 2025-26), total 77 Nos. of Surveys (13 New Line, 64 Doubling) falling fully/partly in the State of Bihar having a total length of 3,991 Km have been sanctioned. Some of the important surveys that have been taken up are as under:-

S No.

Project

Length

(Km)

1

Deen Dayal Upadhyay-Kiul 3rd & 4th Line

390

2

Chhapra-Katihar 3rd & 4th Line

450

3

Bhagalpur-Jamalpur 3rd Line

53

4

Nawada-Pawapuri New Line

33

5

Bihta-Aurangabad New Line

120

6

Gaya-Rafiganj-Daltonganj New Line

137

7

Bakhtiyarpur-Tilaiya doubling

104

8

Rampurhat-Dumka-Bhagalpur doubling

177

9

Laheriyasarai-Jamalpur-Saharsa New Line

96

10

Muzaffarpur-Darbhanga New Line

96

11

Darbhanga - Sakri Doubling

21

12

Mansi – Saharsa Doubling

45

 

Rajasthan:

Budget allocation in the recent years has increased significantly. Budget allocation for infrastructure projects and safety works, falling fully/partly in the State of Rajasthan is as under:-

Period

 Outlay

2009-14

₹682 crore/year

2025-26

₹9,960 crore (Nearly 15 times)

The details of commissioning/laying of new track falling fully/partly in the State of Rajasthan during 2009-14 and 2014-25 is as under:-

Period

New Track Commissioned

Average commissioning of new tracks

2009-14

798 Km

159.60 Km/year

2014-25

3,815 Km

346.82 Km/year (More than 2 times)

As on 01.04.2025, 28 Railway projects (13 New Lines, 05 Gauge Conversion and 10 Doubling), of total length of 3,409 Km costing ₹43,918 crore falling fully/partly in the State of Rajasthan including Udaipur, Salumbar and Pratapgarh districts are at various stages of planning and implementation, out of which 1,238 Km length has been commissioned and an expenditure of ₹18,955 crore has been incurred upto March 2025. The status of work is summarized as under:-

Plan Head

No. of projects

Total Length
 (in Km)

Length Commissioned

 (in Km)

Expenditure upto March 2024
(
₹ in Cr)

New Lines

13

981

196

5769

Gauge Conversion

5

1252

788

6829

Doubling/

Multitracking

10

1176

254

6357

Total

28

3,409

1,238

18,955

Details of some of the recently completed projects falling fully/partly in the State of Rajasthan are as under:-

S.No.

Name of Project

Latest Cost

(₹ in crore)

  1.  

Bangurgram-Ras New Line (28 km)

175

  1.  

ThaiyatHamira-Sonu New Line (58 Km)

350

  1.  

Suratpura- Sriganganagar Gauge Conversion (241 Km)

896

  1.  

Sadalpur-Bikaner & Ratangarh-Degana Gauge Conversion (438 Km)

886

  1.  

Jaipur-Ringus-Sikar-Churu & Sikar-Loharu Gauge Conversion (320 Km)

1105

  1.  

Bhagat ki Kothi-Luni  Doubling (28 Km)

128

  1.  

Rani-Keshav Ganj Doubling (59 Km)

290

  1.  

Guriya-Marwar & Karjoda-Palanpur Doubling (49 Km)

251

  1.  

Rani-Marwar Doubling (52 Km)

346

  1.  

Abu Road-Swaroop Ganj Doubling (26 Km)

195

  1.  

Abu Rd-Sarotra Rd Doubling (23 Km)

152

  1.  

Alwar-Bandikui Doubling (60 Km)

450

  1.  

Ajmer-Bangurgram Doubling (48 Km)

375

  1.  

Bangurgram-Guriya Patch Doubling (47 Km)

395

  1.  

Degana-Rai ka Bagh Doubling (146 Km)

809

  1.  

Bina-Kota Doubling (282 Km)

2476

  1.  

Nimach-Chittaurgarh Doubling (56 Km)

560

  1.  

Dausa-Gangapur City Doubling (93 Km)

950

  1.  

Phulera-Degana Doubling (108 Km)

702

  1.  

Churu-Ratangarh Doubling (43 Km)

423

Some of the main projects falling fully/partly in the State of Rajasthan which have been taken up are as under:-

S.No.

Name of Project

Cost

(₹ in crore)

  1.  

Pushkar-Merta New Line (51 Km)

800

  1.  

Taranga Hill-Abu Road New Line (116 Km)

2798

  1.  

Ramganjmandi-Bhopal New Line (277 Km)

5073

  1.  

Nimach-Badi Sadri New Line (48 Km)

495

  1.  

Ringus-Khatu Shyam Ji New Line (17 Km)

254

  1.  

Merta city-Ras New Line & Bye Pass at Merta Road Station

(56 Km)

947

  1.  

Gwalior-Sheopurkalan Gauge Conversion with extension to Kota (284 Km)

2913

  1.  

Dholpur-Sirmuttra Gauge Conversion with extension to Gangapur City (145 Km)

747

  1.  

Mavli-Devgarh Madariya Gauge Conversion (83 Km)

969

  1.  

Mathura-Jhansi 3rd Line (274 Km)

5924

  1.  

Agra Fort-Bandikui Doubling (150 Km)

988

  1.  

Sawaimadhopur-Jaipur Doubling (131 Km)

1204

  1.  

Churu-Sadulpur & Luni-Bhildi Doubling (330 Km)

3554

  1.  

Ajmer-Chanderiya Doubling (178 Km)

1635

  1.  

Bye Pass line at Sawaimadhopur (14 Km)

304

  1.  

Rewari-Khatuwas Doubling (28 Km)

352

  1.  

Khatuwas-Narnaul Doubling (24 Km)

313

  1.  

Bye Pass line at Marwar (4 Km)

71

Railway infrastructure projects falling fully/partly in the State of Rajasthan are covered under North Western Railway, Northern Railway, North Central Railway, West Central Railway and Western Railway zones of Indian Railways. Zonal Railway wise details of Railway projects including cost, expenditure and outlay are made available in public domain on Indian Railway’s website.

Survey of total 55 projects (23 new line and 32 doubling) of total length 5,497 Km falling fully/partly in the State of Rajasthan have been sanctioned during last three years (2022-23, 2023-24, 2024-25 and current Financial Year 2025-26).

Some important sanctioned surveys falling fully/partly in the State of Rajasthan for improving connectivity are as under:-

S.No.

Name of Project

Length

(In Km)

  1.  

Anupgarh-Bikaner New Line & Spur line from Rojhri to Khajuwala

185

  1.  

Jaisalmer-Bhabhar/Bhildi New Line

380

  1.  

Khajuwala-Jaisalmer New Line

260

  1.  

Ringus-Loharu Doubling

172

Gujarat:

Budget allocation in the recent years has increased significantly. Budget allocation for infrastructure projects and safety works, falling fully/partly in the State of Gujarat is as under:-

 

Period

Outlay

2009-14

Rs. 589 crore/year

2025-26

Rs. 17,155 crore (More than 29 times)

The details of commissioning / laying of  new track, falling fully/partly in the State of Gujarat during 2009-14 and 2014-25, is as under:-

Period

New Track Commissioned

Average Commissioning of new tracks

2009-14

660 Km

132 Km/year

2014-25

2764 Km

251 Km/yr (Nearly 2 times)

As on 01.04.2025, 36 projects (6 New Lines, 17 Gauge Conversion and 13 Doubling), of a total length of 2564 Km, costing Rs.30,275 crore, falling fully/partly in the State of Gujarat, are sanctioned, out of which 863 Km length has been commissioned and an expenditure of Rs.12,865 crore has been incurred upto March 2025. The summary is as under:-

               Category

No. of sanctioned projects

Total length

 (Km)

Length commissioned till Mar'25 (Km)

Total Expenditure upto Mar'25 (Cr.)

New Lines

6

532

105

5494

Gauge Conversion

17

1379

718

6213

Doubling / Multitracking

13

653

40

1158

TOTAL

36

2564

863

12865

 

Details of some of the recently completed projects, falling fully/partly in the State of Gujarat, are as under:-

 

S.No.

Name of Project

Latest Cost (Cr.)

  1.  

Bhildi-Viramgam Gauge Conversion (156 Km)

312

  1.  

Dabhoi-Chandod with extention up to Kevadiya Gauge Conversion (50 Km)

1018

  1.  

Ahmedabad-Botad Gauge Conversion (170 Km)

1810

  1.  

Dhasa-Jetalsar Gauge Conversion (104 Km)

1024

  1.  

Ahmedabad-Mahesana Gauge Conversion (69 Km)

874

  1.  

Katosan Road-Chanasma Gauge Conversion (38 Km)

484

  1.  

Kalol-Kadi-Katosan Gauge Conversion (37 Km)

347

  1.  

Viramgram-Surendranagar Doubling (65 Km)

382

  1.  

Udhna-Jalgaon Doubling (307 Km)

2448

  1.  

Guriya-Marwar & Karjoda-Palanpur Doubling (49 Km)

251

  1.  

Abu Road to Sarotra Road Doubling (24 Km)

152

  1.  

Sarotra Road – Karjoda Doubling (24 Km)

220

  1.  

Viramgam-Samakhiali Doubling (182 Km)

1492

  1.  

Palanpur- Samakhiali Doubling (247 Km)

2538

  1.  

Mahesana-Palanpur Doubling (65 Km)

537

  1.  

Surendranagar-Rajkot Doubling (116 Km)

1425

  1.  

Anand-Godhara Doubling (79 Km)

692

  1.  

Vatva-Ahmedabad 3rd line with Automatic Signaling (8 km)

61

Some of the main projects, falling fully/partly in the State of Gujarat, which have been taken up, are as under:-

S. No

Project

Cost (Cr.)

  1.  

Naliya-Jakhau Port New Line (25 Km)

410

  1.  

Miyagam-Karjan-Choranda-Malsar Gauge Conversion (37 Km)

450

  1.  

Jambusar-Kavi Gauge Conversion (26 Km)

318

  1.  

Kosamba-Umarpada Gauge Conversion (70 Km)

468

  1.  

Khijadiya-Amreli  Gauge Conversion (17 Km)

178

  1.  

Gandhidham(GIM)- Adipur(AI) Quadrupling (11 Km)

152

  1.  

Barejadi-Nandej (Geratpur)- Sanand 4th Line (38 Km)

962

  1.  

Samakhiali and Gandhidham Quadrupling (53 Km)

1430

  1.  

Vishvamitri-Dabhoi Doubling (33 Km)

394

  1.  

Luni-Samdari-Bhildi Doubling (272 Km)

3086

  1.  

Sabarmati D Cabin- Sarkhej Doubling (21 Km)

323

Western Dedicated Freight Corridor (DFC) also passes through Gujarat. About 565 route km of Western DFC is situated in Gujarat, which is about 37% of overall route length of Western DFC. Full project length falling in the State of Gujarat has been commissioned.

The Mumbai-Ahmedabad High Speed Rail (MAHSR) Project (508 Km) is under execution with technical and financial assistance from Government of Japan. Construction works on the flagship high speed bullet train project have gathered momentum in Gujarat. Now, 100% land acquisition has been completed. Construction of viaduct for 352 Km (Foundation & Pier) section of this project falling in the State of Gujarat has been completed. Also, 329 Km Girder Casting and 309 Km Girder Launching have been completed.

Railway infrastructure projects, falling fully/partly in the State of Gujarat, are covered by Western Railway and North Western Railway zones of Indian Railways. Zonal Railway wise details of Railway projects are made available in public domain on Indian Railway’s website.

During last 3 years (2022-23, 2023-24, 2024-25) and current FY, 58 surveys of a total length of 6,321 Km falling fully/partly in the State of Gujarat, have been sanctioned. Some important surveys are as under:-

SN

                               Name of project

Length (Km)

1

Ratlam – Vadodara 3rd & 4th Line

259

2

Viramgam-Kanalus Quadrupling

293

3

Kanalus-Okha doubling

141

Maharashtra:

Budget allocation in the recent years has increased significantly. Budget allocation for Infrastructure projects and safety works, falling fully/ partly in the State of Maharashtra is as under:-

Period

Outlay

2009-14

₹ 1,171 crore/year

2025-26

₹ 23,778 crore (More than 20 times)

Commissioning of sections (New Line, Gauge Conversion and Doubling) falling fully/partly in the State of Maharashtra during 2009-14 and 2014-2024 is as under:-

Period

New track Commissioned

Average commissioning of new tracks

2009-14

292 Km

58.4 Km/year

2014-25

2,292 Km

208.36 Km/year (more than 3 times)

As on 01.04.2025, 38 projects (11  New Lines, 02 Gauge Conversion and 25 Doubling), of a total length of 5,098 km, costing ₹ 89,780 crore, falling fully/partly in Maharashtra including Amravati district, are sanctioned, out of which 2,360 km length has been commissioned and an expenditure of  ₹39,407 crore has been incurred upto March’ 2025. The summary is as under:-

Category

No of sanctioned Projects

Total Length

NL/GC/DL

(in Km)

Length Commissioned till Mar'25
(in Km)

Total Exp upto Mar'25

(₹ in Cr)

New Lines

11

1,355

234

10,504

Gauge Conversion

02

609

334

4,286

Doubling / Multitracking

25

3,134

1,792

24,617

Total

38

5,098

2,360

39,407

Details of some of the recently completed projects falling fully/partly in Maharashtra are as under:-

S.No.

Project

Cost

(₹ in crore)

1

Jabalpur-Gondia Gauge Conversion (300 Km)

2005

2

Chhindwara-Nagpur Gauge Conversion (150 Km)

1512

3

Panvel-Pen Doubling (35 Km)

263

4

Panvel-Roha Doubling (75 Km)

31

5

Pen-Roha Doubling (40 Km)

330

6

Udhna-Jalgaon Doubling (307 Km)

2448

7

Mudkhed-Parbhani Doubling (81 Km)

673

8

Bhusawal – Jalgaon 3rd Line (24 Km)

325

9

Jalgaon-Bhusawal 4th line (24 Km)

261

10

Daund-Gulbarga Doubling (225 Km)

3182

Railways have taken up Bhusawal-Khandwa 3rd & 4th Line (131 Km) project costing ₹3,285 Cr. and a survey has been taken up for Murtizapur – Achalpur Gauge Conversion (77 Km) work falling fully/partly in the Amravati district of Maharashtra.

Some of the main projects falling fully/partly in the Maharashtra which have been taken up are as under:-

S.No.

Name of the project

Cost (₹ In crore)

1

Ahmednagar-Beed-Parle Vaijnath New Line (261 Km.)

4,957

2

Baramati-Lonand New Line (64 Km.)

1,844

3

Wardha-Nanded New Line (284 Km.)

3,445

4

Dhule (Borvihir)-Nardana New Line (51  Km.)

1,171

5

Manmad-Indore New Line (309 Km.)

16,321

6

Wadsa-Gadchiroli New Line  (52 Km)

1,886

7

Jalna -Jalgaon New Line (174 Km.)

5,804

8

Pune-Miraj-Londa  Doubling (466 Km.)

6,463

9

Daund Manmad  Doubling (236 Km.)

30,376

10

Mudkhed - Medchal & Mahbubnagar - Dhone section Doubling (417 Km.)

4,686

11

Hotgi-Kudgi-Gadag Doubling  (284 Km.)

2,459

12

 Kalyan-Kasara - 3rd line (68 Km.)

1,433

13

Wardha -Nagpur 3rd line (76 Km.)

698

14

Wardha-Ballarshah 3rd line (132 Km.)

1,385

15

Itarsi- Nagpur 3rd line (280 Km.)

2,450

16

Manmad Jalgaon 3rd line (160 Km.)

1,677

17

Kazipet -Ballarshah - 3rd line (202 Km.)

3,183

18

Rajnandgaon-Nagpur 3rd line (228 Km.)

3,545

19

Wardha-Nagpur 4th line (79 Km.)

1,137

20

Jalgaon-Manmad 4th Line (160 Km)

2,574

These Multi- tracking projects will enhance line capacity, provide additional passenger and freight traffic, enable faster movement of goods and services, reduce operational bottlenecks, improve logistics efficiency, increase in direct and indirect employment opportunities for the people of the region, reduces operational bottlenecks, develop tourism industry and increase industrial activities in the region.

Further, Construction works on the flagship High speed bullet train project have gathered momentum in Maharashtra. Now 100% land acquisition has been completed. Works of bridges, aqueducts etc. have been taken up.

Western DFC also passes through Maharashtra. About 178 route Km of western DFC is situated in Maharashtra which is about 12% of overall route length of western DFC. 76 Km of this project from New Gholvad to New Vaitarna in Maharashtra has already been commissioned. Balance works have been taken up. Connectivity of WDFC to JNPT will boost the capacity to handle cargo and container traffic from port to Delhi NCR.

Railway infrastructure projects falling fully/partly in the State of Maharashtra are covered under Central Railway, South Central Railway, South East Central Railway, South Western Railway and Western Railway Zones of Indian Railways. Zonal Railway wise details of Railway projects are made available in public domain on Indian Railway’s website.

During the last three years i.e FY 2022-23, 2023-24, 2024-25 and the current FY, 27 Multi-tracking  project of total length 1991 Km., costing approx. 47,126 crore falling fully/ Partly in the State of Maharashtra, have been sanctioned. 

This information was given by UNION MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND ELECTRONICS & INFORMATION TECHNOLOGY SHRI ASHWINI VAISHNAW in a written reply to a question in Rajya Sabha today.

*****