Cabinet approves construction of 4-lane Marakkanam – Puducherry (NH-332A) in Tamilnadu on Hybrid Annuity Mode with an outlay of Rs.2157 crore

Posted On: 08 AUG 2025 4:08PM by PIB Delhi

The Cabinet Committee on Economic Affairs chaired by the Prime Minister has approved construction of 4-lane Marakkanam – Puducherry (46 km) in Tamilnadu. The project will be developed on Hybrid Annuity Mode (HAM) at a total capital cost of Rs.2,157 crore.

Currently, connectivity between Chennai, Puducherry Viluppuram & Nagapattinam is dependent on existing 2-lane National Highway 332A (NH-332A) and associated State Highways, which experience significant congestion due to high traffic volumes, especially in densely populated stretches and key towns along the corridor. To address these challenges, the project will upgrade approximately 46 km of NH-332A from Marakkanam to Puducherry to a 4-lane configuration. This will decongest the existing corridor, improve safety, and cater to the mobility needs of rapidly growing towns such as Chennai, Puducherry Viluppuram & Nagapattinam.

The project alignment integrates with 2 major National Highways (NH-32, NH-332) and two State Highways (SH-136, SH-203), providing seamless connectivity to key economic, social, and logistics nodes across Tamil Nadu. Additionally, the upgraded corridor will enhance multi-modal integration by connecting with two Railway Stations (Puducherry, Chinnababusamudram), two Airports (Chennai, Puducherry), and one Minor Port (Cuddalore) thereby facilitating faster movement of goods and passengers across the region.

Upon completion, the Marakkanam - Puducherry section will play a pivotal role in regional economic growth, strengthening connectivity between major religious and economic centers, boosting tourism to Puducherry, and opening new avenues for trade and industrial development. The project will also generate approximately 8 lakh person-days of direct and 10 lakh person-days of indirect employment, and will open new avenues of growth, development and prosperity in surrounding regions.

Map of Corridor

Appendix - I: Project Details

Feature

Details

Project Name

4-Lane Marakkanam – Puducherry Section (NH 332A)

Corridor

Chennai–Puducherry–Nagapattinam-Tuticorin-Kanyakumari Economic Corridor (East Coast Road - ECR)

Length (km)

46.047

Total Civil Cost (Rs Cr.)

1,118

Land Acquisition Cost (Rs Cr.)

442

Total Capital Cost (Rs Cr.)

2,157

Mode

Hybrid Annuity Mode (HAM)

Bypasses

Puducherry Bypass (Greenfield Access Controlled) – 34.7 km

Major Roads Connected

National Highways – NH-32, NH-332

State Highways – SH-136, SH-203

Economic / Social / Transport Nodes Connected

Airports: Chennai, Puducherry

Railway Stations: Puducherry, Chinnababusamudram

Minor Port: Cuddalore

Economic Nodes: Mega Food Park, Pharma Cluster, Fishing Cluster

Social Nodes: Arulmigu Manakula Temple, Paradise Beach

Major Cities / Towns Connected

Chennai, Marakkanam, Puducherry

Employment Generation Potential

8 lakh Man-Days (direct) & 10 lakh Man-Days (indirect)

Annual Average Daily Traffic (AADT) in FY-25

Estimated at 17,800 Passenger Car Units (PCU)

 

****

MJPS/BM