Budget allocation for Infrastructure projects and safety works, falling fully/partly in the State of Bihar is as under:
|
Period
|
Outlay
|
|
2009-14
|
₹1,132 Cr./year
|
|
2025-26
|
₹10,066 Cr. (Nearly 9 times)
|
The details of commissioning/laying of new track falling fully/partly in the State of Bihar during 2009-14 and 2014-25 is as under :-
|
Period
|
New Track Commissioned
|
Average Commissioning of new tracks
|
|
2009-14
|
318 Km
|
63.6 Km/year
|
|
2014-25
|
1,899 Km
|
172.6 Km/year (More than 2.5 times)
|
As on 01.04.2025, 52 projects (31 New Lines, 01 Gauge Conversions and 20 Doubling), of a total length of 4,663 km, costing ₹86,107 crore, falling fully/partly in Bihar, are sanctioned, out of which 1,014 km length has been commissioned and an expenditure of ₹29,353 crore has been incurred upto March’ 2025. The summary is as under:-
|
Category
|
No of sanctioned Projects
|
Total Length
NL/GC/DL
(in Km)
|
Length Commissioned till Mar'25
(in Km)
|
Total Exp upto Mar'25
(₹ in Cr)
|
|
New Lines
|
31
|
2,691
|
516
|
16,814
|
|
Gauge Conversion
|
1
|
69
|
52
|
544
|
|
Doubling/Multi-tracking
|
20
|
1,904
|
446
|
11,995
|
|
Total
|
52
|
4,663
|
1,014
|
29,353
|
Details of some of the recently completed projects falling fully/partly in Bihar are as under:-
|
SN.
|
Project
|
Length (Km)
|
Cost
(In Crores of Rs)
|
|
1
|
Patna rail cum road Bridge
|
28
|
3,210
|
|
2
|
Munger rail cum road Bridge
|
15
|
3,040
|
|
3
|
Kosi Bridge
|
22
|
863
|
|
4
|
Daniawan-Biharsharif New Line
|
38
|
354
|
|
5
|
Chandan-Banka New Line
|
40
|
496
|
|
6
|
Rampurhat-Mandarhill New Line
|
130
|
908
|
|
7
|
Maharajganj-Masrakh New Line
|
35
|
412
|
|
8
|
Rajgir-Tilaiya & Natesar-lslampur New Line
|
67
|
726
|
|
9
|
Mansi-Saharsa-Purnia Gauge Conversion
|
141
|
752
|
|
10
|
Jaynagar-Narkatiaganj Gauge Conversion
|
260
|
967
|
|
11
|
Kaptanganj-Chhapra Gauge Conversion
|
234
|
819
|
|
12
|
Sakri-Nirmali & Saharasa-Forbesganj Gauge Conversion
|
206
|
2,113
|
|
13
|
Mansi-Saharsa, Saharsa-Purnia & Banmakhi- Bihariganj Gauge Conversion
|
169
|
752
|
|
14
|
Sahibganj-Pirpainti Doubling
|
23
|
129
|
|
15
|
Maheshkunt-Thanabihpur Doubling
|
32
|
115
|
|
16
|
Hajipur-Ramdayalu Nagar Doubling
|
48
|
367
|
|
17
|
Pirpainti-Bhagalpur Doubling
|
51
|
493
|
|
18
|
Bakhtiyarpur-Barh Doubling
|
19
|
237
|
|
19
|
Kiul-Gaya Doubling
|
124
|
2,462
|
|
20
|
Hajipur-Bachwara Doubling
|
72
|
930
|
|
21
|
Darbhanga bypass
|
9
|
253
|
|
22
|
Araria-Galgalia (Thakurganj) New Line
|
110
|
2,132
|
|
23
|
Saraigarh Byepass Line
|
5
|
79
|
|
24
|
Chhapra-Chhapra Kacheri 3rd Line
|
3
|
33
|
Some of the projects falling fully/partly in the State of Bihar which have been taken up are as under:
|
SN.
|
Project
|
Length (Km)
|
Cost
(Rs. in Cr.)
|
|
1
|
Sakri-Hasanpur new line
|
76
|
735
|
|
2
|
Khagaria-Kusheshwarsthan New line
|
42
|
1,511
|
|
3
|
Fatuha-lslampur new line
|
167
|
2,882
|
|
4
|
Koderma-Tilaiya new line
|
65
|
1,980
|
|
5
|
Hajipur-Sagauli new line
|
151
|
2,702
|
|
6
|
Araria-Supaul new line
|
96
|
1,925
|
|
7
|
Kursela-Bihariganj new line
|
58
|
194
|
|
8
|
Bikramshila-Katareah new line
|
26
|
2,171
|
|
9
|
Jhajha-Batia new line
|
20
|
588
|
|
10
|
Pirpainti-Jassidih new line
|
97
|
2,611
|
|
11
|
Chhitauni-Tumkuhi Road new line
|
59
|
1,731
|
|
12
|
Jalalgarh-Kishanganj new line
|
51
|
360
|
|
13
|
Jogbani-Biratnagar (Nepal) new line
|
19
|
402
|
|
14
|
Darbhanga-Kusheshwarasthan new line
|
70
|
367
|
|
15
|
Motihari-Sitamarhi new line
|
77
|
1,007
|
|
16
|
Sitamarhi-Nirmali new line
|
189
|
2,833
|
|
17
|
Nawada-Laxmipur new line
|
137
|
3,121
|
|
18
|
Ara-Bhabua Road new line
|
150
|
2,397
|
|
19
|
Gaya-Daltonganj new line
|
137
|
2,861
|
|
20
|
Muzaffarpur-Darbhanga new line
|
69
|
282
|
|
21
|
Muzaffarpur-Janakpur Road new line
|
67
|
228
|
|
22
|
Dehri on Sone-Banjari new line
|
35
|
111
|
|
23
|
Chhapra-Muzzafarpur new line
|
78
|
1,894
|
|
24
|
Bihta-Aurangabad new line
|
120
|
2,995
|
|
25
|
Gaya-Chatra and Gaya-Natesar new line
|
135
|
4,543
|
|
26
|
Deogarh-Sultanganj new line incl.Banka-Barahat and Banka-Bhitiah Road
|
154
|
665
|
|
27
|
Sultanganj-Katuria new line
|
77
|
291
|
|
28
|
Bariarpur-Mananpur new line
|
68
|
251
|
|
29
|
Hathua-Bhatni new line
|
80
|
318
|
|
30
|
Aurangabad Terminal-Anugrah Narayan Road new line
|
13
|
441
|
|
31
|
Nawadah-Pawapuri New line
|
25
|
492
|
|
32
|
Jaynagar-Bijalpura Gauge conversion
|
69
|
790
|
|
33
|
Dhanbad-Sonnagar 3rd line
|
291
|
7,906
|
|
34
|
Samastipur-Darbhanga Doubling
|
38
|
826
|
|
35
|
Rampur Dumra-Tal-Rajendra Pul-Additional bridge and Doubling
|
14
|
2,535
|
|
36
|
Sagauli-Valmikinagar Doubling
|
110
|
1,456
|
|
37
|
Gaya Bye pass for Manpur
|
2
|
30
|
|
38
|
Muzaffarpur-Sugauli Doubling
|
101
|
1,586
|
|
39
|
Barauni-Bachwara 3rd & 4th line
|
32
|
486
|
|
40
|
Sonenagar bye pass(Chiralapothu to Bagha
Bishunpur)
|
10
|
224
|
|
41
|
Narkatiaganj-Darbhanga & Sitamarhi-Muzaffarpur
Doubling
|
256
|
4,080
|
|
42
|
Chhapra-Ballia Patch Doubling
|
65
|
1,046
|
|
43
|
Gorakhpur-Valmikinagar Doubling
|
96
|
1,121
|
|
44
|
Katihar-Kumedpur and Katihar-Mukuria Doubling
|
65
|
943
|
|
45
|
Bhadaura Station and Karma Station Surface Triangle Line
|
11
|
200
|
|
46
|
ROR at Sasaram connecting GC to Ara-Sasaram Line
|
9
|
470
|
|
47
|
Ara Bye pass Line to be connected from Jagjivan Halt to existing ARA-Sasaram line through link cabin (Y-Connectivity at Ara)
|
3
|
119
|
|
48
|
Son Nagar-Andal Multitracking
|
749
|
12,334
|
|
49
|
Bulb line at Nabinagar (Ankorha)
|
17
|
612
|
|
50
|
Punarakh- Barh-Bhaktiyarpur New 4th line & balance 3rd line
|
28
|
422
|
|
51
|
Sanjaygram to Dhachna By Pass line
|
2
|
34
|
|
52
|
Aluabari Road-Thakurganj Doubling
|
20
|
327
|
|
53
|
Aluabari Road-New Jalpaiguri 3rd & 4th Line
|
57
|
1,630
|
|
54
|
Bhagalpur-Jamalpur 3rd Line
|
53
|
1,156
|
|
55
|
Bhagalpur-Dumka-Rampurh at Doubling
|
177
|
3,169
|
|
56
|
Bakhtiyarpur-Rajgir-Tilaiya Doubling
|
104
|
2,192
|
|
57
|
Bakthiyarpur-Fatuha 3rd and 4th line
|
24
|
931
|
During last three years (i.e. 2022-2023, 2023-24, 2024-25 and current financial year 2025-26), total 92 Nos. of Surveys (16 New Line, 76 Doubling) falling fully/partly in the State of Bihar having a total length of 4,530 Km have been sanctioned.
Zonal Railway wise details of Railway projects are made available in public domain on Indian Railway’s website.
Gopalganj is already an existing station on Hathua-Thawe-Masrakh section and is well connected to rest of Indian Railway network.
Sanction of any railway project depend upon many parameters/factors which include the following:
-
Anticipated traffic projections and Remunerativeness of the proposed route
-
First and last mile connectivity provided by the project
-
Connection of missing links and providing additional route
-
Augmentation of congested/saturated lines
-
Demands raised by State Governments/Central Ministries/Public representatives,
-
Railway’s own operational requirements
-
Socio-economic considerations
-
Overall availability of funds
Completion of Railway project/s depends on various factors which include the following:
-
Land acquisition by State Government
-
Forest clearance
-
Shifting of infringing utilities
-
Statutory clearances from various authorities
-
Geological and topographical conditions of area
-
Law and order situation in the area of project site
-
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****
(This statement was given by Minister for Railways, Information & Broadcasting and Electronics & Information Technology Shri Ashwini Vaishnaw in a written reply to a question in Lok Sabha today.)