Government Notifies India’s First Chip Fabrication Plant at SEZ Dholera

Posted On: 16 APR 2026 4:53PM by PIB Delhi

Government has notified that an SEZ to be set up by M/s. Tata Semiconductor Manufacturing Private Limited exclusively for Electronic Hardware and Software including IT/ITES at Dholera, Gujarat. The SEZ will be spread over 66.166 hectares of land and is poised to provide employment to 21000 persons. The SEZ is designed to support electronic hardware, software, and IT-enabled services, and includes enabling infrastructure and a dedicated approval mechanism to streamline operations and logistics.  This is India’s first chip fabrication plant.

Earlier, Government had taken several significant steps to strengthen India’s semiconductor and electronics manufacturing ecosystem through progressive reforms in the Special Economic Zones (SEZ) law and targeted approvals of sector-specific SEZs. In line with the Government’s focus, these reforms are aimed at promoting high-value, capital-intensive investments, fostering innovation, and enhancing ease of doing business on developing a globally competitive semiconductor ecosystem.

Key amendments to the SEZ Rules, 2006 were carried out through the notification dated 03.06.2025 to address the unique requirements of semiconductor and electronics manufacturing, including reduction in minimum land requirement from 50 hectares to 10 hectares, flexibility in encumbrance norms, inclusion of free-of-cost supplies in Net Foreign Exchange calculations, and permitting domestic sales in the Domestic Tariff Area (DTA) on payment of applicable duties.

 Following through on these reforms, the Board of Approval for SEZs has accorded approvals to major proposals of setting up of SEZs for semiconductor and electronics. Notably, Micron Semiconductor Technology India Pvt Ltd is establishing an SEZ for semiconductor Assembly, Testing, Marking and Packaging in Sanand, Gujarat, with an estimated investment of ₹13,000 crore, while Aequs Group is setting up an electronic component manufacturing SEZ in Dharwad, Karnataka. These projects are expected to catalyse the development of domestic value chains, generate high-skilled employment, and reduce import dependence. List of SEZs approved after the said regulatory easing, is as below:

 

Sl. No.

Name of the entity

Date of notification

Land Area

(in hectares)

Proposed

Investment

(in ₹ crore)

Proposed

Employment (direct/ indirect)

Type of Operation

1.

M/s Micron Semiconductor Technology India Pvt. Ltd

23rd June, 2025

 

37.64

13,000

20,786

Assembly, Testing, Marking and Packaging Unit

2.

M/s. Hubballi Durable Goods Cluster Private Limited

23rd June, 2025

 

11.549

100

4,360

Electronics Components Manufacturing and services

3.

M/s CG Semi Pvt. Ltd.

23rd September, 2025

 

11.541

2150

1,911

Outsourced Semiconductor Assembly and Testing for Semiconductor chips

4.

M/s Kaynes Semicon Pvt. Ltd.

26th September, 2025

18.44

681

2,020

Outsourced Semiconductor Assembly and Testing (OSAT) Unit

5.

M/s. Tata Semiconductor Manufacturing Private Limited

9th April, 2026

 

66.166

91,000

21,000

AI enabled Semiconductor Fabrication facility

 

These SEZs are envisaged to contribute to the gradual build-up of a robust, competitive, resilient, and future-ready semiconductor ecosystem. These initiatives, together with industry participation and policy support, are facilitating and paving a way for the creation of integrated manufacturing clusters, strengthening domestic capabilities, and positioning India as an emerging hub for semiconductor and electronics production.

***

Abhishek Dayal/Anushka Pandey


(Release ID: 2252649) Visitor Counter : 1130