|
Ministry of Railways
EXTENSION OF RAILWAY INFRASTRUCTURE AND NEW RAILWAY SERVICES IN BIHAR
Posted On:
24 JUL 2026 2:54PM by PIB Patna
Railway Budget: Budget allocation in the recent years has increased significantly. Budget allocation for infrastructure projects falling fully/partly in the Bihar is as under:-
|
Period
|
Outlay
|
|
2009-14
|
₹1,132 Cr./year
|
|
2026-27
|
₹10,379 Cr. (More than 9 times)
|
Track construction: The details of commissioning/laying of new track falling fully/partly in the State of Bihar is as under:-
|
Period
|
New Track Commissioned
|
Average Commissioning of new tracks
|
|
2009-14
|
318 Km
|
63.6 Km/year
|
|
2014-26
|
2,034 Km
|
169.5 Km/year (More than 2.5 times)
|
Projects sanctioned: As on 01.04.2026, 59 projects (32 New Lines, 01 Gauge Conversions and 26 Doubling), covering a total length of 5,067 km, costing ₹96,651 crore, falling fully/partly in Bihar are sanctioned. The summary is as under:-
|
Category
|
No of sanctioned Projects
|
Total Length
(in Km)
|
Length Commissioned till Mar'26
(in Km)
|
Total Exp upto Mar'26
(₹ in Cr)
|
|
New Lines
|
32
|
2,616
|
533
|
14,806
|
|
Gauge Conversion
|
1
|
69
|
52
|
544
|
|
Doubling/Multi-tracking
|
26
|
2,382
|
465
|
14,509
|
|
Total
|
59
|
5,067
|
1,050
|
29,860
|
Recently completed projects: Details of some of the recently completed projects falling fully/partly in Bihar are as under:-
|
SN.
|
Project
|
Cost
(In Crores of Rs)
|
|
1
|
Patna bridge (28 Km)
|
3,310
|
|
2
|
Munger rail cum road Bridge (15 Km)
|
3,040
|
|
3
|
Kosi Bridge (22 Km)
|
863
|
|
4
|
Daniawan-Biharsharif new line (38 Km)
|
354
|
|
5
|
Chandan-Banka new line (40 Km)
|
496
|
|
6
|
Rampurhat-Mandarhill new line (130 Km)
|
908
|
|
7
|
Maharajganj-Masrakh new line (35 Km)
|
412
|
|
8
|
Rajgir-Tilaiya & Natesar-lslampur new line (67 Km)
|
726
|
|
9
|
Jaynagar-Narkatiaganj gauge conversion (260 Km)
|
967
|
|
10
|
Kaptanganj-Chhapra gauge conversion (234 Km)
|
819
|
|
11
|
Sakri-Nirmali, Saharasa-Forbesganj gauge conversion (206 Km)
|
2,113
|
|
12
|
Mansi-Saharsa, Saharsa-Purnia, Banmakhi- Bihariganj gauge conversion (169 Km)
|
752
|
|
13
|
Sahibganj-Pirpainti doubling (23 Km)
|
129
|
|
14
|
Maheshkunt-Thanabihpur doubling (32 Km)
|
115
|
|
15
|
Hajipur-Ramdayalu Nagar doubling (48 Km)
|
367
|
|
16
|
Pirpainti-Bhagalpur doubling (51 Km)
|
493
|
|
17
|
Kiul-Gaya doubling (124 Km)
|
2,462
|
|
18
|
Hajipur-Bachwara doubling (72 Km)
|
930
|
|
19
|
Araria-Galgalia (Thakurganj) new line (110 Km)
|
2,132
|
|
20
|
Samastipur-Darbhanga Doubling (38 Km)
|
874
|
Ongoing projects: Some of the projects falling fully/partly in the State of Bihar which have been taken up are as under:
|
SN.
|
Project
|
Cost (Rs. in Cr.)
|
|
1
|
Sakri-Hasanpur new line (76 Km)
|
802
|
|
2
|
Fatuha-lslampur new line (167 Km)
|
3,158
|
|
3
|
Koderma-Tilaiya new line (65 Km)
|
2,287
|
|
4
|
Hajipur-Sagauli new line (151 Km)
|
2,820
|
|
5
|
Araria-Supaul new line (96 Km)
|
2,170
|
|
6
|
Kursela-Bihariganj new line (58 Km)
|
194
|
|
7
|
Pirpainti-Jassidih new line (97 Km)
|
2,700
|
|
8
|
Chhitauni-Tumkuhi Road new line (59 Km)
|
1,881
|
|
9
|
Jalalgarh-Kishanganj new line (51 Km)
|
407
|
|
10
|
Sitamarhi-Nirmali new line (189 Km)
|
2,833
|
|
11
|
Bihta-Aurangabad new line (120 Km)
|
3,606
|
|
12
|
Gaya-Chatra and Gaya-Natesar new line (135 Km)
|
4,543
|
|
13
|
Sultanganj-Katuria new line (77 Km)
|
291
|
|
14
|
Jaynagar-Bijalpura Gauge conversion (69 Km)
|
900
|
|
15
|
Dhanbad-Sonnagar 3rd line (291 Km)
|
7,906
|
|
16
|
Sagauli-Valmikinagar Doubling (110 Km)
|
1,456
|
|
17
|
Muzaffarpur-Sugauli Doubling (101 Km)
|
1,745
|
|
18
|
Barauni-Bachwara 3rd & 4th line (32 Km)
|
486
|
|
19
|
Narkatiaganj-Darbhanga, Sitamarhi-Muzaffarpur doubling (256 Km)
|
4,080
|
|
20
|
Chhapra-Ballia Patch Doubling (65 Km)
|
1,046
|
|
21
|
Katihar-Kumedpur and Katihar-Mukuria Doubling
(65 Km)
|
943
|
|
22
|
Son Nagar-Andal Multitracking (749 Km)
|
12,334
|
|
23
|
Punarakh- Bhaktiyarpur New 4th line & balance 3rd line (28 Km)
|
422
|
|
24
|
Aluabari Road-Thakurganj Doubling (20 Km)
|
327
|
|
25
|
Bhagalpur-Jamalpur 3rd line (53 Km)
|
1,156
|
|
26
|
Bhagalpur-Dumka-Rampurhat doubling (177 Km)
|
3,169
|
|
27
|
Bakhtiyarpur-Rajgir-Tilaiya doubling (104 Km)
|
2,192
|
|
28
|
Bakthiyarpur-Fatuha 3rd and 4th line (24 Km)
|
931
|
|
29
|
Punarakh-Kiul 3rd and 4th line (50 Km)
|
2,668
|
|
30
|
Kiul-Jhajha 3rd Line (54 Km)
|
962
|
|
31
|
Mansi-Saharsa doubling (44 Km)
|
499
|
Completion of Railway projects/s depends on various factors which include the following:
-
Land acquisition by State Government
-
Forest clearance
-
Shifting of infringing utilities
-
Statutory clearances from various authorities
-
Geological and topographical conditions of area
-
Law and order situation in the area of project site
-
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
Electrification :
Electrification of railway network on Indian Railways has been taken up in mission mode. So far, about 99.6% of Broad Gauge (BG) network has been electrified. The electrification in remaining network has been taken up. Electrification carried out during 2014-26 and before 2014 is as under:
|
Period
|
Route Kilometer
|
|
Before 2014 (about 60 years)
|
21,801
|
|
2014-26
|
48,072
|
In Bihar, entire existing BG network has been electrified. Further, all new line / multi-tracking projects are being sanctioned and constructed with electrification.
ROBs & RUBs:
Sanctioning of works of Road over Bridge (ROB)/Road under Bridge (RUB) in lieu of Level crossings (LCs) is a continuous and dynamic process of Indian Railway. Such works are prioritised and taken up on the basis of their impact on safety in train operations, mobility of trains & impact for road users and feasibility etc.
No. of ROBs/ RUBs constructed on Indian Railways during the period 2004-14 vis a vis 2014-26 (Upto May'2026) is as under:
|
Period
|
ROBS/ RUBS constructed
|
|
2004-14
|
4,148
|
|
2014-26 (Upto May'26)
|
14,451 (580 in the State of Bihar)
|
As on 01.06.2026, 4,993 Nos. ROBs/ RUBs works are sanctioned at a cost of approx. ₹1,17,492 Cr on Indian Railways including 328 Nos. ROBs/ RUBs works at a cost of approx. ₹12,250 Cr in the state of Bihar which are at various stages of planning and execution.
During 2023-26 (Upto May'26), 192 Nos. ROBs/ RUBs works were constructed in the state of Bihar and 201 Nos. ROBs/ RUBs works are sanctioned at a cost of approx. ₹7,032 Cr in the state of Bihar which are at various stages of planning and execution.
Completion & commissioning of ROB/RUB works depends on various factors like cooperation of State Governments in giving consent for closure of LC, fixing of approach alignment, approval of General Arrangement Drawing (GAD), land acquisition, removal of encroachment, shifting of infringing utilities, statutory clearances from various authorities, law and order situation in the area of project / work sites, duration of working season in a year for the particular project / area due to climatic conditions etc. All these factors affect the completion time of the projects / works.
Further, Railways have taken following measures to expedite the progress of work:
-
Joint survey with concerned State Govt./Road Owning Authority is done before finalizing the General Arrangement Drawing (GAD) to ensure smooth execution.
-
Periodic meetings of Railway & State Government officials are done to resolve various issues related to ROB/RUB works.
-
Standardization of superstructure and substructure drawings for various combinations of span, skewness and width of road on the Railway portion has been done to avoid delays during the design approval.
Station Redevelopment: Ministry of Railways has launched Amrit Bharat Station Scheme for redevelopment of stations with a long-term approach.
The scheme involves preparation of master plans and their implementation in phases to improve the stations of Indian Railways. The master planning, keeping in view the necessity of each station, includes:
-
Improvement of access to station and circulating areas
-
Integration of station with both sides of city
-
Improvement of station building
-
Improvement of waiting halls, toilets, sitting arrangement, water booths
-
Provision of wider foot over bridge/subway to commensurate with passenger traffic
-
Provision of lifts/escalators/ramps
-
Improvement of platform surface/ provision of platform shelter
-
Provision of kiosks for local products through schemes like 'One Station One Product'
-
Parking development
-
Amenities for Divyangjans
-
Better passenger information systems
-
Provision of air concourse, executive lounges, Multimodal integration, landscaping, etc.
The scheme also envisages sustainable and environment friendly solutions etc. as per necessity, phasing and feasibility and creation of city centre at the station in the long term.
So far, 1,340 stations have been identified for development under this scheme, out of which 98 stations are located in Bihar. The names of stations identified for development under Amrit Bharat Station Scheme in Bihar are as following:
|
State
|
No. of Stations
|
Name of Stations
|
|
Bihar
|
98
|
Anugraha Narayan Road, Ara, Arariya Court, Bakhtiyarpur, Banka, Banmankhi, Bapudham Motihari, Barahiya, Barauni, Barh, Barsoi Jn, Begusarai, Bettiah, Bhabua Road, Bhagalpur, Bhagwanpur, Bihar Sharif, Bihiya, Bikramganj, Buxar, Chakia, Chausa, Chhapra, Dalsingh Sarai, Darbhanga, Dauram Madhepura, Dehri On Sone, Dholi, Dighwara, Dumraon, Durgauti, Ekma, Fatuha, Gaya, Ghorasahan, Guraru, Hajipur Jn, Jamalpur Jn, Jamui, Janakpur Road, Jaynagar, Jehanabad, Jhanjharpur, Kahalgaon, Karhagola Road, Katihar Jn, Khagaria Jn, Kishanganj, Kudra, Labha, Laheria Sarai, Lakhminia, Luckeesarai Jn, Madhubani, Maheshkhunt, Mairwa, Mansi Jn, Masrakh, Mokama, Motipur, Munger (Monghyr), Muzaffarpur Jn, Nabinagar Road, Narkatiaganj Jn, Naugachia, Nawadah, Paharpur, Patliputra, Patna Jn, Piro, Pirpainti, Rafiganj, Raghunathpur., Rajendra Nagar Terminal (Patna), Rajgir, Ram Dayalu Nagar, Raxaul, Sabaur, Sagauli, Saharsa, Sahibpur Kamal, Sakri, Salauna, Salmari, Samastipur, Sasaram, Shahpur Patoree, Shivanarayanpur, Simri Bakhtiyarpur, Simultala, Sitamarhi, Siwan, Sonpur Jn., Sultanganj, Supaul, Taregna, Thakurganj, Thawe
|
Completed stations:
Development works at railway stations under Amrit Bharat Station Scheme in Bihar have been taken up at a good pace. Details of stations completed in Bihar are as under:
|
State
|
No. of Stations
|
Name of Stations
|
|
Bihar
|
08
|
Banmankhi, Dauram Madhepura, Kahalgaon, Pirpainti, Sabaur, Shivanarayanpur, Simultala, Thawe
|
The activities for development at other stations have also been taken up at good pace and progress of some of the stations is as given below:
-
Saharsa station: The works of new main entry station building, parking, improvement to circulating area, platform shelter, entrance gate and boundary wall have been completed. The work of 12 m wide foot over bridge has been taken up.
-
Salauna station: The works of new main entry station building, platform shelter, improvement of circulating area, entrance gate and boundary wall have been completed. The work of 12 m wide foot over bridge has been taken up.
-
Sonpur Junction station: The works of new atrium building, booking counter, improvement of station building, improvement of circulating area, parking and entrance porch have been completed. The work of 12 m wide foot over bridge has been taken up.
-
Anugraha Narayan Road station: The works of extension of platform no. 1/2 & 3/4, improvement of platform surface of platform no. 1/2 & 3/4 and new toilet block have been completed. The works of improvement of station building, improvement of circulating area, entry/exit gate, water booths, platform shelter and 6 m wide foot over bridge have been taken up.
-
Luckeesarai Junction station: The works of new main entry station building, extension of foot over bridge and improvement of circulating area have been completed. The work of lift for existing foot over bridge has been taken up.
Further, development/redevelopment/upgradation/modernisation of stations on Indian Railways is a continuous and ongoing process and works in this regard are undertaken as per requirement, subject to inter-se priority and availability of funds. Development / redevelopment/upgradation/modernisation of a station is carried out based on category of station/condition/traffic handled etc.
Development/Upgradation of railway stations is a complex in nature involving safety of passengers & trains and requires various statutory clearances such as tree cutting, heritage, fire clearance, airport clearance etc. These stations are in operation since long, so brownfield work challenges are being faced, such as shifting of utilities (involving water/sewage lines, optical fibre cables, gas pipelines, power/signal cables, etc.), infringements, operation of trains without hindering passenger movement, speed restrictions due to works carried out in close proximity of the tracks and near to high voltage power lines, etc. and these factors affect the progress of work and completion time.
Development/ upgradation/ modernisation of stations including under Amrit Bharat Station Scheme is generally funded under Plan Head-53 'Customer Amenities'. The details of allocation and expenditure under Plan Head-53 are maintained Zonal Railway- wise and not station-wise or state-wise. Bihar is covered under the jurisdiction of four railway zones, namely, Eastern Railway, East Central Railway, North Eastern Railway and Northeast Frontier Railway. For these zones, an allocation of ₹6,903 crore has been made for the last three financial years and the current financial year, out of which an expenditure (up to June, 2026) of ₹6,021 crore has been incurred so far.
Vande Bharat & Amrit Bharat Express Trains
As the railway network straddles across State boundaries, trains are introduced, as per network requirement, across such boundaries. However, Indian Railways, on originating/terminating basis, have introduced 11 pairs of Vande Bharat Express and 14 pairs of Amrit Bharat Express services catering to the needs of various stations located in the State of Bihar. These are listed below:
Vande Bharat Express
|
SN
|
Train No. and Name
|
|
1
|
22349/22350 Patna - Ranchi Vande Bharat Express
|
|
2
|
22347/22348 Howrah - Patna Vande Bharat Express
|
|
3
|
22233/22234 New Jalpaiguri - Patna Vande Bharat Express
|
|
4
|
22345/22346 Patna - Gomti Nagar Vande Bharat Express
|
|
5
|
22309/22310 Howrah - Jamalpur Vande Bharat Express
|
|
6
|
20893/20894 Tatanagar - Patna Vande Bharat Express
|
|
7
|
22303/22304 Howrah - Gaya Vande Bharat Express
|
|
8
|
21893/21894 Tatanagar - Patna Vande Bharat Express
|
|
9
|
21895/21896 Tatanagar - Patna Vande Bharat Express
|
|
10
|
26501/26502 Patliputra - Gorakhpur Vande Bharat Express
|
|
11
|
26301/26302 Jogbani - Danapur Vande Bharat Express
|
Amrit Bharat Express
|
SN
|
Train No. and Name
|
|
1
|
11015/11016 Lokmanya Tilak (T) - Saharsa Amrit Bharat Express
|
|
2
|
13697/13698 Gaya - Delhi Amrit Bharat Express
|
|
3
|
15293/15294 Muzaffarpur - Charlapalli Amrit Bharat Express
|
|
4
|
15557/15558 Darbhanga - Anand Vihar (T) Amrit Bharat Express
|
|
5
|
15561/15562 Darbhanga - Gomtinagar Amrit Bharat Express
|
|
6
|
15567/15568 BapudhamMotihari - Anand Vihar (T) Amrit Bharat Express
|
|
7
|
22361/22362 Rajendranagar (T) - New Delhi Amrit Bharat Express
|
|
8
|
15133/15134 Chhapra - Anand Vihar (T) Amrit Bharat Express
|
|
9
|
14047/14048 Sitamarhi - Delhi Amrit Bharat Express
|
|
10
|
14627/14628 Saharsa - Chheharta Amrit Bharat Express
|
|
11
|
19623/19624 Madar - Darbhanga Amrit Bharat Express
|
|
12
|
19725/19726 Khatipura- Darbhanga Amrit Bharat Express
|
|
13
|
11431/11432 Pune - Danapur Amrit Bharat Express
|
|
14
|
16601/16602 Erode- Jogbani Amrit Bharat Express
|
Besides, on Indian Railways, introduction of train services is an on-going process, which depends on various factors including:
-
Capacity of that section.
-
Availability of path.
-
Availability of required rolling stock.
-
Availability of matching infrastructure for rolling stock.
-
Maintenance requirement of railway tracks and other assets.
-
Occupancy and the traffic requirement of the section.
*****
(This statement was given by MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND ELECTRONICS & INFORMATION TECHNOLOGY SHRI ASHWINI VAISHNAW in a written reply to a question in Rajya Sabha on 24.07.2026)
(Release ID: 2288813)
|