Ministry of Railways
PENDING LAND ACQUISITION FOR RAILWAY PROJECTS IN WEST BENGAL
प्रविष्टि तिथि:
24 JUL 2026 4:45PM by PIB Kolkata
Kolkata, July 24, 2026
In an answer to the unstarred question raised in the Rajya Sabha today, the Minister for Railways, Information & Broadcasting, and Electronics & Information Technology, Shri Ashwini Vaishnaw stated that Budget allocation towards Railways in the recent years has increased significantly. Budget allotment of projects is made commensurate to the progress achieved in any project.
In fact, the question regarding the total land required, acquired and pending for all sanctioned railway projects in West Bengal as on date and specific hectarage of land acquired since May, 2026 and the status of land acquisition for projects where zero land has been handed over to Railways, including Nabadwipghat-Nabadwipdham, Kaliyaganj-Buniadpur, Naihati-Ranaghat 3rd line, Bypass at Sainthia, Canning-Bagankhali and rail flyovers at Anara and Gourinathdham, project-wise, besides the revised project completion timelines consequent upon land now being made available by the new State Government was raised today by MP, Shri Samik Bhattacharya.
In answer to Shri Bhattacharya’s question, Shri Vaishnaw stated, Budget allocation for infrastructure projects and safety works, falling fully/partly in the State of West Bengal is as under:
Period Outlay
2009-14 Rs.4,380 Cr./year
2026-27 Rs. 14,205 Cr. (More than 3 times)
The Minister said, as on 01.04.2026, 63 projects (14 New Lines, 04 Gauge Conversions and 45 Doubling), covering a total length of 5,148 Km, costing ₹83,433 crore, falling fully/partly in West Bengal are sanctioned. The summary is as under:
As on 01.04.2026, 63 projects (14 New Lines, 04 Gauge Conversions and 45 Doubling), covering a total length of 5,148 Km, costing ₹83,433 crore, falling fully/partly in West Bengal are sanctioned.
Here are the details of the ongoing activities of the Ministry of Railways as furnished by Shri Vaishnaw today in the Rajya Sabha:
Recently Completed Projects:
Details of some of the recently completed projects falling fully/partly in the State of West Bengal are as under:
Sl. No. Project Cost
(Rs. in Cr.)
1 Rampurhat-Mandarhill new line (130 Km) 908
2 Azimganj-Murshidabad new line (7 Km) 164
3 Bardhaman-Katwa Gauge Conversion (52 Km) 696
4 Ahmedpur-Katwa Gauge Conversion (52 Km) 440
5 Panskura Kharagpur Doubling (45 Km) 408
6 Lalgola – Jiaganj Doubling (23 Km) 124
7 Krishnanagar-Bethuadahari Doubling (28 Km) 152
8 Nabadwipdham-Patuli Doubling (22 Km) 170
9 Bethuadhahari-Plassey Doubling (23 km) 132
10 Ambikakalna-Nabadwipdham Doubling (23 km) 145
11 Nalhati-Sagardighi Doubling (26 km) 193
12 Tamluk Jn.- Basulya Sutahata Doubling (24 km) 245
13 Plassey- Jiaganj Doubling (54 km) 234
14 Azimganj-Manigram Doubling (21 km) 150
15 New Coochbehar-Gumanihat Doubling (29 km) 330
16 New Coochbehar-Samuktala Road Doubling (29 km) 445
17 Sainthia-Tarapith 3rd line (22 Km) 186
18 Ambari Falakata-New Maynaguri Doubling (38 km) 843
19 Bandel-Boinchi - 3rd line (31 km) 546
20 Boinchi-Shaktigarh 3rd line (26 km) 424
21 Bazar Sau-Azimganj Jn. Doubling (42 km) 343
22 Sagardighi- Malda Town Doubling (25 Km) 248
23 Kharagpur-Narayangarh 3rd line (24 km) 270
24 Monigram-Nimtita Doubling (24 Km) 713
25 Purulia-Kotshila Doubling (36 Km) 393
Ongoing Projects:
Some of the projects falling fully/partly in the State of West Bengal which have been taken up are as under:
SN. Project Cost
(Rs. in Cr.)
1 Chandil- Damodar 3rd Line(121 Km) 1,932
2 Tarakeshwar-Bishnupur New Line (83 Km) 1,542
3 Sivok-Rangpo New Line (44 Km) 11,973
4 Balurghat-Hilli New Line (30 Km) 1,209
5 Kaliyaganj-Buniadpur New Line (33 Km) 1,147
6 Katihar-Kumedpur and Katihar-Mukuria Doubling (65 Km) 943
7 Kharagpur-Adityapur 3rd line (132 Km) 3,450
8 Narayangarh-Bhadrak 3rd line (153 Km) 3,425
9 Kalipahari-Bakhtarnagar 5th Line (18Km) 350
10 Dankuni-Baltikuri 3rd & 4th line (18 Km) 429
11 Murarai-Barharwa 3rd Line (49 Km) 935
12 Ranaghat-Krishnanagar City 3rd Line (26 Km) 446
13 Aluabari Road-New Jalpaiguri 3rd & 4th Line (57 Km) 1,630
14 Sainthia-Pakur 4th Line (81 Km) 1,569
15 Santragachi- Kharagpur 4th Line (111 Km) 2,905
16 Barbenda-Damrughutu Doubling, Damrughutu-Bokaro Steel City 3rd & 4th Line (52 Km) 815
17 Ranaghat-Bangaon doubling (33 Km) 396
18 Hijli to Nimpura Through yard 3rd line (6 Km) 234
19 Doubling of New Jalpaiguri- Siliguri (7 Km) 215
20 Thakurganj-Siliguri Doubling (56 Km) 916
21 Bypass line at Rampur hat (12 Km) 190
Land Acquisition Status:
Execution of important infrastructure projects falling fully/partly in the State of West Bengal were held up due to delay in land acquisition. Status of land acquisition in West Bengal is as under:
Total Land required 4,696 Ha
Land Acquired 1,273 Ha (27%)
Balance Land to be acquired 3,423 Ha (73%)
Coordination with State Government:
In order to strengthen coordination for expeditious implementation of railway connectivity projects across state, monitoring progress of such projects & facilitating coordinated resolution of implementation issues, a task force has been constituted under chairmanship of Chief Secretary, West Bengal by Govt of West Bengal.
Chingrighata Matter:
Further, temporary diversion of traffic at Chingrighata crossing for launching of viaduct segments for construction of Kolkata Metro was permitted by state government in May-26 after almost 1.5 years since the request made. The work of Chingrighata crossing has finally been completed in May-26.
Completion of Railway projects/s depends on various factors which include the following:
• Land acquisition by State Government
• Forest clearance
• Shifting of infringing utilities
• Statutory clearances from various authorities
• Geological and topographical conditions of area
• Law and order situation in the area of project site
• Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
***********
SSS/Kol/24.7.26…..