Railway Infrastructure in Maharashtra Gets Major Boost


Connectivity Enhancement Projects Progressing Across the State

Posted On: 29 JUL 2026 6:25PM by PIB Mumbai

PIB Mumbai :  29 July 2026

The Ministry of Railways is undertaking a series of infrastructure projects to strengthen rail connectivity across Maharashtra, with significant progress being made on new railway lines, doubling works and capacity augmentation projects.

To enhance rail connectivity in the Shirdi region and adjoining areas, the Daund–Manmad Doubling Project has recently been commissioned. Under the Ahilyanagar (Ahmednagar)–Beed–Parli Vaijnath New Line Project, the 201-km Ahilyanagar–Beed–Badwani section has already been commissioned, while work on the remaining section is progressing.

The Rahuri–Shani Shingnapur New Line and Puntamba–Sainagar Shirdi Doubling Project have been declared Special Railway Projects for land acquisition. Competent Authorities for Land Acquisition (CALA) have been appointed and land acquisition activities are underway to facilitate timely implementation of these projects.

As part of long-term planning to improve connectivity, surveys and Detailed Project Reports (DPRs) have also been taken up for several new railway corridors, including Nashik Road–Sainagar Shirdi, Pune–Ahilyanagar, Dharashiv–Beed–Chhatrapati Sambhajinagar, and Chhatrapati Sambhajinagar–Ahilyanagar. The Minister stated that sanction of railway projects is subject to consultations with State Governments and other stakeholders, followed by the requisite statutory and financial approvals.

The Government has significantly enhanced investment in railway infrastructure in Maharashtra. An allocation of ₹23,926 crore has been made for railway infrastructure and safety works in the State during 2026-27, which is more than 20 times the average annual allocation during 2009-14.

Between 2014 and 2026, a total of 2,585 km of new railway lines have been commissioned in Maharashtra, with the average rate of commissioning increasing to nearly four times that achieved during the 2009-14 period.

As on 1 April 2026, 52 railway projects, comprising 13 new lines, 2 gauge conversion projects and 37 doubling/multitracking projects, covering a total length of 5,956 km at an estimated cost of ₹1,42,635 crore, have been sanctioned in Maharashtra. Of these, 1,598 km has been commissioned up to March 2026, with an expenditure of ₹34,782 crore.

Several key railway infrastructure projects are currently under implementation across the State, including the Ahilyanagar–Parli Vaijnath New Line, Wardha–Nanded New Line, Indore–Manmad New Line, Jalna–Jalgaon New Line, Solapur–Tuljapur–Osmanabad New Line, Panvel–Chowk Double Line, and Kasara–Manmad 3rd & 4th Line, among others. These projects are expected to enhance regional connectivity, improve operational efficiency, facilitate freight movement and contribute to the socio-economic development of Maharashtra.

Railway projects are sanctioned after considering multiple factors, including traffic projections, operational requirements, connectivity needs, socio-economic considerations and the availability of financial resources. The execution of projects is carried out in phases, subject to land acquisition, statutory clearances, forest approvals and other technical requirements.

This information was provided by Union Minister for Railways, Information & Broadcasting and Electronics & Information Technology, Shri Ashwini Vaishnaw, in a reply to a Starred Question in the Lok Sabha today.

PIB Mumbai | Nitin Fulluke/ Priti Malandkar

 

Follow us on social media: @PIBMumbai   Image result for facebook icon /PIBMumbai    /pibmumbai  pibmumbai[at]gmail[dot]com  /PIBMumbai    /pibmumbai

 

 

 

 

 


(Release ID: 2291275) Visitor Counter : 858
Read this release in: Marathi