(i) Existing Permanent Bridges and Temporary Bailey Bridges
|
S.
No.
|
NH
No.
|
State
|
Name of the Bridge/ Location
|
Details
|
No. of Lives Lost
|
Calendar / Financial Year of Collapse
|
Action taken against Defaulting Contractor/ Concessionaire
|
1
|
4
|
A & N Islands
|
Bailey Bridge @ Thoratang; Km 206+000
|
Existing Bailey Bridge collapsed in the Month of Jun 2019.
|
NIL
|
2019
|
Penalty of Rs. 20.00 lakh imposed on the EPC Contractor for improper maintenance of the Bridge.
|
2
|
716
|
Andhra Pradesh
|
Papagni Bridge at Km 153/200
|
There are total number of 72 spans of 6.70 Mts . Out of which 14 No's of Spans were collapsed , due to
flood on 20.11.2021.
|
0
|
2021-22
|
The bridge was constructed by the State (R&B) Department on 1977.
Hence, no action was taken.
|
3
|
565
|
Andhra Pradesh
|
Lingasamudram Bridge at Km 466.750 in
Penchalakona -
Yerpedu section of NH 565.
|
Floods occurred during NIVAR Cyclone in
November 2020 and a vent washed away at
Lingasamudram Bridge at Km 466.750 in
Penchalakona - Yerpedu section of NH 565.
|
0
|
2020
|
The stretch handed over from MoRT&H on 07.02.2019 for which DLP was completed on 15.04.2018
|
4
|
313
|
Arunachal
Pradesh
|
Km 120
|
Bailey bridge failed due to
overloading.
|
|
2021-22
|
|
5
|
713
|
Arunachal Pradesh
|
Kurung River- Bailey Bridge at chainage Km.128+038
on Road Joram
-Koloriang, NH-713
|
Exsiting Bailey Bridge on Kurung River at Ch 128+038 of Joram - Koloriang Road Projects Pkg-08 collapsed on 30.06.2024 due to Flash Flood.
|
NIL
|
2024
|
To restore Traffic a PMGSY Road from Kurung Bridge to Koloriang via Rengchi Village amounting to a length of 8 Km has been strengthened and all traffic is going Through.
A 130 Feet DDRB Bailey Bridge is under Construction and likely to get Completed by 31.08.2024.
As a Permanent measure, a permanent Bridge will be Constructed is due Course of time.
|
6
|
313
|
Arunachal Pradesh
|
Dree-River Bailey Bridge at chainage Km.
120.00 on Road Hunli-Anini,
NH-313
|
Dree-River Bailey Bridge on Hunli-Anini road at chainage Km. 120.00 collapsed on 06/04/2021 (NH-313) due to Over loaded Vehicle.
|
NIL
|
2021
|
A 190 Feet Bailey Bridge was Constructed to keep the line of Communication through.
As a Permanent measure, a permanent bridge with load class
70 R has been Constructed and put to use.
|
7
|
AIP- NH
|
Arunachal Pradesh
|
1. Ego RCC
Bridge at Chainage Km.
67.00 on Road Akajan-
Likabali-Bame.
|
1. Ego RCC Bridge under Akajan-Likabali-
Bame road at chainage Km.
67.00 collapsed on 18/09/2020 due to Flash
Flood.
|
NIL
|
2020
|
To restore Traffic a 130 Feet Bailey Bridge was Constructed to keep the line of Communication open.
Permanent Bridge at this location has been Constructed.
|
8
|
754K
|
Gujarat
|
Jatawada bridge at km 226/473
|
Due to heavy rain in monsson 2022-23 in Rapar, Dist. Kachchh region, scouring in pier foundation of this 2-span minor bridge, pier settled down and bridge
collapsed.
|
Nil
|
2022
|
It was an old bridge was constructed by State Government before declaration of NH. Therefore, the matter does not pertains to this Ministry.
|
9
|
105
|
Himachal Pradesh/ Haryana/ RO HP
|
7.706 (vill. Charaniya) [Length = 54 m (6x9.0)]
|
Due to flash flood occurred on account of unprecedented heavy rainfall (natural calamity) in the month of July/August 2023, 03 nos existing bridges constructed by Public Works Department collapsed in Haryana/ Himachal Pradesh state at Ch. 7+706, Ch. 14+020 &
Ch. 17+661 in NH 105
section of Pinjore-Baddi- Nalagarh.
|
Nil
|
2023-24
|
Nil
|
10
|
105
|
Himachal Pradesh/ Haryana/ RO HP
|
14.020 (vill. Marranwala)
[Length = 107.2 m (16x6.7)]
|
Due to flash flood occurred on account of unprecedented heavy rainfall (natural calamity) in the month of July/August 2023, 03 nos existing bridges constructed by Public Works Department collapsed in Haryana/
Himachal Pradesh state at Ch. 7+706, Ch. 14+020 &
Ch. 17+661 in NH 105
section of Pinjore-Baddi- Nalagarh.
|
Nil
|
2023-24
|
Nil
|
11
|
105
|
Himachal Pradesh/ Haryana/ RO HP
|
17.661 (Baddi / Barotiwala) [Length = 188 m (20x9.4)]
|
Due to flash flood occurred on account of unprecedented heavy rainfall (natural calamity) in the month of July/August 2023, 03 nos existing bridges constructed by Public Works Department collapsed in Haryana/ Himachal Pradesh state at Ch. 7+706, Ch. 14+020 &
Ch. 17+661 in NH 105
section of Pinjore-Baddi- Nalagarh.
|
Nil
|
2023-24
|
Nil
|
12
|
44
|
J&K
|
(km 46+305 to km 46+864)/ Tarnah Bridge
|
Due to heavy rainfall in Kathua district ( 229 mm on upstream barrage location) on 19.07.2023(early morning), the floor protection of the bridge got completely damaged in 05 spans. 03 Foundations ( P 23, P 24 & P 25 ) got
settled. The Tarnah river never attained this level. Increase in water level in the river started eroding the upstream side protection wall of floor protection of the bridge having shallow foundations resulting in caving underneath the foundations.
|
Nil
|
2023-24
|
Event was a Natural Calamity wherein excessive discharge due to unprecedented rains caused scouring beyond the prescribed design limits and damaged 3 pier foundations and caused settlement of spans.
The damaged spans are being reconstructed with design as per extant IRC guidelines.
No such action taken.
|
|
|
|
|
|
|
|
13
|
46
|
Madhya Pradesh
|
77.900
|
Failure due to overloaded truck on dialapated Bridge
|
0
|
(2022-2023)
|
FIR was launched against the transporter of the heavy consignment and legal notice was
also served by PIU-Harda.
|
14
|
44(7)
|
Maharashtra
|
Birdge over Nag River Nagpur at Ch.
1/250
|
- Bridge collapsed on 23/09/2023
- Year of construction 1974 as observed in Masonry
Register
- Bridge was already in dilapitated state and due to
Heavy Floods
|
_
|
2023
|
Does not arise
|
15
|
37
|
Manipur
|
Irang Bailey Bridge (Irang River)
|
Old Irang TDR Bailey bridge was collapsed on May 2024; due to Remal cyclone (heavy rain).
However a permanent 4- Lane 123m span RCC 70 R has been constructed adjacently & is open to
traffic. Hence construction of New bailey bridge is not
required.
|
NIL
|
2024-25
|
-
|
16
|
102B
|
Manipur
|
Khuanggin Bridge Bailey
Bridge at Ch 120.900
|
Length of bailey bridge 180 ft. Year of construction
1994, collapsed due to Flash Flooding and overloading.
|
NIL
|
2022-23
|
-
|
17
|
37
|
Manipur
|
Irang Bailey Bridge (Irang River) (120.9 Km)
|
Old Irang DDR Bailey bridge was collapsed on May 2022; due to scouring of the abutment due to heavy incessannt rain New TDR bailey bridge was constructed & open to
traffic on Aug 2022.
|
NIL
|
2022-23
|
-
|
18
|
37
|
Manipur
|
Irang Bailey Bridge (Irang River)
|
Old Irang DDR Bailey bridge was collapsed on Nov 2020; due to plying of overloaded truck New DDR bailey bridge was constructed & open to
traffic on Dec 2020
|
1
|
2020
|
-
|
19
|
62
|
Meghalaya
|
Km217
|
Washed out due to high flood
|
0
|
2022-23
|
NA
|
20
|
217
|
Meghalaya
|
203rd Km of Ch. 150.00 m
Bakla Bridge
|
Bailey Bridge. Failure of super structure due to overloading beyond Bridge
Capacity.
|
Nil
|
2024
|
No
|
21
|
16
|
Odisha
|
At Km. 79+614
on Chandikhole
-Bhadrak section
|
The Major Bridge is an existing bridge, which retained during upgradation from 4-lane to 6-lane. The Bridge was constructed in the year 2007/2008 by M/s.
Gammon India Limited. The six-laning work was awarded to the Concessionaire M/s DBL Chandikhole Bhadrak Highways Limited and work has been completed w.e.f.
19.02.2023. New DPR
Consultant engaged for preparation of DPR for the damaged bridge and tender invited, work will be commence very soon
|
0
|
2023-24
|
- Penalty of Rs.5 crore imposed on the Construction Contractor,
M/s.Gammon India Ltd.
- Penalty of Rs.20 lakh imposed on the then Supervision Consultant
i.e. M/s.LBLL-NICE(JV) of
Construction of Bridge.
- Debarment of DPR Consultant M/s Sheladia Associates for 1 year.
- The cost of entire remedial measures / reconstruction including cost of DPR preparation recovered from the existing Concessionaire
M/s DBL Chandikhole Bhadrak Highways Limited
- Penalty of Rs.20 lakh and debarment for 1 year on
Independent Engineer M/s.TPF Gentisa Eurostudios S.L with Segmental
- Debarment for 3 years against the then Shri R K Singh, Sr. Bridge
Engineer from Supervision Consultant i.e. M/s.LBLL- NICE(JV)
|
22
|
326
|
Odisha
|
Km 297/520
|
Old Bridge
|
0
|
2022-2023
|
Not applicable
|
23
|
510
|
Sikkim
|
0+200 (Sirwani Bridge)
|
Due to excessive rainfall & Glacial Lake Outburst Flood (GLOF) at South Lhonak in North Sikkim resulting flash
flood in teesta river.
|
NIL
|
2023-24
|
-
|
24
|
208
|
Tripura
|
Steel Bailey Bridge over River Sonaichhara existing Ch.
180.00.
Telaimaura- Harina Section.
|
Steel Bailey bridge collapsed due to Ageing, dilapidated condition & Overloading
|
NIL
|
2022-23
|
The section was taken over from the State PWD, and the steel bridge was already in a dilapidated condition. It collapsed due to aging and overloading. Therefore, no action was taken against the contractor.
|
25
|
208
|
Tripura
|
Steel Bailey Bridge at existing Ch.
167.00.
Telaimaura- Harina Section,
|
Steel Bailey bridge collapsed due to Ageing, dilapidated condition & Overloading
|
NIL
|
2021
|
The section was taken over from the State PWD, and the steel bridge was already in a dilapidated condition. It collapsed due to aging and overloading. Therefore, no action was taken against the
contractor.
|
26
|
730
|
Uttar
Pradesh
|
Minor Bridge
(Ch. 241+704)
|
Due to heavy flood
|
|
2022-23
|
|