Ministry of Road Transport & Highways
azadi ka amrit mahotsav

Stability and Progress of Infrastructure

Posted On: 08 AUG 2024 12:09PM by PIB Delhi

Total 58,635 km National Highways (NHs) has been constructed over the last five years and the current year.

The Ministry is primarily responsible for the development and maintenance of NHs. There have been a few incidents of collapse of bridges/ tunnels in the country during last five years and in the current year. Details are at Annexure-I.

The State/UT - wise details of projects awarded during the last five years and the current year, is at Annexure-II.

At present, 1,379 projects of this Ministry are under construction across the country.

ANNEXURE-I

The details of collapse of bridges/ tunnels in the country during last five years and in the current year

 

(i) Existing Permanent Bridges and Temporary Bailey Bridges

S.

No.

NH

No.

State

Name of the Bridge/ Location

Details

No. of Lives Lost

Calendar / Financial Year of Collapse

Action taken against Defaulting Contractor/ Concessionaire

1

4

A & N Islands

Bailey Bridge @ Thoratang; Km 206+000

Existing Bailey Bridge collapsed in the Month of Jun 2019.

NIL

2019

Penalty of Rs. 20.00 lakh imposed on the EPC Contractor for improper maintenance of the Bridge.

2

716

Andhra Pradesh

Papagni Bridge at Km 153/200

There are total number of 72 spans of 6.70 Mts . Out of which 14 No's of Spans were collapsed , due to

flood on 20.11.2021.

0

2021-22

The bridge was constructed by the State (R&B) Department on 1977.

Hence, no action was taken.

3

565

Andhra Pradesh

Lingasamudram Bridge at Km 466.750 in

Penchalakona -

Yerpedu section of NH 565.

Floods occurred during NIVAR Cyclone in

November 2020 and a vent washed away at

Lingasamudram Bridge at Km 466.750 in

Penchalakona - Yerpedu section of NH 565.

0

2020

The stretch handed over from MoRT&H on 07.02.2019 for which DLP was completed on 15.04.2018

4

313

Arunachal

Pradesh

Km 120

Bailey bridge failed due to

overloading.

 

2021-22

 

5

713

Arunachal Pradesh

Kurung River- Bailey Bridge at chainage Km.128+038

on Road Joram

-Koloriang, NH-713

Exsiting Bailey Bridge on Kurung River at Ch 128+038 of Joram - Koloriang Road Projects Pkg-08 collapsed on 30.06.2024 due to Flash Flood.

NIL

2024

To restore Traffic a PMGSY Road from Kurung Bridge to Koloriang via Rengchi Village amounting to a length of 8 Km has been strengthened and all traffic is going Through.

A 130 Feet DDRB Bailey Bridge is under Construction and likely to get Completed by 31.08.2024.

As a Permanent measure, a permanent Bridge will be Constructed is due Course of time.

6

313

Arunachal Pradesh

Dree-River Bailey Bridge at chainage Km.

120.00 on Road Hunli-Anini,

NH-313

Dree-River Bailey Bridge on Hunli-Anini road at chainage Km. 120.00 collapsed on 06/04/2021 (NH-313) due to Over loaded Vehicle.

NIL

2021

A 190 Feet Bailey Bridge was Constructed to keep the line of Communication through.

As a Permanent measure, a permanent bridge with load class

70 R has been Constructed and put to use.

7

AIP- NH

Arunachal Pradesh

1. Ego RCC

Bridge at Chainage Km.

67.00 on Road Akajan-

Likabali-Bame.

1. Ego RCC Bridge under Akajan-Likabali-

Bame road at chainage Km.

67.00 collapsed on 18/09/2020 due to Flash

Flood.

NIL

2020

To restore Traffic a 130 Feet Bailey Bridge was Constructed to keep the line of Communication open.

Permanent Bridge at this location has been Constructed.

8

754K

Gujarat

Jatawada bridge at km 226/473

Due to heavy rain in monsson 2022-23 in Rapar, Dist. Kachchh region, scouring in pier foundation of this 2-span minor bridge, pier settled down and bridge

collapsed.

Nil

2022

It was an old bridge was constructed by State Government before declaration of NH. Therefore, the matter does not pertains to this Ministry.

9

105

Himachal Pradesh/ Haryana/ RO HP

7.706 (vill. Charaniya) [Length = 54 m (6x9.0)]

Due to flash flood occurred on account of unprecedented heavy rainfall (natural calamity) in the month of July/August 2023, 03 nos existing bridges constructed by Public Works Department collapsed in Haryana/ Himachal Pradesh state at Ch. 7+706, Ch. 14+020 &

Ch. 17+661 in NH 105

section of Pinjore-Baddi- Nalagarh.

Nil

2023-24

Nil

10

105

Himachal Pradesh/ Haryana/ RO HP

14.020 (vill. Marranwala)

[Length = 107.2 m (16x6.7)]

Due to flash flood occurred on account of unprecedented heavy rainfall (natural calamity) in the month of July/August 2023, 03 nos existing bridges constructed by Public Works Department collapsed in Haryana/

Himachal Pradesh state at Ch. 7+706, Ch. 14+020 &

Ch. 17+661 in NH 105

section of Pinjore-Baddi- Nalagarh.

Nil

2023-24

Nil

11

105

Himachal Pradesh/ Haryana/ RO HP

17.661 (Baddi / Barotiwala) [Length = 188 m (20x9.4)]

Due to flash flood occurred on account of unprecedented heavy rainfall (natural calamity) in the month of July/August 2023, 03 nos existing bridges constructed by Public Works Department collapsed in Haryana/ Himachal Pradesh state at Ch. 7+706, Ch. 14+020 &

Ch. 17+661 in NH 105

section of Pinjore-Baddi- Nalagarh.

Nil

2023-24

Nil

12

44

J&K

(km 46+305 to km 46+864)/ Tarnah Bridge

Due to heavy rainfall in Kathua district ( 229 mm on upstream barrage location) on 19.07.2023(early morning), the floor protection of the bridge got completely damaged in 05 spans. 03 Foundations ( P 23, P 24 & P 25 ) got

settled. The Tarnah river never attained this level. Increase in water level in the river started eroding the upstream side protection wall of floor protection of the bridge having shallow foundations resulting in caving underneath the foundations.

Nil

2023-24

Event was a Natural Calamity wherein excessive discharge due to unprecedented rains caused scouring beyond the prescribed design limits and damaged 3 pier foundations and caused settlement of spans.

The damaged spans are being reconstructed with design as per extant IRC guidelines.

No such action taken.

 

 

 

 

 

 

 

13

46

Madhya Pradesh

77.900

Failure due to overloaded truck on dialapated Bridge

0

(2022-2023)

FIR was launched against the transporter of the heavy consignment and legal notice was

also served by PIU-Harda.

14

44(7)

Maharashtra

Birdge over Nag River Nagpur at Ch.

1/250

  • Bridge collapsed on 23/09/2023
  • Year of construction 1974 as observed in Masonry
  • Register

  • Bridge was already in dilapitated state and due to
  • Heavy Floods

    _

    2023

    Does not arise

    15

    37

    Manipur

    Irang Bailey Bridge (Irang River)

    Old Irang TDR Bailey bridge was collapsed on May 2024; due to Remal cyclone (heavy rain).

    However a permanent 4- Lane 123m span RCC 70 R has been constructed adjacently & is open to

    traffic. Hence construction of New bailey bridge is not

    required.

    NIL

    2024-25

    -

    16

    102B

    Manipur

    Khuanggin Bridge Bailey

    Bridge at Ch 120.900

    Length of bailey bridge 180 ft. Year of construction

    1994, collapsed due to Flash Flooding and overloading.

    NIL

    2022-23

    -

    17

    37

    Manipur

    Irang Bailey Bridge (Irang River) (120.9 Km)

    Old Irang DDR Bailey bridge was collapsed on May 2022; due to scouring of the abutment due to heavy incessannt rain New TDR bailey bridge was constructed & open to

    traffic on Aug 2022.

    NIL

    2022-23

    -

    18

    37

    Manipur

    Irang Bailey Bridge (Irang River)

    Old Irang DDR Bailey bridge was collapsed on Nov 2020; due to plying of overloaded truck New DDR bailey bridge was constructed & open to

    traffic on Dec 2020

    1

    2020

    -

    19

    62

    Meghalaya

    Km217

    Washed out due to high flood

    0

    2022-23

    NA

    20

    217

    Meghalaya

    203rd Km of Ch. 150.00 m

    Bakla Bridge

    Bailey Bridge. Failure of super structure due to overloading beyond Bridge

    Capacity.

    Nil

    2024

    No

    21

    16

    Odisha

    At Km. 79+614

    on Chandikhole

    -Bhadrak section

    The Major Bridge is an existing bridge, which retained during upgradation from 4-lane to 6-lane. The Bridge was constructed in the year 2007/2008 by M/s.

    Gammon India Limited. The six-laning work was awarded to the Concessionaire M/s DBL Chandikhole Bhadrak Highways Limited and work has been completed w.e.f.

    19.02.2023. New DPR

    Consultant engaged for preparation of DPR for the damaged bridge and tender invited, work will be commence very soon

    0

    2023-24

  • Penalty of Rs.5 crore imposed on the Construction Contractor,
  • M/s.Gammon India Ltd.

  • Penalty of Rs.20 lakh imposed on the then Supervision Consultant
  • i.e. M/s.LBLL-NICE(JV) of

    Construction of Bridge.

  • Debarment of DPR Consultant M/s Sheladia Associates for 1 year.
  • The cost of entire remedial measures / reconstruction including cost of DPR preparation recovered from the existing Concessionaire
  • M/s DBL Chandikhole Bhadrak Highways Limited

  • Penalty of Rs.20 lakh and debarment for 1 year on
  • Independent Engineer M/s.TPF Gentisa Eurostudios S.L with Segmental

  • Debarment for 3 years against the then Shri R K Singh, Sr. Bridge
  • Engineer from Supervision Consultant i.e. M/s.LBLL- NICE(JV)

    22

    326

    Odisha

    Km 297/520

    Old Bridge

    0

    2022-2023

    Not applicable

    23

    510

    Sikkim

    0+200 (Sirwani Bridge)

    Due to excessive rainfall & Glacial Lake Outburst Flood (GLOF) at South Lhonak in North Sikkim resulting flash

    flood in teesta river.

    NIL

    2023-24

    -

    24

    208

    Tripura

    Steel Bailey Bridge over River Sonaichhara existing Ch.

    180.00.

    Telaimaura- Harina Section.

    Steel Bailey bridge collapsed due to Ageing, dilapidated condition & Overloading

    NIL

    2022-23

    The section was taken over from the State PWD, and the steel bridge was already in a dilapidated condition. It collapsed due to aging and overloading. Therefore, no action was taken against the contractor.

    25

    208

    Tripura

    Steel Bailey Bridge at existing Ch.

    167.00.

    Telaimaura- Harina Section,

    Steel Bailey bridge collapsed due to Ageing, dilapidated condition & Overloading

    NIL

    2021

    The section was taken over from the State PWD, and the steel bridge was already in a dilapidated condition. It collapsed due to aging and overloading. Therefore, no action was taken against the

    contractor.

    26

    730

    Uttar

    Pradesh

    Minor Bridge

    (Ch. 241+704)

    Due to heavy flood

     

    2022-23

     

     

    (ii) Under Construction Bridges

    S.

    No.

    NH

    No.

    State

    Name of the Bridge/ Location

    Details

    No. of Lives Lost

    Calendar / Financial Year of Collapse

    Action taken against Defaulting Contractor/ Concessionaire

    1

    131G

    Bihar

     

     

     

    Km 11+800

    A girder collapse incident occurred during construction activities, attributed to a mechanical failure that took place while a Hydra crane was being used to position shuttering for cross-girder work.

    0

    2022-2023

    Two persons form Supervision Consultants and Two persons from Contractor side suspended from the Project. Further, necessary safety measures were suggested by Expert Committee to avoid further mishappenings.

    2

    20

    Bihar

    Km 133+720

    One no of PSC Girder fallen down during erection due to the Winch failure of Crane of Elevated Structure.

    1

    2022-2023

    Two persons form Supervision Consultants and Two persons from Contractor side suspended from the Project. Further, necessary safety measures were suggested by Expert Committee to avoid further

    mishappenings.

    3

    527A

    Bihar

    Km 10.270 to

    10.330 (P154- P153)

    A girder collapse incident occurred during construction activities, attributed to a mechanical failure

    1

    2023-24

    Chief Project Manager & Engineer (Launching) of Contractor and Team Leader cum Senior Bridge Engineer & Assistant Bridge Engineer of Authority's Engineerworked at the time

    of Collapse have been suspended by theAuthority (NHAI).

    4

    248BB

    Delhi

    GSS-3 P8-P9

    2022-23. One span of under construction flyover toppled due to

    mechanical failure of jacks

    1

    2023

    Strict Warning issued to Contractor

    5

    248BB

    Delhi/ Haryana

    Spin Girder Pillor No. 107-108 &

    108-109

    2020-21. Two spans of under construction flyover collapsed.

    0

    2021

    Levied Penalty of Rs. 6.67 Cr. on Contractor & shall not be bidding in any of

    the Bids of NHAI for 03 Months.

    6

    NH- 248A

    Delhi/ Haryana

    Span Girder Pillar no.10

    2020-21: One span of under construction flyover collapsed.

    0

    2020

    Levied Penalty of Rs. 3 Crore on the contractor and shall not be bidding in any

    of the bids of NHAI consisting major structure works for 6 months.

    7

    58

    Gujarat

    ROB at LC no 165

    Due to some reason the six girder of 1 span of the ROB toppled and collapsed.

    2

    2023

    Government of Gujarat constituted an Expert Committee to investigate the incident for taking action against the

    contractor.

    8

    NH-66

    Kerala

    Pullur Ch 78+971

    Slipped off the girders (9 Nos) during the deck slab at pullur 20m skew bridge at Km 78+971 on the project stretch of Chengala Neeelshwaram section of NH-66 on

    08.05.2024 at 4.40pm

    No casulaity happened

    2024-25

    Show cause notice issued by RO-Kerala to Concessionaire&Consultant vide Ro letter no. 12448/RO-Kerala/Chengala- Neeleshwaram/MEIL/1594 Dt. 31.07.2024

    9

    NH - 66

    Kerala

    Ch.174+150

    (Thalssery-Mahe Bypass Section )

    01 Bridge (4 girders collpased)

    Nil

    2020

  • Penatly of Rs. 1.00 Cr imposed on Contractor and Penalty of Rs. 20.00 lakhs
  • imposed on Authority's Engineer

  • Team Leader, Bridge Engineer of Authority's Engineer was terminated from project and debarred for a period of 2 years
  • Project Manager of Contractor was terminated from project.
  • Contractor was debarred from partipating in Tender for a period of 1 year
  • 10

    66

    Kerala

    Km 72+297 VUP (LHS)

    Collapsed during the concretingdue to staging failure

    0

    2022-23

    Action taken on Concessionaire & Consultancy agencies. Suspended Key persons up to 4months and Penalty

    Imposed.

    11

    66

    Maharashtra

    Chiplun flyover (48/850)

    No such case of Bridge collapsed on the National Highway after

    opening for traffic has occured since 2019-20 in Jurisdiction of National

    0

    2023-24

    The expert committee of 3 bridge experts is formed and the matter is under review. The

    bridge is now under construction with suitable modified design by the

     

     

     

     

     

    Highway division. However on 16.10.2023 girder of under

    construction chiplun Flyover during launching.

     

     

    concessionaire at its own cost.

    12

    16

    Odisha

    At Km. 96+326

    on Chandikhole - Bhadrak section

    During the pouring of concrete in deck of slab of under Construction Bridge, the deck slab was collapsed.

    As per investigation of Expert Committee; the collapse happened due to the absence of some minor/ negligible arrangement on the part of Concessionaire. The Concessionaire executed the remedial measures, as per the suggestion/ recommendation of Expert Committee, by dismantling the Slabs of A1P1, P1P2 and Top layer of Concrete in the Abutment

    and Pier walls

    0

    2021-22

    Penalty of Rs.30 Lakhs on the Concessionaire and penalty of Rs.5 Lakhs on the Independent Engineer. Team Leader of IE and Key Personnel of Concessionaire was suspended

    13

    510

    Sikkim

    Singtam-Tarku NH-510 Km 0+070

    Due to excessive rainfall & Glacial Lake Outburst Flood (GLOF) at South Lhonak in North Sikkim

    resulting flash flood in teesta river.

    2

    2023

    -

    14

    45/36

    Tamil Nadu

    Anaikarai Major Bridge at 107+400

    1.A Segmental Girder between P16 and P17 of RHS Carriageway fell down due to mechanical failure of hydraulic jacks at Km 107+400

    Anaikarai Major Bridge across Kollidam river on 22.01.2022.

    2.The instant mishap has been categorized into minor failure which occurred due to non-robust temporary structure/launching- lowering system as opined by Expert Committee.

    0

    2022

    Three Key personnal of the Indpendent Engineer (2 Nos) and Site Engineers (2 Nos) of the Concessionaire has been suspended and blacklisted with immediate effect of mishap. The Concessionaire firm has been restrained from participating in any NHAI bids till further orders. The Competent Authority has directed to impose a financial penalty of Rs.7.305 Crore, being 0.5% of the BPC on Concessionaire/Promoter of Concessionaire (Patel Infrastructure Ltd) for the lapses/laxity besides reconstruction of the collapse girders/span and its rectification at its own cost. Further, Token pending of Rs. 5 Lakhs has been imposed on IE i.e. M/s.Theme Engineering Services and the IE has remitted this penalty

    amount in favour of “National Highways Authority of India on 29.08.2022.

    15

    785

    Tamil Nadu

    Madurai - Chettikulam Section at Km 2+850

    3 Girders (G1,G2 & G3) between pier P4 & P5 at km 2+850 of down ramp location of the Elevated Road due to jack failure

    1

    2021

    NHAI HQ vide letter dated 28.01.2022, issued orders for debarment of Contractor from participating in NHAI bids w.e.f 13.09.2021 to 28.01.2022 (i.e, date of interim action). Further, NHAI, HQ vide Lr.

    No. 46597 Dt. 28.01.2022 has imposed penalty of Rs.3.00 Cr to the Contractor and the same has been recovered from EPC Contractor from IPC No. 36 for the month of December, 2021.

    Authority Engineer: M/s. Yongma Engineering Co Limited in association

    with M/s. Sterling Indo Tech Consultants Pvt Ltd

    NHAI HQ vide letter dated 28.01.2022, issued orders for debarment of Contractor from participating in NHAI bids w.e.f 13.09.2021 to 28.01.2022 (i.e, date of interim action). Further, NHAI, HQ vide lr.

    No. 46595 dt. 28.01.2022 has imposed penalty of Rs.40.00 lakhs to the Authority Engineer and the same has been reocovered from Authority Engineer from Invoice No.09 for the month of Dec'21 and Invoice No.10 for the month of Jan'22.

    Further, NHAI, RO, Madurai vide Lr. No. 1668 Dt. 03.09.2021, suspended 4 Nos of

    key personnel in EPC contractor and 6 Nos of key personnel in AE.

     

     

     

     

     

     

     

    16

    NH-12

    (old NH-

    34)

    West Bengal

    Construction of new 4-lane bridge over river Ganga at downstream of Farakka Barrage including approaches connecting Farakka –

    Raiganj section of NH-34

    An unfortunate incident occurred on 16.02.2020, wherein one of the launching girders toppled on already launched span leading to collapse of the said span (0.060 km).

    2

    2020

    The Contractor was debarred from participation in future NHAI projects for Three (03) years vide NHAI-HQ letter dated 25.08.2020.

     

    (iii) Under Construction Tunnels

     

    S.

    No.

     

    NH

    No.

     

    State

     

    Name of the Tunnel/ Location

     

    Details

    No. of Lives Lost

    Calendar / Financial Year of Collapse

     

    Action taken against Defaulting Contractor/ Concessionaire

    1

    29

    Nagaland

    Tunnel under Kohima Bypass from Km 11+000 to 11+500

    Eastern Portal of Tunnel Collapsed due to heavy Rainfall on 17.11.2023

    due to cyclonic storm Medhili.

    NIL

    2023

    EPC Contractor has been directed to submit a Restoration Proposal along with modified Working Methodology for recommencing of tunnel works safely.

    2

    134

    Uttarakhand

    Silkyara Bend- Barkot Tunnel , Uttarkashi

    A 60 m portion of under construction tunnel was collapsed on 12.11.2023.

    NIL

    2023

    Investigation committee has been constituted by Govt. of India 06.12.2023. Final report of

    the investigation committee is yet to be received.

    3

    44

    Jammu and Kashmir

    Cafeteria Tunnel (Km 148.655)

    Portal P2 of the 800m long tunnel collapsed in June 2023 at

    Cafeteria morh in Ramban district.

    Nil

    2023

    Show Cause notice was issued to Contractor, Authority Engineer and DPR (Detailed Project Report) Consultant.

    4

    44

    Jammu and Kashmir

    Collapse of Adit portal at Khooni Nallah

    (Km 163.400)

    Adit portal at Khooni Nallah collapsed due to landslide on 19.05.2022 in tunnel package-II in Ramban- Banihal section of NH- 44

    10

    labourers

    2022

    MoRTH constituted an Expert Committee and based on the submission of facts by the Committee, NHAI blacklisted Project Manager of EPC contractor and imposed the penalty of 1

    % of Project cost on EPC contractor.

    Contractor was also debarred for a period of 6 months. Show cause notice was issued to Authority Engineer.

     

    ANNEXURE-II

    The State/UT wise details of length of NH works (in km) awarded during the last five years and the current year:

     

    Sl. No.

    State

    Total no. of projects sanction from

    2019-25 (Till June, 2024)

    1.

    Andhra Pradesh

    3,478

    2.

    Arunachal Pradesh

    678

    3.

    Assam

    1,628

    4.

    Bihar

    2,622

    5.

    Chhattisgarh

    1,231

    6.

    Goa

    181

    7.

    Gujarat

    2,086

    8.

    Haryana

    1,105

    9.

    Himachal Pradesh

    942

    10.

    Jharkhand

    1,784

    11.

    Karnataka

    2,821

    12.

    Kerala

    1,132

    13.

    Madhya Pradesh

    3,860

    14.

    Maharashtra

    6,424

    15.

    Manipur

    1,108

    16.

    Meghalaya

    525

    17.

    Mizoram

    681

    18.

    Nagaland

    983

    19.

    Odisha

    1,636

    20.

    Punjab

    2,030

    21.

    Rajasthan

    3,344

    22.

    Sikkim

    250

    23.

    Tamil Nadu

    2,207

    24.

    Telangana

    1,931

    25.

    Tripura

    604

    26.

    Uttar Pradesh

    4,687

    27.

    Uttarakhand

    1,445

    28.

    West Bengal

    875

    29.

    Union Territories (UTs)

    1,416

     

    This information was given by the Union Minister for Road Transport and Highways, Shri Nitin Gadkari in a written reply in the Lok Sabha today.

    *****