LACK OF RAILWAY CONNECTIVITY FOR SHEOHAR DISTRICT

Posted On: 13 AUG 2026 6:54AM by PIB Patna

To improve connectivity in Sheohar district, Sitamarhi – Sheohar (28 Km) new line project has been sanctioned at a cost of ₹567 Crore. This project has been declared as Special Railway Project. 

Status of works is under:

  • Land acquisition: 98 Ha land out of 160 Ha has been completed. 

  • Works on mega bridge across Bagmati river (over 600m long) between Rewasi-Sheohar station has been taken up.

Bihar:

Railway Budget:

Budget allocation in the recent years has increased significantly. Budget allocation for infrastructure projects falling fully/partly in the Bihar is as under:-

Period

Outlay

2009-14

₹1,132 Cr./year

2026-27

₹10,379 Cr. (More than 9 times)

  

Track construction:

The details of commissioning/laying of new track falling fully/partly in the State of Bihar is as under:-

Period

New Track Commissioned

Average Commissioning of new tracks

2009-14

318 Km

63.6 Km/year

2014-26

2,034 Km

169.5 Km/year (More than 2.5 times)

 

Projects sanctioned:

As on 01.04.2026, 59 projects (32 New Lines, 01 Gauge Conversions and 26 Doubling), covering a total length of 5,067 km, costing ₹96,651 crore, falling fully/partly in Bihar are sanctioned. The summary is as under:-

Category

No of sanctioned Projects

Total Length

 (in Km)

Length Commissioned till Mar'26
(in Km)

Total Exp upto Mar'26

(₹ in Cr)

New Lines

32

2,616

533

14,806

Gauge Conversion

1

69

52

544

Doubling/Multi-tracking

26

2,382

465

14,509

Total

59

5,067

1,050

29,860

 Recently completed projects:

Details of some of the recently completed projects falling fully/partly in Bihar are as under:-

SN.

Project 

Cost

(In Crores of Rs)

1

Patna bridge (28 Km)

3,310

2

Munger rail cum road Bridge (15 Km)

3,040

3

Kosi Bridge (22 Km)

863

4

Daniawan-Biharsharif new line (38 Km)

354

5

Chandan-Banka new line (40 Km)

496

6

Rampurhat-Mandarhill new line (130 Km)

908

7

Maharajganj-Masrakh new line (35 Km)

412

8

Rajgir-Tilaiya & Natesar-lslampur new line (67 Km)

726

9

Jaynagar-Narkatiaganj gauge conversion (260 Km)

967

10

Kaptanganj-Chhapra gauge conversion  (234 Km)

819

11

Sakri-Nirmali, Saharasa-Forbesganj gauge conversion   (206 Km)

2,113

12

Mansi-Saharsa, Saharsa-Purnia, Banmakhi- Bihariganj gauge conversion (169 Km)

752

13

Sahibganj-Pirpainti doubling (23 Km)

129

14

Maheshkunt-Thanabihpur doubling (32 Km)

115

15

Hajipur-Ramdayalu Nagar doubling (48 Km)

367

16

Pirpainti-Bhagalpur doubling (51 Km)

493

17

Kiul-Gaya doubling (124 Km)

2,462

18

Hajipur-Bachwara doubling (72 Km)

930

19

Araria-Galgalia (Thakurganj) new line  (110 Km)

2,132

20

Samastipur-Darbhanga Doubling (38 Km)

874

Ongoing projects:

Some of the projects falling fully/partly in the State of Bihar which have been taken up are as under:

SN.

Project

Cost (Rs. in Cr.)

1

Sakri-Hasanpur new line (76 Km)

802

2

Fatuha-lslampur new line (167 Km)

3,158

3

Koderma-Tilaiya new line (65 Km)

2,287

4

Hajipur-Sagauli new line (151 Km)

2,820

5

Araria-Supaul new line (96 Km)

2,170

6

Kursela-Bihariganj new line (58 Km)

194

7

Pirpainti-Jassidih new line (97 Km)

2,700

8

Chhitauni-Tumkuhi Road new line (59 Km)

1,881

9

Jalalgarh-Kishanganj new line (51 Km)

407

10

Sitamarhi-Nirmali new line (189 Km)

2,833

11

Bihta-Aurangabad new line (120 Km)

3,606

12

Gaya-Chatra and Gaya-Natesar new line (135 Km)

4,543

13

Sultanganj-Katuria new line (77 Km)

291

14

Jaynagar-Bijalpura Gauge conversion (69 Km)

900

15

Dhanbad-Sonnagar 3rd line (291 Km)

7,906

16

Sagauli-Valmikinagar Doubling (110 Km)

1,456

17

Muzaffarpur-Sugauli Doubling (101 Km)

1,745

18

Barauni-Bachwara 3rd & 4th line (32 Km)

486

19

Narkatiaganj-Darbhanga, Sitamarhi-Muzaffarpur doubling (256 Km)

4,080

20

Chhapra-Ballia Patch Doubling (65 Km)

1,046

21

Katihar-Kumedpur and Katihar-Mukuria Doubling
(65 Km)

943

22

Son Nagar-Andal Multitracking (749 Km)

12,334

23

Punarakh- Bhaktiyarpur New 4th line & balance 3rd line (28 Km)

422

24

Aluabari Road-Thakurganj Doubling (20 Km)

327

25

Bhagalpur-Jamalpur 3rd line (53 Km)

1,156

26

Bhagalpur-Dumka-Rampurhat doubling (177 Km)

3,169

27

Bakhtiyarpur-Rajgir-Tilaiya doubling (104 Km)

2,192

28

Bakthiyarpur-Fatuha 3rd and 4th line (24 Km)

931

29

Punarakh-Kiul 3rd and 4th line (50 Km)

2,668

30

Kiul-Jhajha 3rd Line (54 Km)

962

31

Mansi-Saharsa doubling (44 Km)

499

 

Completion of Railway projects/s depends on various factors which include the following:

  • Land acquisition by State Government

  • Forest clearance 

  • Shifting of infringing utilities

  • Statutory clearances from various authorities 

  • Geological and topographical conditions of area

  • Law and order situation in the area of project site

  • Number of working months in a year for particular project site etc.

 All these factors affect the completion time and cost of the project/s.  

*****

(This statement was given by MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND ELECTRONICS & INFORMATION TECHNOLOGY SHRI ASHWINI VAISHNAW in a written reply to a question in Lok Sabha on 12.08.2026)