|
Sr. No.
|
NH No.
|
Details of Project
|
Lanes
|
Status
|
|
1
|
24
(New NH-9)
|
Pkg.-I: From km 0.00 to km 8.716 (Nizamuddin to U.P. Gate) in Delhi
|
6-Lane Expressway + 8 National Highway
|
The project has been completed in June, 2018.
|
|
2
|
24
(New NH-9)
|
Pkg.-II: From km 8.716 to km 28.000 (U.P. Border to Dasna) in UP
|
6-Lane Expressway + 8 National Highway
|
The present physical progress is 53%. The scheduled date of completion is May, 2020.
|
|
3
|
24
(New NH-9)
|
Pkg.-III: From km 28.000 to km 50.270 (Dasna to Hapur Bypass) in U.P.
|
6-National Highway
|
The present physical progress is 93%. Expected date of completion is 31st July, 2019.
|
|
4
|
New Alignment
|
Pkg.-IV: Greenfield alignment from Dasna to Meerut (km 27.740 to km 59.777) in UP.
|
6-Lane Expressway
|
The present physical progress is 51%. Expected date of completion is 31st December, 2019.
|