Prime Minister Shri. Narendra Modi
today dedicated to the nation the 765 kv Ranchi-Dharmjaygarh-Sipat Transmission
Line connecting the Eastern and Western parts of the country.
The transmission link was inaugurated online at
Prabhat Tara, Dhurwa, in Ranchi.
In a slew of inaugurations, Mr.
Narendra Modi also initiated the commencement of work of 3x660 MW North
Karanpura Super Thermal Power Project of NTPC.
The Governor of Jharkhand Shri Sayed Ahmed, the
Chief Minister of Jharkhand Shri Hemant Soren, the Union Minister for
Communications and IT Shri Ravi Shankar Prasad, the MoS(I/c) for Power, Shri
Piyush Goyal, and the MoS(I/c) for Petroleum and Natural Gas, Shri Dharmendra
Pradhan and Minister of
State for Social Justice and Empowerment , Shri Sudarshan Bhagat
were present on the occasion.
Addressing the
gathering, the Prime Minister asserted
that if India has to emerge as a developed nation, then no part of the country
can remain weak and underdeveloped He said eastern India has remained
underdeveloped, and growth should be balanced across north, south, east and
west - so that common people across the country can enjoy the fruits of
development in equal measure.
The Prime Minister pointed out that Jharkhand would benefit enormously by yesterday’s Cabinet decision to increase
royalty rates on minerals. Shri. Narendra Modi also announced that work would
commence shortly on the Jagdishpur-Phoolpur-Haldia gas pipeline - which would
become a major source of energy for eastern India.
Initiating the commencement of work at the North
Karanpura Super Thermal Power Plant, the Prime Minister said this power plant
would dispel darkness not only from Jharkhand but also from different parts of
the country.
Addressing the function on this
occasion, Union Energy Minister Shri. Piyush Goyal said that though NTPC
project in Jharkhand was started more than ten years back but because of lack
of coal linkage and several other issues, the power project could not take off
during the last ten years. Mr. Goyal also announced that the centre is keen to
provide separate feeder line to farmers in the state. Referring to the
underground fire in Jharia coalfield, Mr. Goyal announced that the Union Government
will provide Rs. 100 crore for controlling the underground fire. The Union Energy
Minister expressed concern that despite huge stock of coal, Jharkhand is not
getting adequate energy. He expressed hope that very soon the state will have
adequate supply of electricity to provide continuous power supply for every
sector in the state. This will create a new era of overall development of
Jharkhand.
765kV Ranchi-Dharamjaygarh-Sipat Inter-regional
transmission line:
Power
Grid Corporation of India Ltd. has implemented the 765kV
Ranchi-Dharamjaygarh-Sipat Inter-regional transmission line at a total cost of
Rs. 1600 Crore. The 392 km line has been planned as a part of transmission
scheme associated with DVC generation projects to evacuate/transfer power from
Eastern Region to Western part of India. Two new 765 kV sub-stations have been
built at Ranchi in Jharkhand and Dharamjaygarh in Chhattisgarh.
The benefits of the project include augmentation
of inter-regional capacity of Eastern Region with Western Region, thereby
facilitating exchange of surplus power between Eastern Region and Western
Region, depending on the availability of generation and load demand in each
region.
NTPC’s North Karanpura Super Thermal Power project in
Jharkhand :
The NTPC project,
which is the first of its kind in the state is based on latest eco –friendly
and efficient supercritical technology for power generation.
Air Cooled condensers have also been specified for these units for the first
time in NTPC, to make itself future ready for challenges in meeting water
requirement of power plants.
Former Prime
Minister, Shri Atal Bihari Vajpayee laid the foundation stone for the project
on 6th March 1999. Due to some technical reasons the work could not
commence. Subsequently, Cabinet Committee on
Investment (CCI), cleared the North Karanpura project on 20th February
2013 and decided in-principle to restore the original coal linkage granted to
the project. Ministry of Coal restored the coal linkage on May 2013
with the stipulation that the coal supply will commence during the 13th Five
Year Plan.
NTPC has taken
necessary measures to initiate the project activities for swift implementation
of North Karanpura project by awarding turnkey EPC (Engineering Procurement and
Construction) package to BHEL in Feb 2014. All the units are based on
supercritical technology which is an efficient and environment friendly
technology for power generation. Air Cooled condensers have also been specified
for these units for the first time in NTPC, to make itself future ready for
challenges in meeting water requirement of power plants.
NTPC is already
supplying about 298 MW power to Jharkhand from its various power stations.
Jharkhand will get around 230 MW from this project. In addition 354 MW has been
allocated by Ministry of Power to Jharkhand from other new and under
construction projects of NTPC.
RM/ND