The Cabinet
Committee on Economic Affairs, chaired by the Prime Minister Shri Narendra Modi,
has given its approval for setting up of over 2,000 MW of Grid-Connected Solar
PV Power Projects on Build, Own and Operate basis by Solar Power Developers
(SPDs) with Viability Gap Funding (VGF) under Batch-III of Phase-II of the
Jawaharlal Nehru National Solar Mission (JNNSM).
This would help
in:
o Creation of additional 2000 MW capacity of Grid-connected solar PV power
generation projects.
o Employment generation of about 12,000 people in rural and urban areas.
o Reduction of about 3.41 Million T of CO2 emissions into the environment
every year.
The total investments expected under this scheme is about Rs 12,000 crore. The estimated requirement of funds to provide VGF
for 2,000 MW capacity solar projects is estimated to be Rs. 2100 crore [Rs 1 crore / MW for open
category and Rs 1.31 crore / MW for Domestic Content
Requirement (DCR) Category]. This includes handling charges to SECI @ 1 percent
of the total grant disposed.
The phasing of
investment is estimated as under:
|
Year
|
Amount (Rs.
Cr.)
|
|
2016-17
|
1000
|
|
2017-18
|
260
|
|
2018-19
|
210
|
|
2019-20
|
210
|
|
2020-21
|
210
|
|
2021-22
|
210
|
|
Total
|
2100
|
The tenders will
be State-specific based on the demand from particular State. States/Union
Territories/Discomes/State Utilities are the
beneficiaries. This will also facilitate to create employment and
infrastructure in the States. Installation of 2000 MW Solar PV plants will
generate about 3,320 Million Units per year, which caters power to almost one
Million Households.
The Viability
Gap Funding (VGF) scheme will be implemented for setting up over 2000 MW
capacity of grid connected solar power projects by solar power developers on
Build, Own and Operate basis through open and transparent competitive bidding
to provide solar power at a pre-defined tariff of Rs. 5.43 per kWh for the
first year, with escalation of 5 paisa per kWh each year till the tariff reaches
the level of Rs. 6.43 per kWh. This would take 21 years and the tariff,
thereafter, would remain fixed at Rs. 6.43 per kWh. The levelized
tariff would be Rs. 5.79 per kWh. The overall effort is to continuously reduce
Government financial support for grid connected solar power as the prices of
solar power comes down.
The Scheme will
be implemented by Solar Energy Corporation of India (SECI) as per Ministry of
New and Renewable Energy (MNRE) Guidelines. Solar Energy Corporation of India
(SECI) shall prepare necessary bidding documents for inviting the proposals for
setting up of projects on a competitive bidding through e-bidding. SECI will
enter into Power Purchase Agreement (PPA) with the selected developers and the
Power Sale Agreement (PSA) with the buying entities.
Requisite funds
for provision of the VGF support will be made available to MNRE from the
National Clean Energy Fund (NCEF), operated by Ministry of Finance.
Out of 2000 MW,
250 MW will be developed with mandatory condition of solar PV cells and modules
made in India. This will be called the DCR category and remaining 1,750 MW will
be in open category. Some other important features are as follows:
a) Project
Locations: Projects could be set up in the Solar Parks being developed under a
separate MNRE Scheme and also at other locations, which could be selected by bidders on their own.
b) Commissioning
period would be 13 months from the date of signing of PPAs.
c) The VGF is to
be disbursed in six trenches; 50 percent after commissioning and balance 50
percent at the rate of 10 percent at the end of each year subsequently for the
next 5 years,
d) Tenders will
be State-specific based on the demand from particular a State.
e) Due to
competitive bidding, there may be savings in the VGF amount of Rs 2100 crore. In that case, the total capacity will be increased
from 2000 MW, so that, maximum capacity can be set up in the VGF of Rs 2100 crore after accounting for grant to be given for payment
security mechanism.
f) Bidders will be free to avail fiscal incentives like Accelerated
Depreciation (AD), concessional customs and excise duties, tax holidays, etc.
available for such projects. However, no bidders will be allowed to claim both
AD and VGF.
Background:
The Jawaharlal
Nehru National Solar Mission (JNNSM) was launched in January 2010 by the
Government of India with a target to setup 20,000 MW of grid connected solar
power by 2022.
In addition to
Government of India, several States have taken initiatives and come out with
solar policies to support setting up solar power projects. Amongst others
Andhra Pradesh, Karnataka, Tamil Nadu, Telangana,
Uttar Pradesh and Uttarakhand have come out with
tenders for procurement of solar power recently.
AKT/NT/SBP