08-December-2014 15:47 IST
Government Launches Major Initiatives to Upgrade National Highways

The Minister of State for Road Transport and Highways, Shri Pon

The Minister of State for Road Transport and Highways, Shri Pon. Radhakrishnan informed the Rajya Sabha today that Government has launched major initiatives to upgrade and strengthen 54,478 kms of National Highways (NH) in the country including the State of West Bengal through various phases of National Highways Development project (NHDP), out of which 22,345 km have been completed and 12,625 km are under various stages of implementation till 31st October 2014. Balance length will also be completed in a phased manner. These projects are being implemented through various mode of delivery and through various agencies and various local factors are also often affecting these constructions adversely. Therefore, timelines for completion cannot be determined at this stage.

 

Model Concession Agreement (MCA) lays the guiding principle for safety requirements on the project highway entrusted to National Highways Authority of India (NHAI), that Safety requirements apply to all phases of construction, operation and maintenance with emphasis on identification of factors associated with accidents, consideration of the same, and implementation of appropriate remedial measures. The Concessionaires are also required to abide by the Manual for Safety in Road Design, issued by the Government, insofar as they relate to safety of the users. The Concessionaires have to make adequate arrangements during the Construction Period for the safety of workers and road users and notify NHAI and the Independent Engineer. MCA also elaborates safety requirements applicable to phases of operation and maintenance of the project. For carrying out safety audit of the project highways, Road Safety Cell of NHAI has appointed Safety Consultants. The sSafety Consultant has to collect and analyse the accident data for the preceding two years and study the Safety Report for the Development Period and inspect the Project Highways to assess the adequacy of safety measures.

 

Ā DETAILS OF NATIONAL HIGHWAY PROJECTS UNDER VARIOUS STAGES OF IMPLEMENTATION, STATE-WISE

 

 

Sl.

No.

Name of the Project

State

NH No

Total Length (in km)

Total Project Cost
( Rs. in crore)

Project Funded By

1

Gundla Pochampalli to BowenpalliĀ  Shivarampalli to ThondapalliĀ  (NS-23/AP)

Andhra Pradesh

7

23.1

71.57

NHAI

2

Vijayawada-Gundugolanu Section

Andhra Pradesh

5

103.59

1684

BOT

3

Six Laning of Nellore-Chilkaluripet

Andhra Pradesh

5

183.52

1535

BOT


 

4

Six-Laning of Gundugolanu Rajamundry

Andhra Pradesh

5

120.741

1617

BOT

5

Six-Laning of Anandapuram-Visakapatnam-Anakapalli

Andhra Pradesh

5

58.222

839

BOT

6

Chilkaluripet - Vijayawada (Six lane)

Andhra Pradesh

5

82.5

572.3

BOT

7

Vijayawada-Machhlipatnam

Andhra Pradesh

9

64.611

606

BOT

8

Kudapa-Mydukur-Kurnool

Andhra Pradesh

18

188.752

1585

BOT

9

Nalbari to Bijni (AS-6)

Assam

31

25

225

NHAI

10

Nalbari to Bijni (AS-7)

Assam

31

27.3

208

NHAI

11

Brahmputra Bridge (AS-28)

Assam

31

5

217.61

NHAI

12

Bijni to Assam/WB Border (AS-10)

Assam

31C

33

237.8

NHAI

13

Bijni to Assam/WB Border (AS-11)

Assam

31C

30

195

NHAI

14

Bijni to Assam/WB Border (AS-12)

Assam

31C

30

230

NHAI

15

Guwahati to Nalbari (AS-4)

Assam

31

28

175.96

NHAI

16

Guwahati to Nalbari (AS-5)

Assam

31

28

198.16

NHAI

17

Silchar-Udarband (AS-1)

Assam

54

32

154.57

NHAI

18

Harangajo to Maibang (AS-21)

Assam

54

26

386.1

NHAI

19

Harangajo to Maibang (AS-22)

Assam

54

24

363.74

NHAI

20

Harangajo to Maibang (AS-23)

Assam

54

16

280

NHAI

21

Maibang to Lumding (AS-27)

Assam

54

21

200

NHAI

22

Maibang to Lumding (AS-26)

Assam

54

23

167.64

NHAI

23

Maibang to Lumding (AS-25)

Assam

54

28

385.13

NHAI

24

Maibang to Lumding (AS-24)

Assam

54

15

280.13

NHAI

25

Dharamtul to Sonapur (AS-19)

Assam

37

25.5

200

NHAI

26

Dharamtul to Sonapur (AS-20)

Assam

37

22

160

NHAI

27

Sonapur to Guwahati (AS-3)

Assam

37

19

245

NHAI

28

Nagaon to Dharmatul (AS-2)

Assam

37

25

264.72

NHAI

29

Forbesganj-Simrahi (BR-3)

Bihar

57

34.87

332.94

NHAI

30

Kotwa to Dewapur (LMNHP-10)

Bihar

28

38

240

WB/ NHAI

31

Deewapur to UP/Bihar Border (LMNHP-9)

Bihar

28

41.085

300

WB/ NHAI


32

2 Laning with paved shoulder of Chhapra - Rewaghat - Muzaffarpur section of NH-102

Bihar

102

73.08

415.71

NHAI

33

Patna- Muzzaffarpur

Bihar

19 & 77

63

671.3

Annuity

34

Four laning of Patna - Gaya - Dhobi section of NH-83

Bihar

83

127.2

1027

JICA ODA

35

4 Laning of Khagaria-Bakhtiarpur

Bihar

31

112.982

1635.33

BOT

36

2-Laning with PS khagaria - Purnea

Bihar

31

140

664

Annuity

37

Patna - Bakhtiarpur

Bihar

30

50.6

574

BOT

 

38

2-Laning with PS Motihari-Raxaul (Approved Length 67 Km)

Bihar

28A

68.79

375.09

BOT

39

2 Laning of Forbesganj-Jogwani(Approved Length 13 Km)

Bihar

57A

9.258

73.55

Annuity

40

2-Laning with PS Gopalganj-Chappra

Bihar

85

92

325

Annuity

41

4 Laning of Chappra-Hajipur(Approved Length 153 Km)

Bihar

19

65

575

Annuity

42

Patna - Buxar

Bihar

30 & 84

124.85

1129.11

BOT

43

2 Laning of Muzaffarpur - Sonbarsa(Approved Length 89 Km)

Bihar

77

86

511.54

Annuity

44

2 Laning of Mokama-Munger(Approved Length 70 Km)

Bihar

80

69.27

351.54

Annuity

45

2-Laning with paved shoulder of Muzaffarpur - Barauni

Bihar

28

107.56

356.4

BOT

46

Varanasi-Aurangabad

Bihar/

Uttar Pradesh

2

192.4

2848

BOT

47

Six-Laning of Aurangabad-Barwa Adda

Bihar/

Jharkhand

2

221.346

2340

BOT

48

Four laning of Orissa/Chattisgarh Boarder - Aurang section

Chattisgarh

6

150.4

1232

BOT

49

Aurang - Raipur

Chattisgarh

6

43.485

190

BOT

50

4 laning of end of Durg bypass to Chhattisgarh Maharashtra Border section

Chattisgarh

6

82.6

465

BOT

51

Construction Maintenance and operation of Durg bypass

Chattisgarh

6

18

123

BOT

52

4/6 Laning of Maharastra/Goa Border - Panaji Goa/KNT Border

Goa

17

139

1872

BOT

53

Panji-Goa/Karnatka Border

Goa

4A

69

471

BOT

54

Ahmedabad to Vadodara Section

Gujarat

8

102.3

2125.24

BOT

55

Samaikhiali-Gandhidham

Gujarat

8A

56.16

805.39

BOT

56

Vadodara-Surat Section

Gujarat

8

6.74

503.16

NHAI

57

Gujarat/Maharashtra Border-Surat - Hazira PortĀ  Section

Gujarat

6

132.9

1509.1

BOT

58

4 laning of Jetpur-Somnath section of NH-8D (approved length 127.6)

Gujarat

8D

123.45

828

BOT

59

4 Laning of Ahmedabad to Godhara (Approved Length 210 Km)

Gujarat

59

117.6

1008.5

BOT

60

4 Laning of Godhara to Gujarat /MP Border(Approved Length 210 Km)

Gujarat

59

87.285

785.5

BOT

61

Kandla - Mundra Port(Approved Length 73 Km)

Gujarat

8A

71.4

953.88

BOT

62

Surat - Dahisar (Six lane)

Gujarat/ Maharashtra

8

239

1693.75

BOT

63

Construction of Flyover at Bahalgarh ch.41.210 and construction of additional 2-lane bridge near Rasoi Ch.32.28 on NH-1 in the state of Haryana

Haryana

1

0

77.97

NHAI

64

Four laning of Kaithal - Rajasthan border

Haryana

65

166.25

1393

BOT

65

4-Laning of Rohtak-Jind (Approved Length 45 Km)

Haryana

71

48.6

283.25

BOT

66

4 Laning of UP/Haryana Border-Yamunanagar-Saha-Barwala- Panchkula

Haryana

73

107

934.94

BOT

67

Rohtak - Bawal(Approved Length 97 Km)

Haryana

71

83.65

650

BOT

68

4-Laning of Punjab/Haryana Border-Jind

Haryana

71

68

438.75

BOT

69

Delhi/Haryana BorderĀ  to Rohtak

Haryana

10

63.49

486

BOT

70

4-Laning of Rohtak - Hissar Section

Haryana

10

98.81

959.25

BOT

71

Bhatinda-Suratgarh (ROB)

Haryana

32-B

0

47.75

NHAI

72

Panipat - JalandharĀ  (Six lane)

Haryana/

Punjab

1

291

2288

BOT

73

Gurgaon - Kotputli - Jaipur (Six lane)

Haryana/

Ā Rajasthan

8

225.6

1673.7

BOT

 

74

Delhi - Agra(Approved Length 180.3 Km)

Haryana/

Uttar Pradesh

2

179.5

1928.22

BOT

75

Four Laning of Kiratpur-Ner Chowk Section

Himachal Pradesh

21

84.32

1916.79

BOT

76

Jammu - Udhampur

Jammu Kashmir

1A

65

1813.76

Annuity

77

Srinagar to Banihal

Jammu Kashmir

1A

67.76

1100.7

Annuity

78

Quazigund-Banihal

Jammu Kashmir

1A

15.25

1987

Annuity

79

Chenani-Nashri

Jammu Kashmir

1A

12

2159

Annuity

80

4 Laning of Barhi - Hazaribagh(Approved Length 40 Km)

Jharkhand

33

41.314

398

BOT

81

Hazaribagh-Ranchi

Jharkhand

33

75

625.07

Annuity

82

Ranchi - Rargaon - Jamshedpur

Jharkhand

33

163.5

1479

Annuity

83

Six-laning of Barwa Adda-Panagarh

Jharkhand/

West Bengal

2

122.88

1665

BOT

84

4-Laning of Hospet-Bellary-Karnataka/AP Border

Karnataka

63

95.44

910.08

BOT

85

4-Laning of Goa/Karnataka Border-Kundapur Section

Karnataka

17

187.24

1655.01

BOT

86

MH/ KNT Border Sangareddy

Karnataka

9

145

1266.6

BOT

87

4-Laning of Hoskote-Dobbaspet

Karnataka

207

80.02

720.69

BOT

88

Hospet - Chitradurga

Karnataka

13

120.03

1033.66

BOT

89

Belgaum-Dharwad(Approved Length 111 Km)

Karnataka

4

80

480

BOT

90

4 Laning of Belgaum-Khanpur Section(Km 0.00 to Km 30.00) and 2 Laning with paved sholuders of khanpur-Knt/Goa border.(Km 30.00 to Km 84.120)

Karnataka

4A

81.89

359

BOT

91

4 Laning of Mulbagal - Karnataka / AP border-Approved Length (11 Km)

Karnataka

4

22.18

141.11

BOT

92

Kundapur-Surathkal & Mangalore-KNT/Kerala Border

Karnataka

17

90

671

BOT

93

Devihalli-Hassan(Approved LengthĀ  73 Km)

Karnataka

48

77.23

453

BOT

94

Four lanning of Walayar - Vadakkancherry section

Kerala

47

54

682

BOT

95

NH Connectivity to ICTT Vallarpadam

Kerala

47C

17.2

557

NHAI

96

4-lanning of Kannur Vengalem Kuttipuram (Package -I)

Kerala

17

83.2

1366

BOT

97

KNT/Kerala Border to Kanuur Section(Approved Length 286.3)

Kerala

17

126.6

1157.16

BOT

98

4-lanning of Kannur Vengalem Kuttipuram (Package -II)

Kerala

17

81.5

1312

BOT

99

Charthalai-ochira

Kerala

47

83.6

1535

BOT

100

Six lanning of Vadakkancherry - Thrissuresection

Kerala

47

30

617

BOT

101

Rajmarg Choraha to Lahknadon (ADB-II/C-8)

Madhya Pradesh

26

54

251.03

ADB

102

Jabalpur to Lakhanadone

Madhya Pradesh

7

80.82

776.76

BOT

103

Four laning of Jabalpur-Katni-Rewa Section

Madhya Pradesh

7

225.686

1895.45

BOT

104

Four laning of Gwalior-Shivpuri

Madhya Pradesh

3

125.03

1055

BOT

105

Four laning of Shivpuri-Dewas

Madhya Pradesh

3

330.21

2815

BOT

106

Indore-Dewas(Approved Length 55 Km)

Madhya Pradesh

3

45.05

325

BOT

107

Bhopal-Sanchi(Approved Length 40 Km)

Madhya Pradesh

86Ex

53.78

209

Annuity

108

Indore-Jhabua-Gujrat/MP (Approved Length 168)

Madhya Pradesh

59

155.15

1175

BOT

109

4 Laning of Obedullaganj-Betul Section

Madhya Pradesh

69

125

912

BOT

110

Dholpur - Morena Section (including chambal bridge) NS-1/RJ-MP/1

Madhya Pradesh/ Rajasthan

3

10

232.45

NHAI

111

4 Laning of Nagpur Betul

Madhya Pradesh/ Maharashtra

69

176.3

2498.76

Annuity

112

2-laning with paved shoulders of Multai-Chhindwara-Seoni section & Narsinghpur-Amarwara-Umranala-Saoner section

Madhya Pradesh / Maharashtra

69A & 26B

418

1565

NHAI

 

113

Gwalior - Jhansi

Madhya Pradesh/ Uttar Pradesh

75

80

604

Annuity

114

Borkhedi-Jam (NS-22/MH)

Maharashtra

7

27.4

110

NHAI

115

Four laning from MP/Maharashtra border to Nagpur I/C Kamptee Kanoon and Nagpur bypass

Maharashtra

7

95

1170.52

BOT

116

4-Laning of Amravati-Jalgaon

Maharashtra

6

275.225

2537.81

BOT

117

4-Laning of Jalgaon-Maharashtra/Gujrat Border

Maharashtra

6

208.844

1968.37

BOT

118

4-Laning of Khed - Sinnar Section

Maharashtra

50

137.946

1348.2

BOT

119

4-Laning of Solapur - Yedishi section of NH-211

Maharashtra

211

100

972.5

BOT

120

Four Laning of AurangabadĀ  - Yedishi

Maharashtra

211

190.2

1871.34

BOT

121

4-Laning of Solapur - Maharashtra/ Karnatka Section

Maharashtra

9

100.06

923.04

BOT

122

Pune – Satara(Approved Length 145)

Maharashtra

4

140.35

1724.55

BOT

123

Pimpalgaon - Nasik - Gonde

Maharashtra

3

60

940

BOT

124

Nagpur-Wainganga Bridge (Approved Length - 60 Km)

Maharashtra

6

45.43

484.19

BOT

125

Talegaon-Amravat(Approved Length 58Km)

Maharashtra

6

67.8

567

BOT

126

Nagpur - kondhali

Maharashtra

6

40

168

BOT

127

Pune-Sholapur Pkg-I(Approved Length Pkg I & II 170 Km)

Maharashtra

9

110.05

1110

BOT

128

Pune-Sholapur Pkg-II(Approved LengthĀ  I & II 170 Km)

Maharashtra

9

105

835

BOT

129

Panvel-Indapur

Maharashtra

17

84

942.69

BOT

130

Wadner-Devdhari (NS-60/MH)

Maharashtra

7

29

193.45

NHAI

131

Kelapur-Pimpalkhatti (NS-62)

Maharashtra

7

22

130.81

NHAI

132

4 Laning of Solapur - Bijapur

Maharashtra/ Karnataka

13

110.542

1002.48

BOT

133

2 Laning of Jowai -Meghalaya/AssamĀ  Border (Approved length 109 Km)

Meghalaya

44

102

390

BOT

134

Jorbat-Barapani

Meghalaya

40

61.8

536

Annuity

135

2/4 Laning of Talchar -Dubari-Chandikhole section of NH-200 from Km 301.89 to Km 427.85 including km 8.5 to Km 14.86 of NH-23

Odisha

23 &200

132.35

996.37

NHAI

136

4-Laning of Cuttak - Angul

Orissa

42

112

1123.69

BOT

137

4-Laning of Angul - Sambalpur

Orissa

42

153

1220.32

BOT

138

Rehabitation and Upgradation to Birmitrapur to Barkote (4 Lane-75.66 Km)-(2 Lane-49.955 Km)

Orissa

23

125.615

778.15

BOT

139

Six Laning of Chandikhol-Jagatpur-Bhubaneswar(Approved Length 61 Km)

Orissa

5

67

1047

BOT

140

Bhubneshwar-Puri(Approved Length 59 Km)

Orissa

203

67

500.29

BOT

141

Panikholi-Rimoli (Approved Length 106 Km)

Orissa

215

163

1410

BOT

142

Sambalpur-Baragarh-Chattisgarh/Orrisa Border

Orissa

6

88

909

BOT

143

Rimoli - Roxy - Rajamunda(Approved Length 163Km)

Orissa

215

96

586

BOT

144

Jalandhar - Amritsar

Punjab

1

20

523.85

NHAI

145

Pathankot to Jammu & Kashmir Border (NS-36/J&K)

Punjab

1A

19.65

97.73

NHAI

146

Four lanning of Ludhiyana- Talwandi section

Punjab

95

78

479

BOT

147

Amritsar - Pathankot (Approved Length 101Km)

Punjab

15

106

705

BOT

148

Kota Bypass (RJ-4)

Rajasthan

76

26.42

250.39

NHAI

149

Chambal Bridge (RJ-5)

Rajasthan

76

1.4

281.31

NHAI

150

2-laning with paved shoulders of Bheem to Parasoli section (Package-I)

Rajasthan

148D

33

100.29

MORTH

151

2-laning with paved shoulders of Bheem to Parasoli sectionĀ  (Package-II)

Rajasthan

148D

36.267

113.8

MORTH

152

Kishangarh-Ajmer-Beawar

Rajasthan

8

93.56

795

BOT

153

Reengus - Sikar

Rajasthan

11

43.887

333.51

Annuity

154

Jaipur-Reengus(Approved Length 52.65 Km )

Rajasthan

11

54

267.81

BOT

155

Kota - Jhalawar

Rajasthan

12

88.09

530.01

BOT

156

Deoli - Kota

Rajasthan

12

83

593

BOT

157

Jaipur-Tonk - Deoli(Approved Length 148.77 Km )

Rajasthan

12

150

792.06

BOT

158

Beawar-Pali-Pindwara (Approved Length - 246 Km)

Rajasthan

14

244.12

2388

BOT

159

Padi - Dahod

Rajasthan

113

85.58

279.14

NHAI

160

Two laning with Paved shoulder of KarauIi – Dholpur

Rajasthan

11B

100.9

425.19

NHAI

161

Jaisalmer - Barmer

Rajasthan

15

131.41

482.27

NHAI

162

Jodhpur - Barmer section of Package -I

Rajasthan

112

85.61

264.72

NHAI

163

Jodhpur - Barmer section of Package -II

Rajasthan

112

74.1

206.12

NHAI

164

Bikaner - Phalodi section to Four laning from km.4.200 to km 55.25 and Two-lane paved shoulder from 55.25 to km.163.500

Rajasthan

15

160.3

822.9

BOT

165

Phalodi -Jaisalmer section of NH-15 to two/four lane with PS

Rajasthan

15

160.45

 

NHAI

166

2-Lane with paved shoulder with provision of Capacity Augmentation of Rajasthan Border-Fatehpur-Salasar Section

Rajasthan

65

154.141

530.07

BOT

167

4-Laning of Rajsamand-Gangapur-Bhilwara

Rajasthan

758

87.25

677.79

BOT

168

2-Laning with PS of Jhalawar-Rajasthan/M.P.Border

Rajasthan

12

62.16

177.32

NHAI

169

2-Laning with PS of Lambia-Jaitran-Raipur

Rajasthan

458

52.8

158.04

NHAI

170

Widening & strengthening to 2-Laning with PS of Raipur-Jassa Khera

Rajasthan

458

32.36

149.34

NHAI

171

Widening & strengthening to 2-Lane with PS of Nimbi Jodha-Degana-Merta City Section

Rajasthan

458

139.9

368.15

NHAI

172

2-Laning with PS of Bhilwara-Ladpura section

Rajasthan

758

67.75

240.1

NHAI

173

2-Laning with paved shoulder ofĀ  Rehabitation and augmentation of the Gulabpur-Uniara Section

Rajasthan

148D

214

523.87

NHAI

174

4 Laning of Gomti Chauraha - Udaipur

Rajasthan

8

79.31

914.5

BOT

175

Six Laninig of Kishangarh – Udaipur-Ahmedabad

Rajasthan/

Gujrat

79A, 79, 76 & 8

555.5

5387.3

BOT

176

Chengapalli to Coimbatore Bypass and End of Coimbatore Bypass to TN/Kerala Border

Tamil Nadu

47

54.83

852

BOT

177

New 4-Lane Elevated Road from Chennai Port - Maduravoyal

Tamil Nadu

4

19

1655

BOT

178

Chennai - Tada (Six lane)

Tamil Nadu

5

43.4

353.37

BOT

179

Walajapet-Poonamalee

Tamil Nadu

46

93

1287.95

BOT

180

Six Laning of Krishnagiri-Walajhapet section

Tamil Nadu

46

148.3

1250

BOT

181

Trichy - Karur

Tamil Nadu

67

79.7

516

BOT

182

2 Laning of Dindigul-Perigulam-Theni-Kumili

Tamil Nadu

220

134

485

Annuity

183

2-Laning of Krishnagiri-Tindivanam (Approved Length 170 Km.)

Tamil Nadu

66

176.51

624

Annuity

184

Two Laning of Trichy - Karaikudi and Trichy Bypass(Approved Length 100 Km)

Tamil Nadu

210 & 67

110.372

374

Annuity

185

Tanjore - Trichy

Tamil Nadu

67

56.49

280

BOT

186

4 Laning of Coimbatore-Mettupalayam

Tamil Nadu

67

53.93

592

BOT

187

Development of Adiquate Road Connectivity to Chennai -Ennore Port Connectivity

Tamil Nadu

SR

30.2

600

SPV

188

Six Laning of Hosur-Krishnagiri

Tamil Nadu

7

59.87

535

BOT

189

Tirupati -Tiruthani - Chennai(Approved Length 125.5 Km)

Tamil Nadu/

Andhra Pradesh

205

124.7

571

BOT

190

Thanjavur - Pudukottai section of NH-226

Tamil Nadu

226

55.22

283.27

NHAI

191

2 laning with paved shoulder of Karaikudi - RamanathapuramĀ  section of NH-210 including 500 m on SH-35 section of Madurai road

Tamil Nadu

210

80

451.58

NHAI

192

Thirumayam - Manamadurai section

Tamil Nadu

226

77.72

401.11

NHAI

193

Ganga Bridge to Rama Devi Crossing (UP-6)

Uttar Pradesh

25

5.6

201.66

NHAI

194

Jhansi to Lalitpur (NS-1/BOT/UP-2)

Uttar Pradesh

25, 26

49.7

355.06

Annuity

195

New 4 laning Agra Bypass (NS-1/UP-1)

Uttar Pradesh

2,3

32.8

465.5

NHAI

196

Lucknow - Kanpur (EW/3B)

Uttar Pradesh

25

16

54

NHAI

197

2-laning with paved shoulders of Tanda -Raebareli

Uttar Pradesh

232

155.9

495.78

MORTH

198

2-laning with paved shoulders of Raebareli - Banda section of NH-232

Uttar Pradesh

232

133.28

351.34

MORTH

199

Agra-Etawah Bypass

Uttar Pradesh

2

124.52

1207

BOT

200

Etawah -Chakeri (Kanpur)

Uttar Pradesh

2

160.2

1573

BOT

201

Ghaziabad-Aligarh (Approved Length 106 )

Uttar Pradesh

91

126

1141

BOT

202

Muradabad-Bareily (Approved Length 112)

Uttar Pradesh

24

121

1267

BOT

203

Bareily - Sitapur(Approved Length 134 Km)

Uttar Pradesh

24

151.2

1046

BOT

204

2-Laning with PS Agra - Aligarh

Uttar Pradesh

93

81.4

250.5

BOT

205

2-Laning with PS Kanpur - Kabrai

Uttar Pradesh

86

123

373.47

BOT

206

2-Laning with PS Raibariely to Allahabad

Uttar Pradesh

24B

119

291.36

BOT

207

2-Laning with PS Aligarh - Kanpur

Uttar Pradesh

91

268

723.68

BOT

208

Four laning of Meerut Bulandshahar

Uttar Pradesh

235

66.482

508.57

BOT

209

4-Laning of Lucknow - Sultanpur

Uttar Pradesh

56

125.9

1043.51

BOT

210

Lucknow - Raebareli

Uttar Pradesh

24B

70

635.9

Annuity

211

2-Laning with paved shoulder of Raebareli to Jaunpur

Uttar Pradesh

231

165.5

569.38

Annuity

212

Muzaffarnagar - Haridwar (Approved Length 77 )

Uttar Pradesh/ Uttaranchal

58, 72

80

754

BOT

213

2 laning with paved shoulder of Sitarganj - TanakurĀ  section of NH-125

Uttrakhand

125

52

 

NHAI

214

4-Laning of Kashipur-Sitarganj Section

Uttrakhand / Uttar Pradesh

74

77.2

605.84

BOT

215

2-Laning with PS Sitarganj Bareily Section

Uttrakhand/

Uttar Pradesh

74

74.46

301.04

NHAI

216

Rampur - Kathgodam

Uttaranchal

87

93.226

790

BOT

217

Haridwar - Dehradun (Approved Length 69)

Uttaranchal

72

39

478

Annuity

218

Dalkola Bypass

West Bengal

34

5.5

67

NHAI

219

4 Laning of Brahampore-Faraka

West Bengal

34

103

998.79

BOT

220

4 Laning of Faraka-Raiganj

West Bengal

34

103

1078.84

BOT

221

4 Laning of Raiganj-Dalkola

West Bengal

34

50

580.43

BOT

222

6-Laning of Dhankuni-Khargpur Section

West Bengal

6

111.4

1396.18

BOT

223

Barasat - Krishnanagar

West Bengal

34

84

867

Annuity

224

Krishnanagar - Berhampore

West Bengal

34

78

702.16

Annuity

225

4-Laning of Mahulia to Behragora to Kharagpur

West Bengal/ Jharkhand

33 & 6

127

940

BOT

KEY TO ABBREVIATION:

NHAI: National Highways Authority of India

BOT: Build-Operate-Transfer

WB: State Government of West Bengal

JICA: Japan International Co-operation Agency

MORTH: Ministry of Road Transport & Highways

 

*****

UM/SA/IK