Prime Minister’s Package for Bihar -2015 August 18, 2015

 

I. National Highways

A. Projects under process for award/bidding stage

 

Sl No.

NH No.

Project Name

Length (km)

TPC (in Rs. Cr.)

1

82

Biharsharif – Barbigha – Mokama section of NH-82,NHDP Phase-IV

55

399.54

2

30

4- laning of Patna-Koilawar section of NH 30

33

492

3

30&84

4- laning of Koilawar- Bhojpur section of NH-30 and NH-84

44

750

4

84

4 laning of Bhojpur-Baxar section of NH-84

48

595

5

31

4 laning of Bakhtiyarpur-Mokama section of NH-31

45

970

6

31

New 4-laned bridge across river Ganga at Mokama on NH-31

09

520

7

31

4lane of Simaria – Khagaria on NH-31,NHDP Phase-III

60

1062.58

8

30A

km 0.0-km 69.6 of Fatua-Harnaut-Barh section of NH-30A

71.8

591.2

9

104

Upgradation of Sheohar-Sitamarhi-Jaynagar-Narahiya (km 40-217) of NH 104 in three packages

179.95

701.44

10

106

Upgradation of Birpur-Bihpur (km 0-106) section of NH-106

105.2

575.34

11

85

2-laning with paved shoulder of Gopalganj - Chhapra section

94

748.06

12

28B

Widening and strengthening to 2-lane with paved shoulder & geometric improvement Betiah -Khushinagar Section  from km 25.00 to km 40.00 on EPC mode

15.00

88.61

13

28B

Strengthening and Widening to 2 Lane with Paved Shoulder from km  65 to 97 on EPC mode

33.00

206.80

14

102

2-laning with paved shoulder of Chhapra - Rewaghat - Muzaffarpur

73

420.58

15

133

Strengthening and Widening to 2 Lane with Paved Shoulder from km. 0.00 to 10.903

10.90

28.04

16

327A

Strengthening & Widening to 2 Lane with Paved Shoulder from km. 0.00 to 25.010 on EPC mode

25.01

77.55

17

327E

Strengthening & widening work of existing 2-Lane to two lane with paved shoulder from Km. 93.612 to Km. 98.000

4.39

64.52

18

57A

4 laning of Forbesganj-Jogbani section of NH-57A

9

200

19

83

4 laning of Patna - Gaya - Dobi section of NH 83 with JICA ODA loan assistance

127

1231.98

20

80

Construction of Bhagalpur Bypass

13

268

 

Total

1055.25

9991.24


B. Projects in the Pipeline

 

 

 

Sl.No.

Project

Length (Km)

Cost (Rs. Crore)

1

4 laning of Mokama-Khagariya section of NH-31

60

810

2

Bridge at Munger

18.69

2361.87

3

Development to 2-laned with paved shoulder of Maheshughat-Saharsa-Purnia section of NH-107

171

1000

4

Development of Manjholi-Chirkot section

65

700

5

4/6 laning of Patna Ring Road

65

1500

6

4 laning of Kishanganj Bypass at NH-31

20

250

7

4-laning of Munger-Mirzachowki section of Nh-80

120

1200

8

Development to 2-lane with paved shoulder of sections on NH-2C, NH80, NH81, NH99 and NH527 A.

116

680

9

Construction of MG Setu with JICA assistance

5.6

2800

10

Construction of bridge across Kosi river an Km 136 of NH-106

20

3000

 

Ensuring Connectivity Across Major Rivers

 

 

11

Bridge on river Ganga connecting Manihari in Bihar to Sahibganj in Jharkhand

 

2000

12

Bridge over river Sone  connecting Panduka(Nauhata) on NH-2C in Bihar and Shrinagar(Garhwa District) in Jharkhand

 

2000

13

A new 4-laned bridge on river Ganga parallel to existing MG Setu

 

5000

 

 

 

 

14

Improving Connectivity- Declaration of New National Highway and its development

 

436.58

6600

15

New National Highway connecting Buxar on NH-84-Chausa-Ramgarh-Mohania on NH-2

64

960

Sl.No.

Project

Length (Km)

Cost (Rs. Crore)

 

Projects under “Bharatmala Programme”

 

 

16

Roads connecting Raxaul and Sonbarsa (Parallel to Indo-Nepal Border)

90

1800

17

Chakia- Bargainia connectivity

50

1000

 

Projects For Improving Connectivity Of Places Of Religious Interest

 

 

18

Development of Rampur -Khajuriya -Kesariya end of NH-722 to 4 lane standard

58

1160

19

Development of Umgaon-Basopatti-Benipatti-Rahua-Madhubani-Rampatti-Awam-Laufa-Bheja-Supaul-Mehsi-Saharsa which connects Uchchait Bhagwati Sthan to Mehsi Taraesthan to 2 lane with paved shoulder or 4-lane standard with a bridge over river Kosi

160

5000

20

Development of Ram-Janki Marg as already declared recently part of which falls in Bihar from UP Bihar Border to Siwan-Madhubani-Sitamarhi-Indo-Nepal Border to 4 lane standard

200

4000

 

Rail Over Bridge (ROB)

 

 

21

12 ROBs

 

900

 

Total

1719.87

44721.87

 

Grand Total for NH

2775.12

54713.11


 

II. RURAL DEVELOPMENT

 

To complete about 22,500 km of PMGSY roads in Bihar

 

13820

III. Petroleum and Natural Gas

1

The Barauni Refinery would be expanded from 6 million tons to 9 million tons

 

12000

2

A Polyproplene Recovery Plant for petro-chemical products would also be set up.

 

3500

3

The implementation of the 617 Kms pipeline relating to Bihar in Jagdishpur-Haldia pipeline

 

2300

4

Raxaul Amlekhganj pipeline

 

200

5

Extension of Paradip-Haldia- Durgapur LPG pipeline

 

1800

6

New LPG Plant at Muzaffarpur

 

110

7

Creation of additional capacity for LPG plant at Patna

 

15

8

Implementation of BS IV fuel at Barauni Refinery

 

1500

9

Augumentation of Patna LPG Plant from 60 to 120 TMTPA

 

45

10

Upgradation of Purnea LPG Plant

 

6

 

Total

 

21476

IV. CIVIL AVIATION

1

Construction of a Greenfield Airport at Patna

 

2000

2

Development of Gaya Airport for Airbus 321-200 type of aircraft operations with new terminal building and apron, runway extension, CAT-I approach lighting

 

300

3

Development of Raxual Airport for ATR-72 / Q-400 type of aircrafts for VFR operations

 

250

4

Development of Civil Enclave at Purnea Airport for Airbus 321-200 type of aircraft

 

150

 

Total

 

2700

V. HIGHER EDUCATION

1

Establishment of a Central University near Bhagalpur at the historic site of Vikramshila University

 

500

2

Establishment of IIM, Bodh Gaya

 

500

 

Total

 

1000

VI. SKILL DEVELOPMENT

1

To train one lakh youth under Pradhan Mantri Kaushal Vikas Yojana

 

300

2

25,000 youth to be trained in Power sector

3

Mega Skill University in Bihar

 

1250

 

Total

 

1550


 

VII. AGRICULTURE

1

Upgradation of PUSA (Bihar) to the level of a Central Agricultural University

 

400

2

Development of fisheries

 

200

3

Farm Water Management (Micro irrigation, creation of water resources)

 

750

4

Development of Storage Capacity

 

600

5

Farm Mechanization

 

600

6

Seed production systems

 

300

7

National Research Centre on Integrated Farming System, Motihari, Bihar

 

30

8

Construction of new godowns at Supaul, Madhepura, Hazipur and Chakia Bazar

 

214

 

Total

 

3094

VIII. RAILWAYS

A.    Doubling/Tripling of Railway Line

1

Rampur Dumra - Tal - Rajendrapul Addl Bridge and doubling - 14 Km length

 

938

2

Hajipur - Bachwara  - 72 kms

 

756

3

Samastipur - Darbhanga 38 kms

 

399

4

Kiul - Gaya 123 kms

 

1292

5

3rd line between Dhanbad - Sonnagar (partly in Bihar ) - 429 kms

 

4725

B.     Railway Electrification

 1

Kiul - Tilaiya  87 kms

 

85

 2

Valmikinagar - Narkatiaganj-Sugauli-Muzaffarpur including Sugauli-Raxaul 240 kms

 

397

 3

Ammapali Halt - Kiul including Tinpahar-Rajmahal (Part of Bonidanga link cabin/Bonidanga-Barharwa- Sahibgang-Kiul section incl Tinpahar-Rajmahal)  Length 247 kms

 

279

 

Total

 

8870

IX. POWER

1

Construction of 1300 MW Power plant at Buxar {PIB has recently appraised the project and recommended Rs. 437 cr as pre-investment activity to kick start the project.}

 

10000

2

Deen Dayal Upadhyay Gram Vidyut Yojana

 

5880

3

Under Integrated Power Development Scheme (IPDS).

 

250

 

Total

 

16130


 

X. TELECOMMUNICATION – DIGITAL BIHAR

1

1000 new BTS (towers) to be installed in Bihar

 

250

2

Setting up of 2 new STPI centres (Software Technology Park of India) in Darbhanga and Bhagalpur and Rural BPO scheme for small towns and rural areas. This will help in promoting the IT entrepreneurs and start ups in Bihar.

 

20

3

Setting up 2 new NIELIT Centres in Muzaffarpur and Buxar apart from upgrading the existing centre in Patna, Medical Incubator at IIT Patna, Electronics and ICT Academy at NIT Patna.

 

14

4

Electronic Manufacturing clusters in Bihar for which 50% subsidy for greenfield and 75 % subsidy for Brownfield EMCs are available.

 

150

5

30 WiFi hotspots will be rolled out in Bihar, by BSNL at prominent tourist places such as Rajgir, Vaishali, Gaya, Nalanda and Patna

 

15

 

Total

 

449

XI. TOURISM

1

Vaishali and Bodhgaya development alongwith other places in buddhist circuit including Vikramshla

 

200

2

Sultanganj to Deoghar project

 

50

3

Patna Sahib under Prasad

 

50

4

Mahatma Gandhi Circuit

 

50

5

Ramayan Circuit

 

100

6

Jain Circuit including Champa puri

 

50

7

circuit for Mandar Hills and Ang Pradesh

 

50

8

IITTM chapter in Bihar

 

50

 

Total

 

600

XII. HEALTH

1

Upgradation of 3 Medical colleges at  Patna, Bhagalpur & Gaya under PMMSY in Bihar

 

600

 

Grand Total of the Package

 

1,25,003

 

·         Income Tax Relief on new capital investment in the form of Additional Investment Allowance and Higher Additional Depreciation for investment in backward areas of Bihar

Other Investments : Rs.40,657 crore

 

1.      Unspent amount of 2013 Special Plan (of Rs.12,000 crore) : Rs.8,282 crore

2.      Ongoing works of National Highways : Rs.12,375 crore

3.      Ultra Mega Power Project (UMPP) in Banka under PPP : Rs.20,000 crore

******

 

 