Highway Projects in Haryana

The details of National Highway projects undertaken for development under different phases of National Highway Development Project (NHDP) in the state of Haryana is given below:

 

The details of National Highway projects undertaken for development under different phases of National Highway Development Project (NHDP) in the state of Haryana is given below:

Sl.  No.

Name of Project

NH No.

Length (in Km.)

TPC

(Rs. in Crore)

Config-uration

Mode of Delivery

NHDP Phase

Date of Approval of CCEA/

PPPAC/EFC

Status of Land Acquisition

Physical Progress as on 30.11.15

Remarks/

Reason for delay

1

Zirakpur-Parwanoo

22

28.69

295.00

4

Laning

BOT (Toll)

III

01.11.2006

Completed

2

Ambala-Zirakpur

22

35.09

298.00

4

Laning

BOT (Toll)

III

NA

Completed

3

Panchkula-Yamunanagar (P-1)

73

44.57

468.00

4

laning

EPC

III

31.03.2015

100%

0%

-

4

Panchkula-Yamunanagar (P-2)

73

41.79

436.50

4

laning

EPC

III

29.04.2015

100%

0%

-

5

Widening of existing 4 lane portion in Panipat City

1

10.00

421.50

6

laning

BOT (Toll)

VII

NA

Completed

6

Mukarba Chowk in Delhi State to Panipat

1

70.5

2128.702

8

Laning

BOT (Toll)

VII

22.04.2015

N.A

Appointed date yet to be fixed

Concession Agreement signed on 28.08.2015

7

Flyover at Bahalgarh

1

2.45

69.81

--

EPC

VII

21.01.2014

NA

28%

Likely to be completed in November 2016.

8

Panipat-Jalandhar

1

116.00

2747.50

6

Laning

BOT (Toll)

VII

11.05.2007

NA

Completed except delinked sections / structures

Long Pending litigation

DCOD issued on 30.09.2015.

9

Ambala – Kaithal (Package-1)

65

50.86

457.70


4

Laning

EPC

III

25.02.2015

100%

Appointed date yet to be fixed

Concession Agreement signed on 21.04.2015

10

Ambala – Kaithal (Package-2)

65

44.5

459.00

4

Laning

EPC

III

25.02.2015

PKG-2:  3D (92%)

Appointed date yet to be fixed

Concession Agreement signed on 21.04.2015

11

Delhi/Haryana border-Rohtak

10

63.49

486.00

4/6 Laning

BOT

(Toll)

III

11.10.2006

Completed

94.72%

PCOD issued on 26.11.2015 for 55.722 Km.

12

Rohtak Panipat

71A

80.86

807.00

4

Laning

BOT

(Toll)

III

05.11.2009

Completed

13

Rohtak-Bawal

71

83.66

650.00

4/6 Laning

BOT

(Toll)

III

29.10.2009

Completed

99.40%

PCOD issued for 71.515 Km on 24.08.2013 and for 11.64 Km. on 30.09.14

14

Rohtak –Jind

71

48.60

283.25

4

Laning

BOT

(Toll)

III

10.12.2010

Completed

28.15%

Notice for termination issued to concessionaire on 18.11.2015

15

Rohtak-Hissar

10 &71

98.81

959.25

4

Laning

BOT

(Toll)

III

21.12.2012

Completed

81.85%

Likely to be completed in June 2016.

16

ROB at Dabwali

10

0.89

47.25

4

Laning

BOT

(Toll)

III

16.07.13

NA

98%

Likely to be completed in April 2016.

17

Hisar-Dabwali Package-I

10

57.00

962.31

4

Laning

EPC

III

25.02.2015

92.98 %

16%

Schedule for completion in Feb 2018.

18

Hisar-Dabwali Package-II

 

87.66

973.88

4

Laning

EPC

III

25.02.2015

90.93 %

0

Schedule for completion in May 2018.

19

Kaithal-Rajasthan Border

65

166.26

1393.00

4

Laning

BOT (Toll)

IV

03.09.2013

89.10 %

14%

Schedule for completion in Jan 2018.

20

Punjab / Haryana Border-Jind

71

69.35

520.72

4

Laning

BOT (Toll)

IV

Project is being foreclosed

21

Gurgaon- Kotputli

8

233.20

1896.25

6

Laning

BOT

(Toll)

V

May-June 2007

Completed except some pieces of land

92%

Delay in land Acquisition, Shifting of utilities and financial crunch of the Concessionaire

22

Delhi- Agra

2

179.50

1922.28

6

Laning

BOT

(Toll)

V

28.01.2009

Completed except some pieces of land

41.5 %

Delay in land Acquisition, Shifting of utilities and forest clearances

 

            The details of new projects sanctioned/being considered for sanction under National Highway Development Project (NHDP) in the state of Haryana since November 2014 is gien below:

Sl. No.

Name of project

NH No.

Length (in KM)

Configur-ation

Mode of Delivery

TPC/ Civil Cost

(Rs. in Crore)

1

Ambala Kaithal (PKG-1)

65

50.86

4-laning

EPC

483.14

2

Ambala Kaithal (PKG-2)

65

44.5

4-laning

EPC

460.165

3

Hisar Dabwali (PKG-1)

10

57

4-laning

EPC

579.76

4

Hisar Dabwali (PKG-2)

10

87.66

4-laning

EPC

695.36

5

Yamunanagar- Panchkula (Package-1)

73

44.57

4-laning

EPC

481.45

6

Yamunanagar- Panchkula (Package-2)

73

41.792

4-laning

EPC

450.59

7

Yamunanagar- Panchkula (Package-3)

73

18.892

4-laning

EPC

301.47

8

Delhi-Panipat

1

69.849

8-laning

BOT (Toll)

2128.72

9

Punjab / Haryana Border-Jind

71

69.35

4-laning

BOT (Toll)

520.72

10

Flyover at IFFCO Chowk, Gurgaon

8

--

--

--

386.34

11

Flyover at Rajiv Chowk, Gurgaon

8

--

--

--

285.57

12

Flyover at  Signature Tower,  Gurgaon

8

--

--

--

263.41

 

This information was given by Minister of State for Road Transport & Highways,       Shri Pon. Radhakrishnan in a written reply to a question in the Lok Sabha today. 

 

*****

 