Print
XClose
Press Information Bureau
Government of India
Ministry of Shipping
25-July-2016 16:14 IST
Development of Sea Port at Sagar Island

 

            The Government is developing a Port at Sagar Island. Kolkata Port has been facing the challenges in terms of draft limitations, limited headroom for expansion and efficiency. The constraint has necessitated the need to have an alternative port near to sea, having sufficient draft and no river navigation, as it has been there in Kolkata Port.

           

    Sagar Island has been selected after a detailed study for locating the port. A new port in Sagar will share the hinterland of the Haldia and Kolkata ports, particularly the power and steel plants in the eastern region, and containers from the eastern parts of India (Western UP, Odisha, Jharkhand, Chhattisgarh etc.) and neighboring landlocked countries- Nepal and Bhutan. The port will be a viable alternative to serve as for spill-over cargo, specifically non-POL bulk from the Haldia dock complex.

 

Containers will be another major variant to be handled at the Sagar port.  This is primarily due the limitation of capacity and the inability to expand the Haldia and Kolkata ports, which can result in an overflow of containers that can be handled at the Sagar port.

 

The traffic for the Sagar port is projected to be around 3.5 MTPA in 2020 increasing to around 27 MTPA in 2035.      

 

The timeline for development of Sagar Port is as follows:

 

 

ACTIVITY

TIMELINE

PPPAC Presentation

22 March 2016

Preparation of bid documents (including reclamation and dredging)

Already submitted to PPPAC and MOS 

PPPAC Approval to be recd

Awaited

EFC Memo

07 June 2016

Notification of Port Limits

24 June 2016

CCEA Approval To Be Recd

Awaited

TOR Amendment Presentation

29 July 2016

RFQ Issue Date

20 August 2016

Last date of receiving RFQ queries

16 September 2016

Pre-application conference (RFQ)

22 September 2016

Authority response to queries

29 September 2016

Application due date (RFQ)

09 October 2016

Announcement of short list of applicants

26 October 2016

RFP Issuance Date

03 November 2016

CRZ Recommendation from State Coastal Zone Management Authority (SCZMA)

07 November 2016

Final application to MoEF & CC for Environmental Clearance (EC) with final EIA report to be submitted

30 November 2016

RFP Submission Date

18 December 2016

Security clearance to be obtained

31 December 2016

Letter of Award

31 January 2017

Environmental Clearance

28 February 2017

Signing of Concession Agreement

28 February 2017

 

 

       The cost of the project as per Revenue Model is estimated at INR 1464 crores. The work related to reclamation, dredging and provision of basic infrastructure will be undertaken by Special Purpose Vehicle (SPV) and Kolkata Port Trust.  Total cost of these works is estimated to be Rs.515 crores. The construction of port related infrastructure like berths etc. will be undertaken by the concessionaire at an estimated cost of Rs. 948.6 crores. The break-up of cost is given below:

 

            (Rs. in crores)

S.No.

Works

SPV EPC Model

PPP (DBFOT Model)

1.

Dredging

28.2

 

2.

Land Reclamation, Clearing & Land Improvement

324.3

8.3

3.

Common Infrastructure Facilities (Administration building, Gate House, Customs Building, Harbour Master Block and control room, Signal Station, Fire Station building, Users building, etc.)

 

92.4

4.

Development of Berths & Cargo Terminal (Berthing Jetty, Approach Trestle, Stack Yard, Paved storage yard, Other Miscellaneous works)

 

346.8

5.

Cargo Handling Equipment

 

276.5

6.

Navigational aids

2

 

7.

Harbour Crafts & locomotives

 

 

8.

Provision of External Power

11.5

45.7

9.

Provision of Water supply.

 

2.4

10.

Provision of Telecommunication

 

5.9

11.

External Road

32.8

 

12.

Internal Main / Secondary Roads to Operational Areas and Parking

 

18.9

13.

Railway Lines and Rail Yard in Mainland

67.1

 

14.

Contingencies @ 15%

23.1

41.3

15.

Environment Aspects

 

12

16.

Fire Fighting System/ Hazard Mitigation

 

12

17.

Project management & Engineering consultancy

 

5.3

 

TOTAL 

489

867.5

18.

Other costs (EIA, VTMS, IDC, etc.)

26.4

81.1

 

TOTAL COST OF THE PROJECT 

515.4

948.6

 

 

   The Project is now being taken for Phase-I. The total Phase-I cost of Sagar Port Development has been estimated to Rs. 1464 crores. 

 

            This information was given by Minister of State for Shipping, Shri Pon. Radhakrishnan in a written reply to a question in the Rajya Sabha today. 

 

*****

UM/NP