192 villages have been
electrified across the country during last week (from 25th to 31st
July 2016) under Deen Dayal Upadhyaya Gram Jyoti Yojna (DDUGJY). Out of these
electrified villages, 10 villages belong to Assam, 2 in Bihar, 24 in Jharkhand,
2 in Madhya Pradesh, 123 in Meghalaya, 3 in Nagaland, 15 in Odisha, 7 in
Rajasthan, 5 in Uttar Pradesh and 1 in Uttarakhand. The progress of ongoing
electrification process can be tracked on http://garv.gov.in/dashboard

An update on ongoing electrification process: -
In view of the Prime Minister, Shri Narendra Modi’s address
to nation, on Independence Day, Government of India has decided to electrify
remaining 18,452 un-electrified villages within 1000 days i.e. by 01st
May, 2018. The project has been taken on mission mode and strategy for
electrification consists of squeezing the implementation schedule to 12 months
and also dividing village electrification process in 12 Stage milestones with
defined timelines for monitoring.
9,326 villages have been electrified till date. Out
of remaining 9126 villages, 501 villages are uninhabited. 5,694 villages are to
be electrified through grid, 2,638 villages to be electrified through off-grid
where grid solutions are out of reach due to geographical barriers and 293
villages are to be electrified by State Government.
Total 1654 villages were electrified during April
2015 to 14th Aug 2015 and after taking initiative by Government of
India for taking it on mission mode, 7,672 additional villages have been
electrified from 15th August 2015 to 31st July, 2016.
In order to expedite the progress further, a close monitoring is being done
through Gram Vidyut Abhiyanta (GVA) and various actions are also being taken on
regular basis like reviewing the progress on monthly basis during the RPM
meeting, sharing of list of villages which are at the stage of under energization
with the state DISCOM, identifying the villages where milestone progress are
delayed.