Status of 39 Govt. Medical Colleges/Institutions being taken up for
up-gradation under Phase-III of PMSSY -
(Total outlay: Rs.150.00Cr.(Central Share: Rs.120 Cr. & State Share:
Rs.30 Cr.) - Data regarding civil work
|
|
|
S. No.
|
Name of the State
|
Name of the
GMC/ Institute
|
Name of Executing Agency / Contractor
|
Approved DPR Cost for Construction Work (Rs. Cr)
|
Approved Contract value (Rs. )
|
Date of Award of work/Target date of completion
|
Scheduled date of completion
|
Physical Progress
|
Fund released (Rs)
|
Hindrances
|
|
|
|
1
|
Andhra
Pradesh
|
Siddhartha
Medical College, Vijayawada
|
HSCC(I) Ltd./ M/s.KMV
Projects Ltd.
|
80.03
|
65,97,96,831
|
May'
2016 / Oct.' 2017
|
Oct.
2017
|
22%
|
21,70,75,310
|
|
|
|
2
|
Andhra Pradesh
|
Govt Medical
College, Anantapur
|
HITES /
M/s. HaigreevaIntratech Projects Ltd.
|
80
|
75,27,57,000
|
14.05.2016
/ 06.12.2017
|
06.12.2017
|
9%
|
17,51,85,778
|
|
|
|
3
|
Assam
|
Gauhati Medical College, Guwahati
|
HSCC(I) Ltd./ M/s.ShreeGautam Constructions Co. Ltd.
|
80
|
68,41,01,880
|
Jan.'
2017 / July' 2018
|
July,
2018
|
|
7,18,87,132
|
Aproval from Guwahati
Metropolitan Development Authority awaited.
|
|
|
4
|
Assam
|
Assam
Medical College, Dibrugarh
|
HSCC(I) Ltd./ M/s.KMV
Projects Ltd.
|
80
|
73,11,99,125
|
Aug.'
2016 / March' 2018
|
Mar.
2018
|
7%
|
19,31,19,913
|
Existing structures to be demolished
|
|
|
5
|
Bihar
|
Srikrishna Medical College, Muzaffarapur
|
HITES /
M/s. Gannon Dunkerley& Co. Ltd., New
Delhi
|
85
|
86,27,22,010
|
04.11.2016
/ 31.05.2018
|
31.05.2018
|
2%
|
8,58,90,541
|
Delay in cutting of trees coming in the
layout of the building
|
|
|
6
|
Bihar
|
Govt
Medical College, Darbhanga
|
HITES /
M/s. Vijeta Projects & Infrastructure Ltd.,
Ranchi
|
85
|
85,35,56,206
|
30.09.2016
/ 31.05.2018
|
31.05.2018
|
1%
|
8,52,48,934
|
Delay in shifting of underground
utilities and existing structures
|
|
|
7
|
Goa
|
Goa
Medical College, Panaji
|
HSCC
|
386.35
|
work
yet to be awarded
|
|
|
|
11,59,00,000
|
Removal of encroachments/ statutory
clearances
|
|
|
8
|
Gujarat
|
Govt
Medical College, Rajkot
|
HITES /
M/s. Kunal Structures Pvt. Ltd., Rajkot
|
88.5
|
69,29,80,242
|
08.06.2016
|
|
|
7,50,08,617
|
Work yet to commence as non-availability
of clear site.
|
|
|
9
|
Himachal
Pradesh
|
Indira Gandhi Medical College, Shimla
|
HSCC
|
|
|
|
|
|
6,25,50,947
|
DPR is being revised based on the
proposal submitted by State Govt. to change location.
|
|
|
10
|
Jharkhand
|
Patliputra Medical College, Dhanbad
|
CPWD
|
85.71
|
50,08,00,000.00
|
27.08.2016
/ 26.12.2017
|
31.03.2018
|
21%
|
22,07,10,000
|
|
|
|
11
|
Karnataka
|
Vijayanagar Institute of Medical Sciences, Bellary
|
HITES /
M/s. HaigreevaIntratech Projects Ltd.
|
65
|
59,50,45,338
|
14.05.2016
/ 06.09.2017
|
14.09.2017
|
16%
|
26,07,12,509
|
1. Delay in getting approval from local
bodies 2. Electrical connection to be
provided by Medical College for Trauma Centre
|
|
|
12
|
Karnataka
|
Karnataka
Institute of Medical Sciences, Hubli
|
HITES /
M/s. Harsh Construction Pvt. Ltd.
|
75
|
69,70,95,383
|
14.05.2016
/ 10.02.2018
|
10.02.2018
|
10%
|
14,69,93,064
|
|
|
|
13
|
Kerala
|
Kozhikode
Medical College, Kozhikode
|
HITES /
M/s. CheriayanVarkey Construction Projects Ltd.
|
80
|
71,13,94,146.51
|
01.06.2016
|
|
|
10,40,27,590
|
Work on hold on account of change in
designs/drawings proposed by State Govt. Commitment of State Govt. for
additional funds received. However, State cabinet approval is pending for the
same.
|
|
|
14
|
Kerala
|
Govt
TD Medcial College, Alappuzha
|
HITES /
M/s. CheriayanVarkey Construction Projects Ltd.
|
80
|
74,14,80,342
|
01.06.2016
|
|
|
10,54,77,624
|
Work on hold on account of change in
designs/drawings proposed by State Govt. Commitment of State Govt. for
additional funds received. However, State cabinet approval is pending for the
same.
|
|
|
15
|
Madhya
Pradesh
|
Shyam Shah Medical College, Rewa
|
HSCC(I) Ltd/ M/s.KMV
Projects Ltd.
|
77.83
|
66,24,81,896.33
|
May'
2016 / Oct.' 2017
|
Oct.,
2017
|
22%
|
29,99,48,381
|
|
|
|
16
|
Madhya
Pradesh
|
Netaji SubhashCh Bose Medical
College, Jabalpur
|
HSCC(I) Ltd/ M/s.Rama Construction Company
|
77.89
|
65,69,06,406.29
|
May'
2016 / Oct.' 2017
|
Oct.,
2017
|
39%
|
32,78,45,320
|
|
|
|
17
|
Madhya
Pradesh
|
GR
Medical College, Gwalior
|
HSCC(I) Ltd/ M/s.Anurag Enterprises
|
79.96
|
64,38,30,066.95
|
June'
2016 / Nov.' 2017
|
Nov.,
2017
|
14%
|
18,43,83,007
|
|
|
|
18
|
Maharashtra
|
Govt
Medical College, Aurangabad
|
HSCC(I) Ltd/ M/s.TirupatiSarjan Ltd.
|
74.92
|
63,17,20,008.58
|
May'
2016 / Dec.' 2017
|
Dec.,
2017
|
21%
|
11,17,20,401
|
|
|
|
19
|
Maharashtra
|
Govt
Medical College, Latur
|
HSCC(I) Ltd/ M/s.KMV
Projects Ltd.
|
74.36
|
58,72,18,469.66
|
June'
2016 / Jan.' 2018
|
Jan.,
2018
|
18%
|
10,84,05,293
|
|
|
|
20
|
Maharashtra
|
Govt
Medical College, Akola
|
CPWD
|
74.75
|
48,19,00,000.00
|
10.09.2016/
09.01.2018
|
09.01.2018
|
8%
|
14,95,00,000
|
|
|
|
21
|
Maharashtra
|
Shri VasantraoNaikGovt Medical College, Yavatmal
|
CPWD
|
74.36
|
48,47,00,000.00
|
12.09.2016/
11.01.2018
|
11.01.2018
|
7%
|
14,87,20,000
|
|
|
|
22
|
Odisha
|
MKCG
Medical College, Berhampur
|
HSCC(I) Ltd/ M/s.HaigreevaInfratech Projects Ltd.
|
80
|
65,94,78,093.47
|
May'
2016 / Oct.' 2017
|
Oct.
2017
|
23%
|
16,01,63,466
|
|
|
|
23
|
Odisha
|
VSS
Medical College, Burla
|
HSCC
|
79.15
|
work
yet to be awarded
|
|
|
|
2,40,00,000
|
1. Dismantling of existing
structures
2. Approval from local bodies awaited
|
|
|
24
|
Punjab
|
Govt
Medical College, Patiala
|
HSCC
|
82.74
|
work
yet to be awarded
|
|
|
|
2,48,00,000
|
Aproval from local bodies for Building
Plan
|
|
|
25
|
Rajasthan
|
SP
Medical College, Bikaner
|
HSCC(I) Ltd/ M/s.NKG
Infrastructure Ltd.
|
72
|
60,62,49,520.41
|
May'
2016 / Oct.' 2017
|
Oct.'
2017
|
34%
|
26,77,37,466
|
|
|
|
26
|
Rajasthan
|
RNT
Medical College, Udaipur
|
HSCC(I) Ltd/ M/s.Shivalaya Construction Co. Pvt. Ltd.
|
74.95
|
53,51,82,923.16
|
July'
2016 / Feb.' 2018
|
Feb.'
2018
|
22%
|
15,35,18,292
|
|
|
|
27
|
Rajasthan
|
Govt
Medical College, Kota
|
HSCC(I) Ltd/ M/s.TirupatiSarjan Ltd.
|
79.61
|
61,39,00,449.89
|
May'
2016 / Oct.' 2017
|
Oct.'
2017
|
27%
|
29,03,38,031
|
|
|
|
28
|
Tamil
Nadu
|
Thanjavur Medical College, Thanjavur
|
HITES /
M/s. KMV Projects Ltd.
|
79.93
|
79,79,91,266
|
01.06.2016
/ 14.12.2017
|
14.12.2017
|
16%
|
35,51,22,916
|
|
|
|
29
|
Tamil
Nadu
|
Tirunelveli Medical College, Tirunelveli
|
HITES /
M/s. KMV Projects Ltd.
|
83.95
|
79,63,75,336
|
01.06.2016
/ 21.12.2017
|
21.12.2017
|
19%
|
37,31,27,839
|
|
|
|
30
|
Telangana
|
Rajiv
Gandhi Institute of Medical Sciences, Adilabad
|
HITES /
M/s. KMV Projects Ltd.
|
80
|
77,57,72,952.29
|
14.05.2016
/ 31.12.2017
|
15.01.2018
|
10%
|
24,02,67,166
|
Shifting of water pipeline and open
drain
|
|
|
31
|
Telangana
|
Kakatiya Medical College, Warangal
|
HITES /
M/s. KMV Projects Ltd.
|
80
|
78,64,76,879.25
|
14.05.2016
/ 31.12.2017
|
31.12.2017
|
9%
|
25,19,60,099
|
|
|
|
32
|
Tripura
|
AgartalaGovt Medical College, Tripura
|
CPWD
|
114.54
|
work
yet to be awarded
|
17.01.2020
|
31.10.2019
|
|
20,00,00,000
|
|
|
|
33
|
Uttar
Pradesh
|
Govt
Medical College, Jhansi
|
HSCC(I) Ltd/ M/s.Kamladitya Construction Pvt. Ltd.
|
78.72
|
66,68,84,099.20
|
May'
2016 / Oct.' 2017
|
Oct.'2017
|
21%
|
16,02,81,887
|
|
|
|
34
|
Uttar
Pradesh
|
Govt
Medical College, Gorakhpur
|
CPWD / M/s. KashyapiInfrastrcturePvt.
Ltd. Ghaziabad
|
69.87
|
43,96,97,000
|
19.05.2016
/ 31.01.2018
|
31.01.2018
|
25%
|
20,94,70,000
|
|
|
|
35
|
Uttar
Pradesh
|
MLN
Medical College, Allahabad
|
HSCC(I) Ltd/ M/s.Akasva Infrastructure Pvt. Ltd.
|
70
|
57,93,71,996.52
|
May'
2016 / Nov.' 2017
|
Nov.,
2017
|
20%
|
20,17,87,048
|
|
|
|
36
|
Uttar
Pradesh
|
LLR
Medical College, Meerut
|
CPWD / M/s. Som Projects
Pvt. Ltd.
|
69.99
|
41,74,77,059.00
|
11.06.2016
/ 10.11.2017
|
10.11.2017
|
45%
|
18,97,90,000
|
|
|
|
37
|
West
Bengal
|
BS
Medical College, Bankura
|
CPWD
|
79.98
|
54,79,00,000.00
|
05.08.2016/
31.03.2018
|
31.03.2018
|
8%
|
40,99,60,000
|
|
|
|
38
|
West
Bengal
|
Govt.
Medical College, Malda
|
CPWD
|
61.39
|
44,96,00,000.00
|
17.12.2016/
16.08.2018
|
31.12.2018
|
|
16,13,90,000
|
Site not clear. Nurses
hostel existing on the site is being demolished by the college.
|
|
|
39
|
West
Bengal
|
North
Bengal Medical College, Siliguri, Darjeeling
|
HSCC(I) Ltd/ M/s.Gannon&Dunkerley& Co. Ltd.
|
80
|
71,94,38,828.39
|
June'
2016 / Jan.' 2018
|
Jan.,
2018
|
15%
|
17,19,43,883
|
Shifting of Services.
|
|