Sr.
No.
|
Name of the Project
|
NH No.
|
Length (km)
|
Estimates Total Project Cost
(Rs. Crores)
|
Expenditure (Rs. Crores)
|
|
1
|
Rehabilitation and upgradation of NH -565 from km 1.00 to 86.057 (Nakrekal to Nagarjunsagar Dam section) to two-lanes with paved shoulders under NHDP-IV on EPC basis.
|
565
|
85.06
|
270.00
|
102.45
|
|
2
|
Rehabilitation and upgradation of NH-221 from km 71/2 to 121/0 (of Vijayawada-Jagdalpur AP Border to Rudrampur) under NHDP-IV.
|
221
|
49.38
|
244.30
|
162.48
|
|
3
|
Rehabilitation and upgradation of NH-221 from km 121/0 to 165/00 (of Vijayawada-JagdalpurRudrampur to Sarapaka) under NHDP-IV.
|
221
|
43.19
|
334.82
|
88.67
|
|
4
|
Rehabilitation and upgradation to Two lane with Paved Shoulders from Km 0/0 to 72/6 of NH-365 (Nakrekal to Thanamcherla section) in the State of Telangana under NHDP-IV on EPC basis.
|
365
|
66.56
|
605.08
|
64.53
|
|
5
|
Construction of HLB across river Godavari at km 166/0 of NH 221 on EPC mode.
|
30
|
2.3
|
98.45
|
28.122
|
|
6
|
Four Laning from Km 4/8 to 24/6 of Nizamabad-Jagdalpur section of NH-63 (Old NH-16) in the State of Telangana under NH(O) on EPC mode .
|
63
|
19.00
|
117.56
|
19.093
|
|
7
|
Widening existing 2 lane to 2 lane with paved shoulders in km 67/2 to 109/0 including intermediate lanes of NH 363.
|
363
|
41.36
|
153.21
|
86.590
|
|
8
|
Widening &Strenthening of existing 2 lane carrige way on Hyderabad -Tokapalli section of NH 765 from km 108/8 to 128/6 including construction of new HL B Major at km 109/745 & construction of 4 new HLB minor at km 109/360,km 111/150, km 111/335 & km 111/405 and its approches.
|
765
|
19.80
|
77.26
|
57.796
|
|
9
|
Widening &Strenthening of NH 167 from km 227/6 to 283/0.
|
167
|
55.40
|
127.24
|
51.608
|
|
10
|
Widening to two/four lane with Paved Shoulders from existing Km 182.120 to Km 227.600 of NH-167 on Haggiri-Jadcherla road in the State of Telangana on EPC mode.
|
167
|
45.92
|
298.32
|
18.857
|
|
11
|
Widening to two/four lane with Paved Shoulders from existing Km 180.60 to Km 223.00 of NH-63 on Nizamabad-Jagadalpur road in the State of Telangana on EPC mode.
|
63
|
42.40
|
248.83
|
21.883
|
|
12
|
Widening to two lane with paved shoulders from Km 40/410 to Km 84/037of Thirumalagiri to Suryapet section of NH-365B.
|
365B
|
43.89
|
244.54
|
13.589
|
|
13
|
Widening to two lane with paved shoulders from Km 0/970 to Km 40/410 of Janagaon-Thirumalagiri of NH-365B.
|
365B
|
39.18
|
196.52
|
0.577
|
|
14
|
Widening to two lane with paved shoulders from Km 15.525 to Km 62.880 of Jadcherla-Kalwakurthy section of NH-167.
|
167
|
47.355
|
283.00
|
0.129
|
|
15
|
Widening to two lane with paved shoulders from Km 59.500 to Km 132.033 of Manneguda-Ravulapallysecttion of NH-163.
|
163
|
72.53
|
359.27
|
13.448
|
|
16
|
Widening to two lane with paved shoulders from Km 67.00 to 114.425 of Kalwakurthy-Mallepally section of NH-167.
|
167
|
47.005
|
300.00
|
13.502
|
|
17
|
Improvement from Km 493/0 to 524/0 of Pune-Hyderabad section of NH-65 (Old NH-9).
|
65
|
31
|
48.22
|
14.56
|
|
18
|
Development of Missing Link from Km 0.00 to 3.240 of Kalyan-Nirmal road of NH-61 in Nirmal town.
|
61
|
3.24
|
25.91
|
2.735
|
|
19
|
Widening to two lane with paved shoulder from Km 125/242 to 137/604 of NH-150 on Kalaburgi-Yadgiri-Krishna road.
|
150
|
12.24
|
34.76
|
0
|
|
20
|
Four-Laning of Yadgiri –Warangal Section of NH-163 (Old NH-202) from Km 54/0 to Km 150/0 (Design Length 99.103 km).
|
163
|
99.103
|
1905.23
|
589.37
|
| |
Total
|
|
866
|
5972
|
1350
|