S. No.
|
State
|
Name of the
proposal
|
Year of Approval
|
Date of Final
Approval /Date of Approval in Steering Committee
|
Due Date of Comp
|
Implementing
Agency
|
Facilities
created
|
|
1
|
Assam
|
Brass and Bell Metal Industry
Cluster, Hajo, Kamrup
|
2007-08
|
24.03.08
|
Due date was 16.09.10,
extension of duration will be considered upon receipt of request from State
Govt.
|
Director of Industries,
Government of Assam
|
Facilities for melting,
molding, casting, scraping, threading & soldering, hot rolling mill,
circle cutting and shearing machines, mechanical power press, polishing,
lacquering, chemical and metallurgical laboratory etc.
|
|
2
|
Goa
|
Cashew Cluster, Goa
|
2009-10
|
16.08.11
|
Completed report pending from
State Govt.
|
Goa Khadi and Village Industry
Board, Goa
|
Common Processing Facilities Training Centre
Common Packaging Facilities
|
|
3
|
Gujarat
|
Gem & Jewellery cluster, Ahmedabad
|
2010-11
|
12.08.10
|
Under
implementation, extension will be considered.
|
Canter for
Entrepreneurship Development, Ahd, Govt of Gujarat
|
Design Centre, Research and Development & Training
Centre
|
|
4
|
Haryana
|
Home Furnishing, Panipat
|
2013-14
|
Approved in 33rd
meeting of Steering Committee held on 14.06.13
|
2 years from date
of issue of Final approval
|
Investment
Promotion Centre, Chandigarh
|
(i) High Tech Cad
Design Centre,
(ii) Common Processing Facilities.
|
|
5
|
Haryana
|
Pharmaceuticals Cluster, Karnal
|
2013-14
|
Approved in 33rd
meeting of Steering Committee held on 14.06.13
|
2 years from date
of issue of Final approval
|
Investment
Promotion Centre, Chandigarh
|
Testing lab facility
|
|
6
|
Haryana
|
Stainless Steel Cluster, Kundli, Sonepat
|
2013-14
|
Approved in 33rd
meeting of Steering Committee held on 14.06.13
|
2 years from date
of issue of Final approval
|
Investment
Promotion Centre, Chandigarh
|
(i) Common Processing Facilities. (ii) Tool
Room
(iii) Material Storage.
|
|
7
|
Haryana
|
Footwear Cluster, Bahdurgarh
|
2011-12
|
03.12.12
|
02.12.14
|
Investment
Promotion Centre, Chandigarh
|
(i) Design Centre
(ii) Testing Lab
(iii) Value added facility.
(iv) Skill Development Centre
|
|
8
|
Haryana
|
Printing & Packaging Cluster, Karnal
|
2012-13
|
09.01.13
|
08.01.15
|
Investment
Promotion Centre, Chandigarh
|
(i) Design studio
(ii) Common Processing Facilities.
|
|
9
|
Karnataka
|
Auto (Servicing) Cluster, Bidar
|
2012-13
|
28.12.12
|
27.12.14
|
Karnataka Council
for Technology Up gradation (KCTU), Bangalore
|
(i)
Dismantling Testing & Calibration Section (ii) Fitting Centre (iii) Gear
Box Section (iv) Major Repair & Engine Section (v) Workshop Section (vi)
Final Fitment & Testing Section (vii) Emergency Section (viii) Training
Design & Research Section.
|
|
10
|
Karnataka
|
Automobile Components, Gokul Industrial
Estate, Hubli
|
2007-08
|
05.03.08
|
6.03.09
|
Karnataka Council
for Technology Up gradation (KCTU), Bangalore
|
A
centre named centre of Excellence and Common Facility Centre which will have
two major activities: one providing common facility services and the other
R&D and prototype development. In addition, these facilities will also be
utilized for skill development training at operator level and CAD/CAM course
for graduate and diploma students. The centre will have State of Art technology with
CNC machinery & equipment suitable for precision machining, manufacture
of jigs & fixtures, design & manufacture of moulds & Dies. It
will also have an exclusive R&D centre.
|
|
11
|
Kerala
|
Furniture Cluster, Kozhikode
|
2013-14
|
Approved in 33rd
meeting of Steering Committee held on 14.06.13
|
2 years from date
of issue of Final approval
|
Kerala Bureau of
Industrial Promotion (KBIP), Thiruvananthapuram
|
Design facility, Training facility, Primary Processing
facility, Value added component development facility, Finger joint board
facility, Tool Room Facility, Test and Training facility.
|
|
12
|
Kerala
|
Agriculture Cluster, Shornur
|
2013-14
|
Approved in 33rd
meeting of Steering Committee held on 14.06.13
|
2 years from date
of issue of Final approval
|
Kerala Bureau of
Industrial Promotion (KBIP), Thiruvananthapuram
|
Heat Treatment
Plant, Shearing Machine, Die Forging Hammer, Pneumatic Power Hammer, Trimming
Press, Size Rolling Machine, Oil Furnace, Plasma Cutting Machine, Rubber
Molding Machine, Plastic Injection Machine & Powder Coating Machine
|
|
13
|
Kerala
|
Wood Cluster, Taliparamba, Kannur
|
2011-12
|
28.08.12
|
28.08.14
|
Kerala Bureau of
Industrial Promotion (KBIP), Thiruvananthapuram
|
Modernized
manufacturing facilities, Preservation and seasoning of wood with
sophisticated technologies, Finger Joining Facilities which facilitates
joining of small pieces of wood which helps in maximum utilization of raw
material, Training, Procurement of raw materials, Providing other support
facilities
|
|
14
|
Kerala
|
Wood Processing Cluster, Kollam
|
2010-11
|
20.1.12
|
20.01.14
|
Kerala Bureau of
Industrial Promotion (KBIP), Thiruvananthapuram
|
Manufacturing
facility: The CFC will provide different
types of services like wood planning, moulding panel saw, preserving, kiln
seasoning, painting, polishing etc. Training: CFC will impart training
for cluster units and unskilled labour. Designing Center:
The designing center in CFC would help in manufacturing of modern wood
products with minimum wastage of raw material.
|
|
15
|
Kerala
|
Offset Printers Cluster, Kannur
|
2012-13
|
31.05.2013
|
30.05.2015
|
Kerala Bureau of
Industrial Promotion (KBIP), Thiruvananthapuram
|
The
proposed CFC would have design equipment, computer to plate equipment, plate
exposing equipment, Multi colour offset printing, Web Offset Machine etc.
|
|
16
|
Kerala
|
Ethnic Food Processing Women Cluster, Pala,
Kottayam
|
2009-10
|
02.07.10
|
31.10.13
|
Kerala Bureau of
Industrial Promotion (KBIP), Thiruvananthapuram
|
Raw
material storage facility, Finished Chill Room Storage Facility and packaging
facility.
|
|
17
|
Kerala
|
General Engineering Cluster, Malappuram,
Manjeri
|
2010-11
|
29.10.10
|
31.12.13
|
Kerala Bureau of
Industrial Promotion (KBIP), Thiruvananthapuram
|
Testing
facility for raw material and finished goods, Advanced machineries, Training
for development & up gradation of the skills for better employability,
Research & Development of products for construction & building
industry.
|
|
18
|
Maharashtra
|
Auto & Engineering Cluster, Ahmednagar
|
2013-14
|
Approved in 33rd
meeting of Steering Committee held on 14.06.13
|
2 years from date
of issue of Final approval
|
MIDC, Mumbai
|
(i) Common Testing (ii)
Training Facilities.
(iii) Common Processing Facilities.
|
|
19
|
Maharashtra
|
Mango Processing Cluster, Ratnagiri
|
2013-14
|
Approved in 33rd
meeting of Steering Committee held on 14.06.13
|
2 years from date
of issue of Final approval
|
MIDC, Mumbai
|
(i) Testing Laboratory
(ii) Common Processing Facilities.
|
|
20
|
Maharashtra
|
Powerloom Cluster, Shirpur, Dhule
|
2011-12
|
07.03.12
|
1 year from 1st
release
|
MIDC, Govt. of
Maharashra
|
(i) Common Processing (Pre and Post- processing)
(ii) Machine shop services;
|
|
21
|
Maharashtra
|
Fly Ash Cluster, Chandrapur
|
2010-11
|
25.02.11
|
24.02.13
|
MIDC, Govt. of
Maharashra
|
(i) Common Processing Centre
(ii) Testing Laboratory
(iii) Training Centre
(iv) Common Marketing Centre
|
|
22
|
Maharashtra
|
General Engg. Cluster, Bhosari, Pune
|
2012-13
|
22.04.13
|
21.04.15
|
MIDC, Govt. of
Maharashra
|
(i) Common Processing House
(ii) Industrial Waste Processing Centre.
(iii) Metrology, Metallurgy, Testing and Analysis Lab.
(iv) Training (HR) Centre.
|
|
23
|
Maharashtra
|
Dal Mill Cluster, Nagpur
|
2011-12
|
12.11.12
|
11.11.14
|
MIDC, Govt. of
Maharashra
|
(i) Raw material storage (ii)
Testing Lab.
(iii) Common Processing Centre
|
|
24
|
Maharashtra
|
Textile Cluster, Malegaon,
Nasik
|
2011-12
|
28.08.12
|
27.08.14
|
MIDC, Govt. of
Maharashra
|
(i) Common Processing House. (ii) Testing Laboratory.
|
|
25
|
Maharashtra
|
Garment Cluster, Nagpur
|
2011-12
|
14.03.12
|
13.03.14
|
MIDC, Govt. of
Maharashra
|
(i) Skill Training facilities
(ii) Computer Aided Designing and Embroidery facilities
(iii) Common Processing Centre
|
|
26
|
Maharashtra
|
Garment Cluster, Ichalkaranji, District Kolhapur
|
2011-12
|
24.09.12
|
23.09.14
|
MIDC, Govt. of
Maharashra
|
(i) Laboratory Testing, R&D Facilities.
(ii) Design Centre.
(iii) Value Addition Facility.
(iv) Common Processing.
(v) Marketing display, exhibition and sales.
(vi) Common Raw Material Preparation.
|
|
27
|
Odisha
|
Cashew Cluster, Ganjam, Orissa
|
2012-13
|
03.05.13
|
03.05.15
|
Orissa Small
Industries Corporation Limited (OSIC), Cuttack
|
(i) Common Processing Facilities (ii) Storage / Warehouse unit.
(iii) Common value added products development centre.
(iv) Common cashew shell oil extraction centre.
(v) Common Cashew Packaging Centre.
|
|
28
|
Punjab
|
Mohali Hitech Metal Cluster at Mohali, Punjab
|
2011-12
|
03.07.13
|
03.07.15
|
Cheif Coordinator,
Udyog Sahayak, Chandigarh
|
(i) R & D facility
(ii) Training
(iii) Mini Tool Room
|
|
29
|
Tamilnadu
|
Rice mill Cluster, Thanjavur
|
2013-14
|
Approved in 33rd
meeting of Steering Committee held on 14.06.13
|
2 years from date
of issue of Final approval
|
TANSIDCO, Chennai
|
(i) Common Processing Facilities
(ii) Testing Facility
(iii) Training Facility
|
|
30
|
Tamilnadu
|
Plastic Cluster, Chennai, Kancheepuram
|
2013-14
|
Approved in 33rd
meeting of Steering Committee held on 14.06.13
|
2 years from date
of issue of Final approval
|
TANSIDCO, Chennai
|
(i) Common processing centre
(ii) Testing Facilities
(iii) A Centre for training
|
|
31
|
Tamilnadu
|
Steel Product Fabrication Cluster, Salem
|
2012-13
|
03.05.13
|
03.05.15
|
TANSIDCO, Chennai
|
(i) Common Processing Centre
(ii) Tool room
(iii) Testing Lab
|
|
32
|
Tamilnadu
|
Starch and Sago Cluster (Phase-II) at Salem and Namakkal
|
2012-13
|
15.05.13
|
15.05.15
|
TANSIDCO, Chennai
|
(i) Laboratory equipments
(ii) Common Packaging Facilities
(iii) Conveyors for loading/unloading of bags.
|
|
33
|
Tamilnadu
|
Ceramic Cluster, Vridhachalam
|
2008-09
|
09.06.10
|
1 year from 1st
release
|
TANSIDCO, Chennai
|
(i) Tunnel Kiln
(ii) Common Processing Facilities
|
|
34
|
Tamilnadu
|
Bricks Cluster, Tirunelveli
|
2009-10
|
19.04.10
|
1 year from 1st
release
|
TANSIDCO, Chennai
|
(i) Common Processing Centre (ii) Vertical Shaft Brick Kiln (iii) Training Centre
|
|
35
|
Tamilnadu
|
Engineering Cluster, Hosur
|
2010-11
|
13.04.11
|
1 year from 1st
release
|
TANSIDCO, Chennai
|
(i) Common Metal
Processing Facilities
(ii) Testing cum calibration centre
(iii) Training centre for skill up-gradation
|
|
36
|
Tamilnadu
|
Engineering Cluster, Ranipet, Vellore Distt.
|
2010-11
|
04.03.11
|
1 year from 1st
release
|
TANSIDCO, Chennai
|
(i) Training
Facility
(ii) Lab facility for testing
(iii) Research & Development
facility
(iv) Facility for complimenting the
process at the firm level for high-end job works.
|
|
37
|
Tamilnadu
|
Printing Cluster, Sivakasi, Virudhnagar
|
2010-11
|
03.02.11
|
1 year from 1st
release
|
TANSIDCO, Chennai
|
Common Processing Facilities
|
|
38
|
Tamilnadu
|
Rice Mill Cluster, Keelapavoor
|
2010-11
|
04.04.11
|
1 year from 1st
release
|
TANSIDCO, Chennai
|
(i) Common
Processing (Solvent Extraction Plant) Centre
(ii) Training Centre
|
|
39
|
Tamilnadu
|
Singai Coir Cluster, Singampunari
|
2008-09
|
13.09.10
|
1 year from 1st
release
|
Coir Board, Cochin
|
(i) PVC Tufted Mat
Unit.
(ii) R&D Centre for Testing, Designing & Development
|
|
40
|
Tamilnadu
|
Wet Grinder Industry Cluster, Coimbatore
|
2004-05
|
Approved in 9th
meeting of Steering Committee held on 28.2.05
|
|
TANSIDCO, Chennai
|
(i) Common Processing Facilities (ii) Design and
development facility (iii) Plastic
Testing equipment.
|
|
41
|
Tamilnadu
|
Printing Cluster, Krishnagiri
|
2011-12
|
28.08.12
|
28.08.14
|
TANSIDCO, Chennai
|
(i) Pre-press activities such as design and
computer-to-plate facilities.
(ii)Common Processing Facilities
|
|
42
|
Tamilnadu
|
Rice Mill Cluster, Alangulam, Tirunelveli
|
2012-13
|
21.01.13
|
21.01.15
|
TANSIDCO, Chennai
|
(i) Common Processing
Facilities
(ii) SILO Storage
(iii) Training Centre
|
|
43
|
Uttar Pradesh
|
Modern Carpet Backing Plant for Tufted
Carpets, Bhadohi
|
2007-08
|
Approved in 33rd
meeting of Steering Committee held on 14.06.13
|
31.12.13
|
UPTPA, Kanpur/BIDA,
Bhadohi
|
Backing
Plants (5 nos.) 9’x12’, 6’x9’, 8’x5’, 6’x3’, 2’x3’ and other standards
accessories/assets for 6 lakh sq. mt. Carpet backing, Training facilities and
Testing facilities.
|
|
44
|
Uttar Pradesh
|
Scissors Cluster, Meerut
|
2009-10
|
Approved in 33rd
meeting of Steering Committee held on 14.06.13
|
30.06.14
|
The National
Institute for Entrepreneurship and Small Business Development (NIESBUD),
Noida.
|
Modern
forging presses and dies to produce semi-finished (dimensionally near
finished) instruments, Training Cell for basic training in CAD/CAM in forging
technology, Raw material bank, for high quality raw materials by either
association or Consortium/SPV, Marketing Assistance Cell for domestic and
international markets.
|
|
45
|
Uttar Pradesh
|
Stainless Steel, Brass & German Silver
Utensils Cluster, Mirzapur
|
2012-13
|
14.01.13
|
14.01.15
|
UPTPA, Kanpur, Govt. of UP
|
Common
Casting Unit, Common Rolling Unit, Common finishing & Polishing Unit,
Common Testing Laboratory.
|
|
46
|
West
Bengal
|
National Programme for Technology
Upgradation of Brass & Bell Metal Industry / Artisan Enterprises in
Khagra and others Areas in the WB and Neighbouring States
|
2007-08
|
31.08.08
|
08.09.11
|
UNIDO
|
Marketing
support, process demonstration, raw materials supply, consultancy, training,
testing, product design and development, quality management
|
|
47
|
West
Bengal
|
Fan Manufacturing Cluster, Kolkata
|
2010-11
|
07.06.11
|
7.06.13
|
West Bengal
State Export Promotion Society,
Govt. of West Bengal.
|
(i)
Air Delivery Room, Anemometer Analogue, Stop Watch, Angle Protractor, Multimeter
& Ohms meter Digital, High voltage Tester, Megger, Tachometer, Digital
& Analogue Watt Meter, A.C. Earthing Tester, Ten Pin, Humidity Chamber,
Impact Tester, Tensile Tester, Torsion Tester, Mechanical Endurance Tester,
High Voltage Tester etc., (ii) In addition, the CNC Turning Machine will be
installed for development of proto types while High end Computer with
peripherals, UPS and necessary software will be installed for computer aided
design (CAD) of fans of different types. The Armature Winding Machine will
also be installed for winding of high purity copper wire on the rotor.
|
|
48
|
West
Bengal
|
Re-Rolling Mills Cluster, Howrah
|
2010-11
|
29.07.11
|
31.03.14
|
West Bengal
State Export Promotion Society,
Govt. of West Bengal.
|
(i)
Testing facilities consisting of chemical lab, mechanical and NDT lab and
pollution lab, (ii) Machine shop facility consisting of planning machines,
shapers, radial drilling machines, slotting machines, precision central lathe
machines, horizontal, boring machines, etc., (iii) Raw materials processing consisting of
coreless furnace.
|
|
49
|
West
Bengal
|
Silver Filigree Cluster, Magrahat
|
2011-12
|
29.07.11
|
29.07.13
|
West Bengal
State Export Promotion Society,
Govt. of West Bengal.
|
Accurate
tooling as per their designs, Melting/Casting of alloys with certified
composition, Fine wire drawing, Ultrasonic cleaning, Modern pollution free
polisher, Modern testing facility, Design of the filigree items as per the
creativity of the artisans.
|
|
50
|
West
Bengal
|
Zari Embroidery Cluster, South 24 parganas
|
2011-12
|
28.08.12
|
28.08.14
|
West Bengal
State Export Promotion Society,
Govt. of West Bengal.
|
The
CFC will be instrumental in providing umbrella facilities like raw- material
bank, machination facilities in the form of centralized facility. These includes
testing cum quality control, Centralized facility for critical processing of
raw materials, Common packaging and branding facility etc.
|
|
51
|
West
Bengal
|
Honey Processing Cluster, Malda
|
2011-12
|
27.06.12
|
27.06.14
|
West Bengal
State Export Promotion Society,
Govt. of West Bengal.
|
(i)
Value addition by withering moisture content by modern and efficient
machinery instead of primitive process now being adopted and reducing loss
and specification, (ii) Testing Lab evidently required for mechanical
processing, (iii) Introduction of new products like Pollen bread, royal
jelly, pro-polish and even bee-venom having high demand in international
market, (iv) Automatic packaging and labeling machines will be used to
produce more at lesser time and to maintain uniformity and attraction in the
product packaging, (v) Production of comb foundation sheet on service basis,
(vi) Sales outlet at the CFC place to increase the sales volume of the
cluster.
|
|
52
|
West
Bengal
|
Roofing Tiles Cluster, Bankura
|
2012-13
|
03.10.12
|
03.10.14
|
West Bengal
State Export Promotion Society,
Govt. of West Bengal.
|
Modern
Kiln, R&D for new product, Training and testing activities.
|
|
53
|
West
Bengal
|
Lead Acid Battery, Siliguri
|
2012-13
|
01.02.13
|
1.02.15
|
West Bengal
State Export Promotion Society,
Govt. of West Bengal.
|
(i) Waste Battery
recycling plant to yield quality oxide, lead alloy and refined lead, (ii)
Component plate development facility, (iii) Testing lab. for raw material as
well as finished battery.
|
|
54
|
West
Bengal
|
Plastic Processing Cluster, Dabgram,
Rajganj, Jalpaiguri
|
2012-13
|
16.05.13
|
16.05.15
|
West Bengal
State Export Promotion Society,
Govt. of West Bengal.
|
PLC Controlled Screw milling
lathe, Precision Lathe, Honing, Milling, Radial Drill, Hard Chroming, Gas
nitrating, Rubberising, Cutting, Welding, Product Testing etc.
|
|
55
|
Madhya Pradesh
|