The
project for design and development of Kaveri engine
was sanctioned to achieve the interim flight standard for LCA ‘Tejas’ integration. Though the Kaveri
engine was not fully meeting the requirement of LCA ‘Tejas’,
it provided a platform for gas turbine technology development in the country.
This
project was the first indigenous aero-engine development project in the
country. Besides, some of the reasons for delay in the project are:-
(i)
Ab-initio development of
state-of-the-art gas turbine technologies.
(ii)
Technical/technological complexities.
(iii)
Lack of availability of critical equipment & materials and denial
of technologies by the technologically advanced countries.
(iv)
Lack of availability of test facilities in the country necessitating
testing abroad.
(v)
Non availability of skilled/technically specialized manpower.
Gas Turbine Research Establishment (GTRE)
associated itself with a premier scientific organisation of Russia i.e., Central
Institute of Aviation Motors (CIAM) with an objective of fine tuning of Kaveri engine performance. This association brought GTRE
per se Kaveri project in higher platform, resulting
in successful completion of one major milestone i.e. altitude testing,
simulating Kaveri engine performance at different
altitude and Mach No. Subsequently, one of Kaveri
prototype (K9) is being integrated with IL-76 aircraft at Gromov
Flight Research Institute (GFRI), Russia for ground and flight
tests, of Flying Test Bed (FTB) trials, this will be
the second major milestone to be achieved. These two milestones would make ‘Kaveri engine flightworthy.
The details of the funds allocated
and utilized are as under:
|
Financial Year
|
Allocation
(Rs in crore)
|
Expenditure
(Rs in crore)
|
|
2007-2008
|
157.05
|
152.51
|
|
2008-2009
|
153.54
|
153.54
|
|
2009-2010
|
123.20
|
122.06
|
This information was given by
Defence Minister Shri AK Antony in a written reply to
Shri C Rajendran in Lok Sabha today.
DM / RAJ