Ministry of Power25-April, 2013 18:01 IST
Power Projects in Chhattisgarh
Out of four Power Projects in Chhattisgarh, one project, namely, Korba West Extension Thermal Power Project (1x500 MW) has already achieved full load on 22

Out of four Power Projects in Chhattisgarh, one project, namely, Korba West Extension Thermal Power Project (1x500 MW) has already achieved full load on 22.03.2013 and Commercial Operation (COD) is anticipated in June, 2013. Marwa Thermal Power Project (2x500 MW) is under construction and the first Unit (500 MW) of Marwa Thermal Power Station is expected to be commissioned in August,2013 and the second unit (500 MW) in December, 2013. The work on the two other thermal power projects, namely, 2x660 MW Bhaiyathan thermal power project & 2x660 MW IFFCO – Chhattisgarh TPP power project are yet to be started. The reasons for delay are as follows:

Sl. No.

Project Name

Capacity (MW)

Reasons for Delay

1

Marwa TPP

2x500

-          Agitation by villagers.

-          Non-readiness of Balance of Plant equipment.

2

Bhaiyathan TPP

2x660

Delay due to non clearance of coal blocks allotted to the project. MOEF has not accorded environmental clearance for the development of Gidhmuri & Paturia Coal Blocks. Therefore, M/s India Bulls Pvt. Ltd. has withdrawn their offer for development of the project due to uncertainty regarding these two captive coal blocks allotted to the project.

3

IFFCO – Chhattisgarh TPP

2x660

The project is delayed due to delay in getting stage-II clearance from MOEF for development of Tara Captive Coal Block.

 

The commissioning schedule of  Marwa TPP (2x500 MW), Bhaiyathan TPP (2X660 MW) and IFFCO – Chhattisgarh TPP (2x660 MW) are as follows:

 

Sl. No.

Project Name

Capacity (MW)

Commissioning Schedule

1

Marwa TPP

2x500

Unit-1:  August, 2013

Unit-2:  December, 2013

2

Bhaiyathan TPP

2x660

Due to uncertainty regarding MOEF clearance for the Captive Coal Blocks allocated to Bhaiyathan TPP and IFFCO – Chhattisgarh TPP, it is not possible to set a deadline for completion of these two projects.

 

This information was given by MoS (I/C) Power Sh. Jyotiraditya M. Scindia in the Lok Sabha today.

****