Golden Quadrilateral project
Rajya Sabha
Four/six
laning of eighty four per cent of Golden Quadrilateral has been completed
as on 30.6.2005. There has been some
delays in some of the contracts pertaining to Golden Quadrilateral Project. However, it is expected that the projects would
be substantially completed by December 2005. It is also estimated that the actual expenditure on the project
will not differ much from the estimated cost, allowing for escalation.
The
Government has taken several steps to expedite the project. These are:
(a) The
Contracts are regularly monitored at various levels such as by Supervision
Consultants/Independent Engineers, Project Directors, National Highways Authority
of India officials at Headquarters.
(b)
State Governments
have appointed Senior officers as nodal officers for resolving problems associated
with implementation of the National Highways Development Project such as land
acquisition, removal of utilities, forest/pollution/environment clearances
etc.
(c)
A Committee
of Secretaries has been constituted to address inter-ministerial and Central-States
issues such as land acquisition, utility shifting, environment approvals,
clearance of Road Over Bridges etc.
(d)
To expedite
the construction of Road Over Bridges, an officer of the Railways has been
posed to National Highways Authority of India to coordinate with Railways.
Memorandum of Understanding has been signed with M/s IRCON International
Ltd.
This
information was given in the Rajya
Sabha today in a written reply by the Minister of State for Shipping, Road
Transport and Highways, Shri K. H. Muniyappa.