Ministry of Water Resources02-December, 2014 13:43 IST
Pending Irrigation Projects with CWC

ANDHRA-PRADESH

Fact Sheet

 

New (Major, Medium & Extension, Renovation & Modernisation (ERM) and Multipurpose) project proposals and 24 Revised (Major, Medium & ERM and Multipurpose) project proposals are under various stages of appraisal   in Central Water Commission. (CWC). Appraisal status of such project proposals is as follows:

 

 

STATUS  OF  NEW  PROJECTS  UNDER  VARIOUS  STAGES  OF  APPRAISAL

As on 18.11.2014

 

 

ANDHRA PRADESH

 

Sl. No.

Project

Category

Rivers/

Basin

District Benefited

Date of receipt

Benefits (Th.Ha)

Estt. Cost (Crore)

Status

1.

Dr. B.R. Ambedkar Pranhita – Chavella Sujala Sravanthi

Major

Pranhita/ Godavari

Adilabad,Nizamabad,Karimnagar,Medak, Warangal, Rangareddy & Nalgonda Distts. of drought prone areas in Telangana region of A.P.

12/10/10

 

663.7

40,300

SOR (2007-08)

·       Clearance from MoEF & MoTA not submitted by project authorities.

·       Simulation studies are under examination.

·       Details of design have been received               and are under examination.

·       The cost of the project shall be finalised once all the design and other statutory approvals are submitted. The detailed observation on cost have been issued in September, 2014.

2.

 

B.R.R.                                              Vamsadhara Project,               Phase-II, Stage-II

Major

Vamsadhara

Srikakulam

August, 2014

43.433

1658.97             (2013-14)

·       Compliance to Observations of Ministry of Agriculture, Hydrology received in October, 2014.

·       Observation on irrigation planning and weir and canal design, Embankment Design, and ground water have been sent to Project Authority during Oct. 2014 to November, 2014.

·       Statutory clearance from MoTA is not received.

3.

Andhra Pradesh Irrigation and Livelihood Improvement Project, Phase-II. (Consists of ERM of 11 nos. of Medium projects, Lift schemes and new Minor schemes)* PPO

Major

 

spread over several districts

DPR of 11 sub-projects submitted in phases starting from February, 2013.

77.679

1155.00

·       All the eleven projects are at various stages of appraisal in CWC.

·       After the bifurcation of Andhra Pradesh into Andhra and Telangana States, both State Governments are revising and updating their proposals accordingly.

 

 

ASSAM

 

Sl.

No.

Name of Project

Major/

Medium

River/

Basin

District Benefited

Date of Receipt

Benefit

(Th. Ha)

Estt. Cost

(Crore)

Status

1.

Amreng  Irrigation Project

Medium

Amreng / Brahmputra

Karbi/

Anglong

12/2011

6.80 (CCA)

10.88

96.967

·       DPR submitted to CWC(HQ) for hydrology confirmation on 02/04/2013.

·       Comments on Barrage and Canal aspect forwarded to field office of CWC on May, 2013.

·       Comments on Hydrological aspects have been sent to Project Authority during July 2014.

 

 

 

BIHAR

Sl.

No.

Name of Projects

Major/

Medium

River/

Basin

District Benefited

Date of Receipt

Benefits

(Th.Ha)

Estt. Cost

(Cr.)

Status

1

Burhi Gandak-None- Baya- Ganga Link Project.

 

Major

Burhi Gandak/ Ganga

Samastipur, Begusarai and Khagaria

20.01.2014

2.50 lakh.ha.

4213.75  (PL 2012-13)

·      Comments of CWC regarding clarification of Command Area has been issued in Jan, 2014.

·      Issues discussed with Principal Secretary, WRD, Bihar in Feb, 2014.

·      Observations on agricultural, hydrology, construction material, Irrigation Planning  and cost aspects have been sent to Project Authorities during Jan, 2014 to Aug,2014.

·      Meeting under the Chairmanship of Secretary, WRD, Govt. of Bihar with the Officers of CWC & NWDA was held on 5.8.2014 to review the progress of appraisal works.

2

Kosi-Mechi Intra State Link Project

Major

Kosi and Mechi/ Ganga

Supaul, Araria, Kishanganj, Purnia,  and Katihar

July, 2014

2.1052 lakh.ha

2903.25   (PL-2013-14)

·      DPR circulated to specialized Directorates of CWC and other Central Agencies in Sep, 2014.

 

 

 

 

 

CHHATTISGARH

Sl.

No.

Name of Project

Major/

Medium

River/

Basin

District Benefited

Date of Receipt

Benefit

(Th. Ha)

Estt. Cost

(Cr.)

Status

1.

Arpa Bhaisajhar Project

Major

Arpa/ Seonath/ Mahanadi

Bilaspur

09/2013

25.00

606.43

(2010)

·       Observations on Irrigation Planning, Cost and Hydro mechanical design aspects have been sent to project authorities.

·       Environment Clearance need to be furnished by State Govt.

·       Ground Water aspects Cleared

·       Interstate Matter, construction material aspects under examination

 

2.

Rajiv Samoda Nisda diversion scheme phase II

Major

Mahanadi

Raipur

02/2014

30.00

124.798

·       Project  received  from sent back category after receipt of Compliance of Interstate Matter, Cost, design, Irrigation Planning, CGWB.

·       Comments on Irrigation Planning have been sent to Project authority.

 

 

 

JAMMU & KASHMIR

Sl.

No.

Name of Project

Major/

Medium

River/

Basin

District Benefited

Date of Receipt

Benefit

(Th.Ha)

Estt. Cost

(Cr.)

Status

1

Remodeling of Sanigaloo Canal

ERM- Medium

Jhelum/ Jhelum

Shopian

11/2011

 

3.818

98.72    (PL-2008)

·       TAC Note is returned to IBO, Chandigarh and requested to modify the TAC Note incorporating the compliance submitted by the project authorities.

 

JHARKHAND

Sl.

No.

Name of Project

Major/

Medium

River/

Basin

District Benefited

Date of Receipt

Benefit

(Th.Ha)

Estt. Cost

(Cr.)

Status

1.

Rarhu Reservoir Project

Major

Rarhu/ Subernarekha

Ranchi

26.4.2013

 

 

CCA   10.472

852.09   (PL-2010-11)

·         Observation of Cost, Hydrology, CSMRS and MoA aspects have been sent to Project Authorities during June, 2013 to August, 2013.

·         Issues discussed with Project Authorities in Jan, 2014.

·         State Government has been requested to submit CDO Certificate.

 

 

KARNATAKA

Sl. No.

Project

Category

Rivers/

Basin

District Benefited

Date of receipt

Benefits (Th.Ha)

Estt.Cost (Crore)

Status

1.

Sonthi LIS

Major

Bhima/

Krishna

Gulbarga and Yadgir

12/2012

16.00

600.00           (PL-2012-13 )

·         DPR is under examination in MoWR, & MoF.

·         Observation on Irrigation Planning, Central Soil & Material Research Station have been sent to Project Authority.

·         Compliance to observations  on Cost and Hydrology received from the Project Authority.

·         Stage-I Forest Clearance for 0.78 ha of forest land has been received.

·         MoEF Environmental  Clearance is awaited from Project Authority.

2

Shiggaon Lift Irrigation Scheme

Major

Varada/

Krishna

Haveri

Dec, 2013

13.5

532.0

(2012-13)

·         Observations of Irrigation Planning, Hydrology, Interstate, Ground Water, Construction Material and Ministry of Agriculture have been sent to project authorities during April, 2014 to June, 2014.

·         Statutory Forest Clearance from MoEF and MoTA for the project are to be obtained by project authorities.

·         Environmental Clearance from MoEF received.

3.

Modernisation of Tunga Anicut Canal System

Medium, ERM

Tunga/ Krishna

Shimoga, Davanger

June, 2012

8.705

309.20

(2011-13)

·         Details on command area have been received from Project Authority.

4.

Karanataka Integrated and Sustainable Water Resources Management Investment Program- Tranch-II (Consist ERM of 02 nos of Major projects namely modernisation of Vijayanagara channels and modernisation works of Tungabhadra left bank canal system along with associated soft components).*PPO

Major

 

 

January-February, 2014

Vijayanagar: 11.154

TLBC:

1006.05

Vijayanagar: 355.68

TLBC:

1136.90

·       Both projects are at various stages of appraisal in CWC.

 

 

KERALA

 

Sl. No.

Project

Category

Rivers/

Basin

District Benefited

Date of receipt

Benefits (Th.Ha)

Estt.Cost (Crore)

Status

1.

Chitturpuzha Project

Major- ERM

Bharathapuzha basun

Pallakad

08/2014

16.94

45.36

·         Observation on cost has been sent to Project Authority in September, 2014.

 

 

MADHYA PRADESH

 

Sl.

No

Name of Projects

Major/

Medium

River/ Basin

District Benefited

Date of Receipt

Benefits

(Th. Ha)

Estt. Cost

(Cr.)

Status

1

Bina Complex Irrigation& Multi-purpose Project

 

Major

Bina, Dhasa,

Dehra

Sagar

Oct,

2010

77.00/

2x16MW

1624.36

(PL 2010)

·       The Project is under appraisal from 10/2010.

·       The response of the project authority for the compliance of observations of CWC was inadequate for speedy appraisal of the project for some period. Project authority started responding after that and Hydrology aspect has been cleared during 03/2014. On the basis of Hydrology, Irrigation Planning and other aspects are in the process of appraisal.

·       Water availability finalised.

·       Comments on Hydel Civil design, Cost, Interstate, International, Hydropower planning and other aspects related to CEA ,Cost aspects related to hydropower, CSMRS, and Ground Water have been sent to the project authorities during Jan, 2011 to Nov.,2014.

·       Compliance received from Project authority in respect of Embankment, CMDD, Gates design aspect, Irrigation Planning (on changes in basic planning, no demand of irrigation during Kharif season and review of cropping pattern) during May, 2011 to Nov, 2014.

·       Apart from the above, the Project Authorities have been requested to submit the Statutory Clearance from MoEF and MoTA.

2

Morand & Ganjal Complex Project

Major

Morand & Ganjal/

Narmada

Hoshangabad, Harda &

Khandwa

Sept.,

2011

70.476

1434.37

(PL2010-11)

·       Statutory clearances of MoEF (Env. And forest) and MoTA awaited. Cost and B/C ratio will be finalised after receipt of statutory clearances.

·       Irrigation planning need to be examined due to curtailing of command.  However, Project authority reiterated that there is no change in the command area.

·       Observations of FE&SA sent to project authority for approval of seInterstate mattersic design parameters.

·       Observations on Dam break analysis of the project have been sent to project authority during Oct, 2014 to Nov,2014.

3

Chinki Multipurpose Project

Major

Narmada

Narsinghpur

1/2013

86.215/

15MW

1420.20

(PL2009-10)

·       Interstate matters aspect cleared

·       Observations on water availability, Irrigation planning, construction material, Design, cost, and Ground water aspects have been sent to Project Authority during March, 2013 to Sept, 2014.

·       Compliance on CMC, agriculture, Hydro power aspects received from Project Authority.

·       Project authorities have been requested to furnish Statutory Clearance from MoEF and MoTA.

4

Bansujara dam  Project

Major

Dhasan/ Betwa

Tikamgarh/ Chhatarpur

July, 2013

58.680

980.23    (2009-10)

·       Observations of  construction material aspect, Ministry of Water Resources (international matter) , Irrigation Planning, Hydrology, Cost  and Ministry of Agriculture have been sent to Project Authority during July, 2013 to Sept, 2014.

·       Compliance on interstate, Ground water  and Agricultural aspects received from Project Authority.

·       Environmental & Forest Aspects cleared.

5

Barna

Major- ERM

Bama/ Narmada

Raisen&

Sehore

1.03.12

54.556

300.00   (PL.-2009)

·       Compliance on Cost and Agriculture  aspects received from Project Authority.

·       Comments on Irrigation Planning, Hydrology and interstate aspects have been sent to Project Authority in Aug, 2014. Ground water, Canal design and construction machinery aspects cleared.

6

Mohanpura Major Multipurpose Project

Major

Newaj/chambal

Rajgarh

29.01.14

65.000

2171.55

(PL-2009)

·       Comments/observations on Design, Agriculture, Irrigation Planning, interstate matters, Hydro Mechanical design, Cost (regarding issues on old SOR/2009, furnishing of Soft copy and Certificate on SOR etc), Hydrology(regarding water availability, Design flood studies, sedimentation studies etc) and Hydel Civil design aspects have been sent to project authority during June, 2014 to Oct,2014.

·       International, Ground water  and  construction machinery aspects received from Project Authority.

·       NWDA has furnished comments on fitment of Mohanpura project in Parbati-Kalisindh-Chambal (PKC) link.

7

Sher-Shakkar-Machhrewa Complex Project.

Major

Sher,Shakkar,Machhrewa

Narsinghpur

January, 2014

64.800

30MW

2259.14 Cr.

( PL 2009)

·       Compliance on Hydrology, Ground water, CMC-Plant planning, Canal design, Gates design, Hydro Mechanical design and Hydel Civil design aspects received from Project Authority.

·       Comments/ observations on Agriculture, Irrigation Planning and Design  aspects  have been sent to project authority during July, 2014 to Oct,2014.

·       Interstate aspect cleared.

8

Sip-Kolar Link Irrigation project

Medium

Sip/ Narmada

Sehore

June’ 10

2.600

109.23

·       Compliance on Irrigation Planning, Ground water aspects received from Project authority.

·       Project authorities have been asked to update the cost.

·       Environmental issues cleared.

9

Majhgaon

Medium

Bada Nalla/ Ken/ Yamuna

Panna

 

January, 13

13.6

258.99

·       TAC note is under finalization.

·       interstate issue cleared.

10

Panchamnagar

Medium

Bewas/ Sonar/ Ganga

Damoh

January, 2012

12.60

263.10

·       Observation on TAC note have been sent to field office for getting compliance from Project authorities.

·       Environmental clearance yet to be obtained by project authority.

·       Interstate issue has been cleared.

11

Sonpur

Medium

Sonar/ Ken/ Ganga

Sagar

November, 2011

7.000

127.46

·       Observation on TAC note have been sent to field office for getting compliance from Project authorities.

·       Environmental clearance yet to be obtained by project authority.

12

Pawai

Medium

Ken/ Yamuna

Panna

September, 2011

9.800

261.5

·       TAC note have been returned back with a request to expedite statutory clearances.

13

Tarped

Medium

Tarped /Dhasan/ Yamuna

Chhatarpur

January, 13

4.3

78.76

·       Observation on the proposal have been sent to project authorities.

·       International clearance obtained.

·       Environmental clearance yet to be obtained by project authority.

14

Chandrakeshar

 

Medium (ERM)

Chadarkeshar/ Narmada

Dewas

Nov. 2012

 

6.060/ (1.800 addl.)

15.55281

·       Observation on the proposal sent to project authorities.

15

Surajpur Medium Irrigation Project

Medium

Dehar/ Ken/ Yamuna

Sagar

Nov.-13

4.205

70.61

·       The revised DPR as per guide lines has been received on 19.11.2013. Observations have been sent to Project Authorities in Aug, 2014.

·       Forest and MoEF clearance yet to be obtained.

16

Ghogra

Medium

Ajnal/ Narmada

Sehore

August, 2010

7.78

145.365

·       TAC note have been returned back with a request to expedite statutory clearances.

17

Saroj Sarovar

Medium ERM

Jhamad/ Mahi

Ratlam

June, 2013

6.52

13.9

·       Observations have been sent to  Project Authority regarding increased utilisation, lesser yield etc.

·       Compliance to earlier Investment clearance to be provided by project authorities.

18

Bhawsa

Medium

Amravati/ Tapi

Burhanpur

March-12

2.140

58.05

·       Preliminary Observation on the proposal have been sent Project Authority April, 2014. Interstate matters aspect, Clearance of forest land affected by the project yet to be obtained by the Project Authorities.

·       Indicative Master Plan of Tapti project for Choti utawali and Bhawasa project has been received from Project Authority.

·       Adm. Approval of State Govt, concurrence of state finance yet to be obtained by project authorities.

19

Chhoti Utawali

Medium

Chhoti Utawali/ Tapi

Burhanpur

October 2013

2.5

70.34

·       Indicative Master Plan of Tapti project for Choti utawali and Bhawasa project has been received from Project Authority.

·       Further Comments/ Observations on Preliminary Report have been sent to  Project Authority in Dec, 2013.

·       Clearance of forest, environment, Interstate matters need to be submitted by project authorities.

20

Keet Khedi

Medium

Kanthal/ Choti Kalisindh/ Chambal

Shajapur

Oct, 13

3.350

66.47

·       Revised DPR received from Project Authorities in Oct, 2013.

·       Environment, International and  Interstate matters clearance yet to be obtained by Project Authorities.

21

Semri

Medium

Semri/ Bina/ Betwa/ Yamuna

Raisen

Nov-13

5.700

110.9082

·       Project Authorities submitted DPR to IP(N) for clearance from inter State angle on 24.07.2014.

·       Comments on interstate aspect have been sent to Project Authority in Sept, 2014.

22

ERM proposal of Tawa Irrigation Project. * PPO

Major

Tawa/

Narmada

Hosangabad & Harda

Dec. 2012

254.484

2366.01

·       State Govt./ Project authority has been requested to remove/deduct the 4000 ha of CCA of Morand & Ganjal project from ERM of Tawa irrigation project and modify the DPR of ERM of Tawa irrigation project accordingly. The same is not received.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

MAHARASHTRA

 

Sl. No

Project

Major/

Medium

River/

Basin

District

Benefited

Date of

Receipt

Benefits

(Th. Ha)

Estt. Cost

(Crore)

Status

1

Jigaon

Major

Purna/ Tapi

Buldana,

Akola

12/09

112.32

4044.13

·         Observations on cost have been sent to Project Authority in September, 2014.

2

Upper Pravara

Major

Pravara/

Godavari

Ahmednagar

1/10

86.100

1810.19

·         Observations on Cost,  Hydrology                              and Irrigation Planning have been sent to Project Authority during May, 2014 to Aug, 2014.

·       MoEF and MoTA cleared.

3

Sulwade-Jamphal –Kanoli  LIS scheme

Major

Tapi

Dhule

5/2012

52.720

2148.29

(PL-2011-12)

·  The project was   considered in 115th TAC meeting in July 2012. Due to higher cost per hectare, the project was deferred by TAC.

·  Compliance of HCD, Embankment aspect received from Project Authority. CE, PAO, in Jan 2014 advised to discuss the matter with design Directorates for early finalization of design parameters.

4

Lower Penganga                                                                                                                                    Project

Major

Penganga/ Godawari

Yavatmal and Chandrapur

6/2012

227.241

10,429.0 (PL-2009

·       State Govt. advised in May 2014 to update the DPR as per suggestions of CWC due to major change in scope as compared to Preliminary Report cleared in year 2011.

·       Clearance from MoEF and MoTA (Andhra Portion) is yet to be obtained by project authorities.

5

Jihe Kathapur

Major

Krishna

Satara

12/2012

27.5

953.77 Crore (PL-2011-12

·       Observations on Barrage and canal   , Cost, Hydel Civil Design , Gates and Irrigation planning aspects  have been sent to Project Authority during Feb, 2013 to May, 2013.

·  MoEF and MoTA cleared.

6

Lower Tapi Project

Major

Tapi

Jalgaon

2/2013

25.6

1905.52 (PL-2011-12)

 

 

 

·       Observations on Embankment (7.6.13) and  Irrigation planning (17.9.13) aspects  have been sent to Project Authorities for compliance.

·  Compliance on Gates, Cost received from Project Authority.

·  Clearances from MoEF and MoTA awaited

·  Project authorities have been asked to furnish full hydrological data to finalise water availability, in a meeting held at CE, PAO Chamber

7

Kanhan

(Kochi Barrage)

Medium

Godavari

Nagpur

07/2012

3960

262.253

·  Compliance to observations on various aspects have been sent to Project Authority.

8

Katepurna LIS

Medium

Tapi

Akola

11/2009

4.137

69.97

·  Compliance to observations on various aspects have been sent to Project Authority.

9

Uma Barrage

Medium

Tapi

Akola

11/2009

5.510

78.62

·  Compliance to observations on various aspects have been sent to Project Authority.

10

Dogargaon-Thanegaon

Medium

Godavari

Godichiroli

07/09/2009

2.5

31.45

·  Compliance to observations on various aspects have been sent to Project Authority.

11

Babhali Barrage

Medium

Godavari

Nanded

28.03.2006

7.995

149.44

·       Comments on Hydrology have been sent to Project Authority  in Feb 2014.

·       Interstate matters aspect  cleared.

12

Bordi nalla

Medium

Tapi

Amravati

10.12.2009

4.126

176.87

·  Compliance to observations on various aspects have been sent to Project Authority.

13

Palasgaon Amdi LIS

Medium

Godavari

Chandrapur

8.10.2008

2.890

70.38

·  Compliance to observations on various aspects have been sent to Project Authority.

14

Prakasha Burai LIS

Medium

Tapi

Nandurbar

28.08.2012

7.085

439.31

·  Compliance to observations on various aspects have been sent to Project Authority.

15

Tajnapur LIS

Medium

Godavari

Ahmednagar

03.12.2012

6.960

438.70

·  Compliance to observations on various aspects have been sent to Project Authority.

16

Varkhede- Londhe Barrage

Medium

Tapi

Jalgaon

10.12.2012

7.919

236.02

·  Compliance to observations on various aspects have been sent to Project Authority.

 

MANIPUR

 

Sl. No.

Name of Project

Category

Rivers/

Basin

District Benefited

Date of receipt

Benefits (Th. Ha)

Estt.Cost (Crore)

Status

1.

Chakpi Multi-purpose Project

Medium

Chapki River/ Manipur River

Chandel, Thoubal

07/2012

 

9.860  Th ha CCA.

Flood Control :  5 Th ha,

Navigation, Water Supply  to  1 lakh population,  &    12.5 MW power

707.04  (PL-2011)

 

·          The Project is under appraisal in CMC, HCD, FMO, MoWR, & CGWB, Statutory clearances are awaited.

·          Cleared from Inter State aspects, Ministry of Agriculture.

·          Compliance to observations of Cost Appraisal (HWF) received in April, 2013.

·          Compliance to observations on Cost       (Irr.), Barrage and Canal Design, Irrigation Planning, Foundation Engg. And Special Analysis  , Embankment , Gates Design , Hydrology , and Central Soil & Material Research Station,Central Electric Authority have been sent to Project Authority during April, 2013 to Aug, 2013.

·         State Govt. informed in Jan 2014 that due to frequent PAP protests,   geo-technical exploration could not be started.  GSI (NER), Shillong is engaged for geological exploration during 2014-15.

 

 

ODISHA

 

Sl. No.

Project

Category

Rivers/

Basin

District Benefited

Date of receipt

Benefits (Th. Ha)

Estt. Cost (Crore)

Status

1.

Ong Dam Project

Major

Ong/ Mahanadi

Bargarh and Bolangir

Dec, 2011

30.0

1111.01

(PL -2012)

·         Clearance from MoTA not obtained.

·         Cost aspect is yet to be finalised.

2

Lower Vansadhara Project Stage-I

Major

Sananadi, Vansadhara

Rayagadu

June, 2014

22.15

611.40

·         INTERSTATE MATTERS Dte, CWC has informed that the DPR of the project is not acceptable form inter-state aspects. The same is being communicated to State Govt..

 

RAJASTHAN

 

S.

No.

Name of Project

Major/

Medium

River/

Basin

District

Benefited

Date of Receipt

Benefits

(Th.ha)

Estt.

Cost (cr)

Status

1

Manoharthana Irrigation Project

Medium

Parwan

Jhalawar

6/2011

CCA-9.8

93.10

·       Project proposal deferred by TAC due to non receipt of Environmental clearance. Project authorities have been requested to furnish environmental clearance.

 

TAMILNADU

Sl. No.

Project

Category

Rivers/

Basin

District Benefited

Date of receipt

Benefits (Th. Ha)

Estt. Cost (Cr)

Status

1.

Flood carrier canal from Kannadian Channel to drought prone area of Sathankulam, Thisaiyanvilal, by interlinking of river Tamiraparani, Karumeniyar and Nambiyar rivers

Major

Tamiraparani, Karumeniyar andNambiyar/ Tamiraparani

Tirunelveli and Thoothukudi

11/2011

23.04

572.40

·         MoEF Clearance awaited. EIA study is under progress.

·         Cost shall be updated and finalized  after the environmental clearance

 

UTTAR PRADESH

Sl.

No.

Name of Project

Major/

Medium

River/

Basin

District Benefited

Date of Receipt

Benefit

(Th.Ha)

Estt. Cost

(Cr.)

Status

1

Project for providing irrigation facilities in 15 villages of Babina block

Medium

Betwa/ Yamuna

Jhansi

08.03.2013

CCA-5.799

212.64 (PL-6/2011)

·         The proposal is under appraisal in CWC, Lucknow

·         Modified Report was submitted by the Project Authority in Sept, 2014. Further supplementary report on the project was submitted by the Project Authority in Sept, 2014.

·         The report is under examination.

2

Badaun Lift Canal Irrigation Project

Major

Ganga/ Ganga

Badaun, Sambhal

14.08.2014

CCA-139.665

1850.35

·         DPR circulated to specialised Dte.,& other Central Agencies in Aug, 2014.

·         Observations on Inter-State angle, hydrology and Agriculture aspects have been sent to Project Authority during Sept, 2014 to November, 2014..

·         Clearance on construction machinery aspects received.

UTTARAKHAND

Sl.

No.

Name of Project

Major/

Medium

River/

Basin

District Benefited

Date of Receipt

Benefit

(Th.Ha)

Estt. Cost

(Cr.)

Status

1

Strengthening, Renovation and Moderation of existing Baur and Haripura dam in Bazpur/Gadarpur block district Udham Singh Nagar (ERM),

Major

Baur, Karrala, Bhakra river (Ramg-anga/ Ganga Basin)

Rampur (UP), Udham Singh Nagar

01/09/

2011

74.391

34.15         ( PL 2010)

·         Comments on Embankment, Hydrology, Cost, Dam Safety, CSMRS, Irrigation Planning aspects were sent to Project Authorities during Oct, 2011 to Feb, 2012.

·         The proposal is being returned to State Govt. due to non-submission of compliance for more than a year

 

 

 

 

Samir/jk

 

 

 