Participative Policy for rail connectivity and capacity augmentation was issued
in December, 2012 which provides five different models of PPP.
Under the policy PPP projects initiated during the Twelfth Five Year Plan are given
below.
Projects under PPP model
are undertaken on the basis of financial viability, bankability and interest of
stakeholders.
Cost
of such PPP projects is estimated at around ₹
14,000 crore of which projects worth of ₹
11,000 crore approximately do not require any
financial commitment from Ministry of Railways.
Each
of the projects has target for completion within 3-5 years of start of
construction.
APPENDIX REFERRED TO IN
REPLY TO PART (a) OF UNSTARRED QUESTION NO. 764 BY SHRI PARIMAL
NATHWANI ANSWERED
IN RAJYA SABHA ON 04.12.2015 REGARDING RAILWAY PROJECTS DURING TWELFTH FIVE
YEAR PLAN UNDER PPP MODEL
1.
Sanctioned PPP projects under
implementation ( Private line and Joint Venture):
Sl.No
|
Project name
|
Cost in Cr.
|
Km
|
Zone
|
State
|
|
1
|
Digni - Jaigarh Port( NL)
|
771
|
35
|
KRCL
|
Maharashtra
|
|
2
|
Roha- Dighi Port (NL)
|
724
|
34
|
CR
|
Maharashtra
|
|
3
|
Palanpur- Samkhayali (D/L)
|
1267
|
248
|
WR
|
Gujarat
|
|
4
|
Gevra Road-Pendra Road (NL)
|
838
|
122
|
SECR
|
Chhattisgarh
|
|
5
|
Kharasia-Dharamjaigarh - Ghargoda-Donga Mahua, (NL)
|
1647
|
104
|
SECR
|
Chhattisgarh
|
|
6
|
Rowghat-Jagdalpur (NL)
|
304
|
140
|
SECR
|
Chhattisgarh
|
|
7
|
Tuna Port
|
142
|
17
|
WR
|
Gujarat
|
|
|
Total
|
5693
|
700
|
|
|
2. Sanctioned projects under implementation (Customer Funded):
Sl.No
|
Project
name
|
Cost in
Cr.
|
Km
|
Zone
|
State
|
|
1
|
Hotgi- Kudgi section (Doubling)
|
946
|
134
|
SWR
|
Karnataka
|
|
2
|
Manpur-Tilaiya-Bakhityarpur section (Electrification)
|
140
|
135
|
ECR
|
Bihar & Jharkhand
|
|
3
|
Lalitpur-Udaipura (Electrification)
|
44
|
28
|
NCR
|
UP
|
|
4
|
Balgona-Katwa Section (GC)
|
112
|
25
|
ER
|
West Bengal
|
|
5
|
Bhaktiyarpur Flyover including 3rd Line
|
250
|
18
|
ECR
|
Bihar
|
|
6
|
Khandwa-Nimar Kheri (GC)
|
487
|
35
|
WR
|
MP
|
|
7
|
Jagdalpur-Ambagaon (Doubling)
|
257
|
25
|
ECoR
|
Chhattisgarh
|
|
|
Total:
|
2236
|
400
|
|
|
3. Sanctioned
projects identified for implementation through Annuity route:
Sl.No
|
Project name
|
Cost in Cr.
|
Km
|
Zone
|
State
|
|
1
|
Bhadrak-Nargundi 3rd line
|
900
|
80
|
ECoR
|
Odisha
|
|
2
|
Kazipet-Vijaywada 3rd line with electrification
|
1566
|
202
|
SCR
|
Telangana & Andhra Pradesh
|
|
3
|
Nagpur-Wardha 3rd line
|
550
|
76
|
CR
|
Maharashtra
|
|
|
Total:
|
3016
|
358
|
|
|
4. Projects under PPP where In Principle approval granted:
Sl.No
|
Project name
|
Cost in Cr.
|
Km
|
Zone
|
State
|
|
1
|
New Bhubaneswar - Astrangra Port /ECoR/New line, Odisha
|
1310
|
75
|
ECoR
|
Odisha
|
|
2
|
Sayan/Kim -Hazira Port /WR/New line, Gujarat
|
734
|
47
|
WR
|
Gujarat
|
|
3
|
Hamrapur- Rewas port /CR/New line
|
349
|
26
|
CR
|
Maharashtra
|
|
4
|
Bhimnath- Dholera Rail Link /WR/, (New Line)
|
252
|
27
|
WR
|
Gujarat
|
|
5
|
Chhara Port/WR/New Line
|
351
|
20
|
WR
|
Gujarat
|
|
6
|
Nargol Port /WR/ New Line
|
82
|
11
|
WR
|
Gujarat
|
|
|
Total:
|
3078
|
206
|
|
|
This information was given by the Minister of State
for Railways Shri Manoj Sinha in a written reply to a question in Rajya Sabha
today.
****