Three New JNNURM projects for Kolkata approved
Ministry of Urban Development has given approval to three new JNNURM
projects in Kolkata, West Bengal. The Central sanctioning and monitoring committee
for the sanctioning of projects under submission-1, Urban infrastructure and
governance (UIG) has sanctioned Transmunicipal
surface water supply scheme for Dum Dum, North Dum
Dum and South Dum Dum municipality,
Municipal solid waste management project
of 13 municipal towns of Kolkata (Halisahar, Kanchrapara,
Kayani, Gayeshpur, Nalhati, Bhatpara, Khardah, Barasat, Madhyamgram, Mahestala, Pujali, Baruipur and Uluberia) and construction
of flyover from Parks Circus to Parama Island.
The first project will improve
the deteriorating ground water supply, both in quality and quantity by augmenting
the existing water treatment plant at Kamarhati from 140 MLD to 280 MLD by
utilizing the water from existing source. After implementation of the project
24Hrs connectivity will be provided to 100% households. The project will reduce
the wastage of water by replacing the leaky pipe and installing water meters
to measure the actual consumption. The project will be implemented in 30 months
by Kolkata Municipal Corporation.
Regarding the solid waste management project for 13 municipal towns,
it would cover 251.40sqkms of area and a population 24.90lakhs. The project
will address the problem of source segregation of solid waste, street side
storage in open masonry vats, open dumping in low
lying areas, designing of sanitary landfill site with requiste
infrastructure facilities treatment of MSW through Vermi/Mechanical
composting. The Construction of flyover from Parama
Island will ease traffic congestion at Park Road due to 7 roads meeting at
the intersection. The project would be completed by March 2010.
The details of the projects are as under:
|
Sl. No.
|
Mission City/State
|
Project Cost
|
Approved Cost
|
Central Share
|
ACA Proposed to be released
|
|
1
|
Kolkata, West Bengal
|
Transmunicipal Surface Water Supply scheme for Dum Dum, North Dum Dum and South
Dum Dum Municipalities
|
31272.08
|
10945.23(35%)
|
2616.04 (1st installment)
|
|
2
|
Kolkata, West Bengal
|
Municipal Solid Waste
Management of 13 municipal towns for Kolkata (Halisahar,
Kanchrapara, Kayani, Gayeshpur, Nalhati, Bhatpara, Khardah, Barasat, Madhyamgram, Mahestala, Pujali, Baruipur and Uluberia)
|
11196.52
|
3918.78(35%)
|
979.69 (1st installment)
|
|
3
|
Kolkata, West Bengal
|
Construction of Flyover
from Park Circus to Parama Island
|
29166.14
|
10208.15(35%)
|
2552.04 (1st installment)
|
The CSMC also sanctioned 2nd and 3rd
installments in respect of 5 ongoing projects as under:-
|
4
|
Kolkata, West Bengal
|
Construction of Flyover
between E.M. Bypass and Kazi Nazrul
Islam Sarani
|
3802.00
|
1330.70(35%)
|
332.67 (2nd installment)
|
|
5
|
Kolkata, West Bengal
|
Surface Water Supply scheme
within added areas of Howrah Municipal Corporation
|
9068.91
|
3174.12(35%)
|
793.53 (2nd installment)
|
|
6
|
Kolkata, West Bengal
|
Development and management
of water supply and sewerage systems of Sector-V under NDITA at Salt Lakh (Phase-I)
|
2606.62
|
912.32(35%)
|
228.08 (3rd installment)
|
|
7
|
Kolkata, West Bengal
|
10MGD water treatment plant
at Uluberia Municipal Town under KMDA
|
4558.00
|
1595.30(35%)
|
398.83 (3rd installment)
|
|
8
|
Kolkata, West Bengal
|
Underground water
reservoir-cum-booster pumping station at Gandhi Maidan
Akra
|
1066.00
|
373.10(35%)
|
93.28 (2nd installment)
|
TFK/AP
(Release ID :47982)