Ministry of Housing & Urban Affairs04-January, 2010 15:38 IST
New projects for West Bengal under JNNURM approved

 

            The Central Sanctioning and Monitoring Committee (CSMC) for sanctioning of projects under Sub Mission of UIG under Jawaharlal Nehru  National Urban Renewal  Mission (JNNURM) has approved new projects for West Bengal.

            The storm water drainage project in  Budge Budge Municipal area  within Kolkata Urban Agglomeration, West Bengal was approved by CSMC in order to rid the town of water logging during monsoons affecting the routine economic activities. The situation worsens in the absence of storm water drains.  The project would build comprehensive storm water drainage system in the town with proper outfalls to the river through cannals. The system will provide 100% coverage of total road network of 32 kms. The project will be implemented in 24 months. The details of the project are as under:-

Rs. In lakhs

S.No.

Mission City/State

Project Name

Project Cost

Central Share

Installment (25% of Central Share) to be released

1.

Kolkata, West Bengal

Storm Water Drainage Scheme in Budge Municipal Area within Kolkata U.A.

3480.16

1218.05

 304.51

 (1st instt.)

 

            Another project for Durgapur, Urban Agglomeration of Asansol, West Bengal - 24X7   water supply scheme (Phase-III) was approved to ensure adequate potable water supply as per norms for the uncovered wards of Durgapur Municipal Corporation  and new growth areas covered under the project. The project will provide connectivity of  100% households and a supply pattern of  24X7 as per  JNNURM objectives  and  it will also provide water metering system to ensure sustainability of

 

the water project and incentivize conservation of water.  The project will cover slum population of 1.38 lakhs and minority population of 1.13 lakhs . The project will be implemented by Durgapur Municipal corporation and will take  2 years for completion. The details of the project are as under:-

Rs. In  lakhs

S.No.

Mission City/State

Project Name

Project Cost

Central Share

Installment (25% of Central Share) to be released

2.

Durgapur (UA of Asamsol), West Bengal

24x7 water supply scheme (Phase-III) for Durgapur

12681.40

6340.70

1585.18

(1st instt.)

TFK/KS


(Release ID :56593)