S. No.
|
State
|
Name of the cluster and district
|
Amount released during 2004 – 05 to 2006 – 07
|
Cumulative expenditure upto
30.06.10
|
% of Expenditure
|
Achievements
|
|
1
|
Assam
|
Gohpur
Dist: Sonitpur
|
386.00
|
390.83
|
100.00
|
A total of 73 works under road
connectivity were sanctioned, out of which 45 works related to road improvement
whereby small existing roads have been broadened, raised and extended by
earth-work. 25 R.C.C. culverts have been constructed at vantage points to
ensure water drainage throughout the year. 3 road works are for Black
Topping.
The work relating to construction of 2
science laboratory, 3 knowledge centre, 1 godown for agriculture produce and 1 multi chamber cold
storage facility have been completed.
The work relating to
setting up a marketing centre including a slaughter house, construction of Kisan Ghar and drainage and
sewerage have been completed.
|
|
2
|
Andhra Pradesh
|
Rayadurg
Dist. Anantpur
|
328.80
|
297.10
|
90.36
|
6 road works for providing BT surface and
6 road works for gravelling were taken. All works have been completed.
In case of drinking water, 6 works
were sanctioned and all of them have been completed.
In case of Anganwadi
centres, 2 works were sanctioned and both have been
completed.
In case of setting up of Common
Facility Centre (CFC), a training hall with a provision of 200 machines has
been constructed. The machines are being purchased.
|
|
3
|
Bihar
|
Motipur
Dist: Muzaffarpur
|
384.00
|
379.96
|
98.94
|
13 road works were undertaken, out of
which 12 works were completed and 1 road work is in progress.
In case of market connectivity, the
construction of 16 shops, marketing sheds have been completed.
|
|
4
|
Maharashtra
|
Basmath
Dist: Hingoli
|
427.30
|
357.36
|
83.63
|
In case of road connectivity, out of 32
works 19 have been completed, 11 are ongoing and 2 have not been started.
In case of drinking water, out of 5 works
1 work has been completed, 4 are in progress.
In case of employment generation, 21
groups have been selected and activities like Jaggary
Making Unit, Banana Chips, Dall
Mill etc. have been identified. Administrative sanctions for 16 activities have
been accorded and works are in progress.
In case of setting up of library and
shopping complex, the work is under progress.
|
|
4
|
Maharashtra
|
Basmath
Dist: Hingoli
|
427.30
|
357.36
|
83.63
|
In case of road connectivity, out of 32 works
19 have been completed, 11 are ongoing and 2 have not been started.
In case of drinking water, out of 5
works 1 work has been completed, 4 are in progress.
In case of employment generation, 21
groups have been selected and activities like Jaggary
Making Unit, Banana Chips, Dall
Mill etc. have been identified. Administrative sanctions for 16 activities
have been accorded and works are in progress.
In case of setting up of library and
shopping complex, the work is under progress.
|
|
5
|
Orissa
|
Kujanga
Dist: Jagat
singhpur
|
545.00
|
332.41
|
61.00
|
13 road works were taken up and all the
road works have been completed.
In case of market connectivity, construction of 50 shop rooms are in progress at Bhutmundai and Paradeepgada.
In case of power connectivity, the work
is under progress.
|
|
6
|
Rajasthan
|
Shahpura
Dist: Bhilwara
|
401
|
297.71
|
74.24
|
In case of road
connectivity, out of 18 road works 15 have been completed and 3 are
ongoing.
In
case of education, 15 class rooms have been constructed.
In case of health, construction of Anganwadi center in Nimbahera
and Aarni villages has been completed.
In case of Computer/ Internet
Connectivity/ Rural Capacity Building centre, actual works are yet to be
started, though letter of expression of interest has been issued.
|
|
7
|
Uttar Pradesh
|
Bharthana
Dist: Etawah
|
527.90
|
534.06
|
100.00
|
Work relating to 44.50 km of bricks
laying (kharanza), repairing of old kharanza of 15
km and 2.60
Km of road (along both side drain) have been
completed.
In case of market connectivity, 4 market shops / godown
have been constructed.
In case of setting up of 3 mini stadiums
and wrestling facilities, the work has been completed.
|
|
|
Total
|
3000.00
|
2589.43
|
86.31
|
|