The first phase of
the Jawaharlal Nehru National Solar Mission (JNNSM) is scheduled to be
completed by 2013 only. However, as per progress available so far all the
application segments of the Mission are going on as scheduled and on target.
The details of projects sanctioned under the
Phase-I of the JNNSM are as under:
i) Projects under Migration Scheme (84
MW-Solar PV - 54MW, Solar Thermal – 30 MW)
ii) Projects under New Project Scheme
(Batch-I) (Solar PV- 150 MW, Solar Thermal- 470 MW):
iii) Projects
under New Projects Scheme (Batch-II) (Solar PV- 350 MW)
iv)
Projects under Roof top PV
and Small Solar Power Generation Programme (RPSSGP) –
98.05 MW
The details of the projects are given below:-
a) Projects under Migration Scheme (84 MW – Solar PV-54 MW,
Solar Thermal-30 MW)
State
|
Projects under Migration
Scheme
|
Solar PV (MW)
|
Solar Thermal (MW)
|
Total (MW)
|
Rajasthan
|
36
|
30
|
66
|
Maharashtra
|
11
|
|
11
|
Punjab
|
7
|
|
7
|
Total
|
54
|
30
|
84
|
b) Projects under Batch-I, Phase-I (Solar PV-150 MW, Solar
Thermal-470 MW)
State wise details of Selected Capacity is as under:
State
|
New Projects
|
Solar PV (MW)
|
Solar Thermal (MW)
|
Total (MW)
|
Rajasthan
|
105
|
400
|
505
|
Maharashtra
|
5
|
|
5
|
Andhra
Pradesh
|
15
|
50
|
65
|
Karnataka
|
10
|
|
10
|
Gujarat
|
|
20
|
20
|
Orissa
|
5
|
|
5
|
Tamil
Nadu
|
5
|
|
5
|
Uttar
Pradesh
|
5
|
|
5
|
Total
|
150
|
470
|
620
|
Out of the above, PPA’s were signed with 36 Solar Power Developers for
145 MW Solar PV and 470 MW of Solar Thermal by 10th January, 2011.
c) Projects under Batch-II, Phase-I (Solar PV-350 MW)
State
|
Project Capacity
(MW) /
No. of Projects
|
Solar PV (MW)
|
5
|
10
|
15
|
20
|
Total
|
Rajasthan
|
5
|
9
|
4
|
6
|
24
|
295
|
Maharashtra
|
1
|
|
|
1
|
2
|
25
|
Andhra
Pradesh
|
|
|
|
1
|
1
|
20
|
Tamil
Nadu
|
|
1
|
|
|
1
|
10
|
Total
|
6
|
10
|
4
|
8
|
28
|
350
|
Out of the above,
PPA’s were signed with 21 selected bidders for 27 Solar Power projects (340 MW)
by 27th January, 2012.
d)
Projects under Roof top PV and Small Solar Power
Generation Programme (RPSSGP) – 98.05 MW
S. no
|
State
|
Sanctioned
Project Capacity (MW)
|
1
|
Andhra Pradesh
|
10.5
|
2
|
Chhattisgarh
|
4
|
3
|
Haryana
|
8.8
|
4
|
Maharashtra
|
5
|
5
|
Orissa
|
8
|
6
|
Punjab
|
8.5
|
7
|
Rajasthan
|
12
|
8
|
Tamil Nadu
|
7
|
9
|
Uttrakhand
|
5
|
10
|
Uttar Pradesh
|
8
|
11
|
Jharkhand
|
16
|
12
|
Madhya Pradesh
|
5.25
|
Total
|
98.05
|
No project is pending
for approval with the Ministry.
The details of the projects completed,
commissioned and synchronized with the grid, State-wise are provided below:-
a) Migration Projects: Commissioning Status of the Solar PV
Projects (as per reports received from State Nodal Agencies)
State
|
Solar PV capacity
to be commissioned as per PPA
(MW)
|
Solar PV capacity
actually commissioned
(MW)
|
Rajasthan
|
36
|
35
|
Maharashtra
|
11
|
9
|
Punjab
|
7
|
2
|
Total
|
54
|
46
|
Solar Thermal
Projects (30 MW) to be commissioned in 28 months from the date of signing of
PPA (i.e. up to mid February, 2013)
b) Projects under Batch-I, Phase-I - Commissioning Status of
the Solar PV Projects (as per reports received from State Nodal Agencies)
State
|
Solar PV capacity
to be commissioned as per PPA (MW)
|
Solar PV capacity
actually commissioned
(MW)
|
Rajasthan
|
100
|
100
|
Maharashtra
|
5
|
-
|
Andhra
Pradesh
|
15
|
10
|
Karnataka
|
5
|
-
|
Orissa
|
5
|
5
|
Tamil
Nadu
|
5
|
5
|
Uttar
Pradesh
|
5
|
5
|
Total
|
140
|
125
|
Solar Thermal Projects (470 MW) scheduled to be commissioned in 28 months
from the date of signing of PPA (i.e. up to mid May, 2013).
c) Projects under Batch-II, Phase-I
Solar PV Projects
(340 MW) scheduled to be commissioned in 13 months from the date of signing of
PPA (i.e. Feb, 2013)
d)
Rooftop PV and Small Solar Power Generation Programme (RPSSGP)
State
Wise:
S. No.
|
State
|
Solar
PV
|
Solar
PV
|
|
|
|
capacity
to be
|
capacity
|
|
|
|
commissioned
|
actually
|
|
|
|
as
per PPA
|
commissioned
|
|
|
|
(MW)
|
(MW)*
|
|
|
|
|
|
|
1
|
Andhra
Pradesh
|
10.5
|
7.75
|
|
2
|
Chhattisgarh
|
4
|
4
|
|
3
|
Haryana
|
8.8
|
7.8
|
|
4
|
Maharashtra
|
5
|
5
|
|
5
|
Orissa
|
8
|
5
|
|
6
|
Punjab
|
8.5
|
5.5
|
|
7
|
Rajasthan
|
12
|
8
|
|
8
|
Tamil
Nadu
|
7
|
5
|
|
9
|
Uttrakhand
|
5
|
3
|
|
10
|
Uttar
Pradesh
|
8
|
5
|
|
11
|
Jharkhand
|
16
|
2
|
|
|
|
|
|
|
12
|
Madhya
|
5.25
|
0
|
|
Pradesh
|
|
|
Total
|
98.05
|
58.05
|
|
|
|
|
|
*Out of total 78 sanctioned Projects 11
Projects are to be commissioned by June, 2012.
The
guidelines that deal with the import of solar modules for Phase-I are specified
as under:
Batch-I: For Solar PV
Projects, it is mandatory for Projects based on crystalline silicon technology
to use the modules manufactured in India.
Batch-II: For Solar PV Projects to be selected
in second batch, it will be mandatory for all the projects to use cells and
modules manufactured in India. PV Modules made from thin film technologies or
concentrator PV cells may be sourced from any country, provided the technical
qualification criterion is fully met.
All the Developers
using Crystalline Silicon technology have confirmed compliance of domestic
content clause.
Following
allegations in a section of the media about violation of guidelines by some
companies, the Ministry has set up an inquiry committee. The committee
comprises representatives from the Ministries of New & Renewable Energy,
Power and Corporate Affairs.
The
inquiry committee is yet to submit its final report.
This information was
given by the Minister of New and Renewable Energy Dr. Farooq
Abdullah in a written reply to a question in Lok Sabha today.
…
MA/KT/VN