GUJARAT – Rs.54,856 cr
Port
Modernization
|
|
Projects
|
Investment
( INR Cr)
|
|
1
|
LPG
Import Terminal at Kandla
|
500
|
|
2
|
LNG
Import Terminal at Mundra
|
4,000
|
|
3
|
Dredging
of the common channel of Magdalla and Sewagram
|
30
|
|
4
|
Mechanisation
of Barge Unloading Facility at Kandla
|
100
|
|
5
|
Development
of Tuna Tekra Container Terminal at Kandla
|
2,000
|
|
6
|
Development
of Tuna Tekra Additonal Bulk Terminal at Kandla
|
1,200
|
|
7
|
Mechanisation
of Fertiliser Handling Facility at Kandla
|
200
|
|
8
|
Mechanisation
of Food Grains Handling Facility at Kandla
|
155
|
|
|
Total
|
8185
|
Port-led Industrialization
|
|
Projects
|
Investment
(
INR Cr)
|
|
1
|
Petrochemical
cluster in Gujarat
|
420
|
|
2
|
Development
of an export based apparel cluster in Saurashtra
|
3,321
|
|
3
|
Cement
Cluster in Gujarat
|
735
|
|
4
|
Maritime
cluster in Saurashtra
|
5,000
|
|
5
|
Development
of marble based furniture hub in Kutch
|
2,258
|
|
6
|
Auto
cluster in Sanand
|
4,465
|
|
|
Total
|
16,199
|
Port Connectivity
|
|
Projects
|
Investment
( INR Cr)
|
|
1
|
Expansion
of Salaya Mathura Pipeline
|
1,000
|
|
2
|
Expressway
from Sarkhej ( Ahmedabad) to Mundra
|
10,000
|
|
3
|
Expressway
from Sarkhej ( Ahmedabad) to Pipavav
|
9,000
|
|
4
|
Connection
of Western DFC to Hazira
|
300
|
|
5
|
Connection
of Western DFC to Pipavav
|
2,500
|
|
6
|
Connection
of Western DFC to Mundra
|
3,500
|
|
7
|
Providing
alternative Road from Bhavnagar to Sosiya-Alang Ship Recycling Yarad
|
70
|
|
8
|
RoB
on Kandla-Kutch Road
|
125
|
|
9
|
Product
pipeline from Jamnagar to Mundra
|
500
|
|
|
Total
|
29,695
|
Coastal Community Development
|
|
Projects
|
Investment
( INR Cr)
|
|
1
|
Development
of Gujarat Maritime University
|
268
|
|
2
|
Ro-Pax
Ferry Services between Gogha and Dahej in Gulf of Cambay
|
509
|
|
|
Total
|
777
|
GOA – Rs.2,823 cr
Port Modernization
|
|
Projects
|
Investment(
INR Cr)
|
|
1
|
Finger
Jetty at Vasco Bay for Liquid Cargo, Passenger and Fishing at Mormugao
|
80
|
|
2.
|
Redevelopment
of berths 8 and 9 into multipurpose terminal at Mormugao
|
1,085
|
|
3
|
Conversion
of berth 3 into multipurpose berth at Mormugao
|
150
|
|
|
Total
|
1,315
|
Port Connectivity
|
|
Projects
|
Investment
( INR Cr)
|
|
1
|
Road
circulation plan for ease of movement of break bulk cargo at Mormugao
|
50
|
|
2
|
Hospete-Hubballi-Londa-Tinaighate-Vasco
da gama at Mormugao
|
1,458
|
|
|
Total
|
1,508
|
KARNATAKA – Rs. 6,215 crore
Port
Modernization
|
No.
|
Projects
|
Investment
(INR Cr)
|
|
1.
|
Mechanised
food grain handling facility at Mangalore
|
120
|
|
2.
|
Mechanised
fertilizer handling facility at Mangalroe
|
155
|
|
|
New
Port at Belekari
|
4,000
|
|
|
Total
|
4,275
|
Port
– led Industrialization
|
No.
|
Projects
|
Investment
(INR Cr)
|
|
1.
|
Petrochemical
cluster in Mangalore
|
420
|
|
|
Total
|
420
|
Port
Connectivity
|
No.
|
Projects
|
Investment
(INR Cr)
|
|
1.
|
Rail
evacuation from port to Hospet and Bellary (Hubli – ankoka Link)
|
1,000
|
|
2.
|
Bellikeri
port to Ankola – Railways line
|
1,420
|
|
3.
|
4
Laning of Shiradi Ghat Road – Concretizing for smoothening of traffic road
|
1,200
|
|
4.
|
New
ICD Development in Hubli and Mangalroe
|
170
|
|
|
Total
|
3,790
|
Coastal
Community Development
|
No.
|
Projects
|
Investment
(INR Cr)
|
|
1.
|
Development
of Fishery Harbour at Kulai
|
230
|
|
|
Total
|
230
|
KERALA – Rs. 2,604 crore
Port
Modernization
|
No.
|
Projects
|
Investment
(INR Cr)
|
|
1.
|
Setting
up of fertilizeer bagging facility at Cochin
|
155
|
|
2.
|
Setting
up of food grain import terminal at Cochin
|
120
|
|
3.
|
Setting
of edible oil terminal at Cochin
|
10
|
|
|
Total
|
285
|
Port
– led Industrilization
|
No.
|
Projects
|
Investment
(INR Cr)
|
|
1.
|
Development
of an integrated wooden furniture export
|
2,258
|
|
|
Total
|
2,258
|
Port
Connectivity
|
No.
|
Projects
|
Investment
(INR Cr)
|
|
1.
|
Azhikkal
Port – Proposed NH – Bypass (13 km) with widening of 2 km
|
61
|
|
|
Total
|
61
|
TAMIL NADU – Rs.89,406 crore
Port
Modernization
|
No.
|
Projects
|
Investment
(INR Cr)
|
|
1.
|
LNG
Import Terminal at Ennore
|
3,000
|
|
2.
|
NCB
1 – Utilisation of its full capacity at Tuticorin
|
760
|
|
3.
|
Dedicated
coastal berth for food grain imports at Tuticorin
|
80
|
|
4.
|
Development
of additional container berths at Tuticorin
|
1,200
|
|
5.
|
Upgrading
of existing coal jetty (CJ2) at Tuiticorin
|
250
|
|
6.
|
Multi
– User Liquid Terminal-II at Ennore port
|
320
|
|
7.
|
SBM
terminal at Chennai port
|
600
|
|
8.
|
Development
of Cuddalore / Sirkazhi port
|
3,000
|
|
9.
|
Ne
Port at Enayam serving as a transhipment hub
|
6,575
|
|
10.
|
Installation
of buoys at Pamban
|
2
|
|
|
Total
|
15,787
|
Port
– led Industrialization
|
No.
|
Projects
|
Investment (INR Cr)
|
|
1.
|
Petrochemical
cluster in Ennore
|
420
|
|
2.
|
Power
plant in Tamil Nadu
|
7,350
|
|
3.
|
Development
of an integrated export based leather and footwear cluster in Perambur
|
1,880
|
|
4.
|
Refinery
and petchem cluster in Tamil Nadu
|
4,200
|
|
5.
|
Marine
cluster in Ennore
|
5,000
|
|
6.
|
Steel
cluster in Ennore
|
10,500
|
|
|
Total
|
29,350
|
Port
Connectivity
|
No.
|
Projects
|
Investment (INR Cr)
|
|
1.
|
Northern
Rail Link connecting north of Minjur to KPL
|
168
|
|
2.
|
Expressway
from Tirupur industrial cluster (Combatore) to Enayam
|
13,000
|
|
3.
|
Expressway
from Whitefield industrial cluster (Bangalore) to Enayam
|
20,000
|
|
4.
|
Expressway
from Whitefield industrial cluster (Bangalore) to Chennai
|
10,000
|
|
5.
|
Road
connectivity to Hare Island (Tuticorin Port)
|
54
|
|
6.
|
Development
of roads connectivity to Cuddalore Port
|
100
|
|
7.
|
Four
lane road from Northern gate of port to Thachur, outering corridor – 6 laning
ith service roads
|
271
|
|
8.
|
Enhanced
pipeline capacity to CPCL Manali, increasing dia from 30” to 42”
|
500
|
|
9.
|
Connectivity
to Enayam through Nagarcoil
|
86
|
|
10.
|
Developmnet
of Coastal road to the East of container mTerminal II at Chennai Port
|
90
|
|
|
Total
|
44,269
|
ANDHRA PRADESH – Rs. 46, 745 crore
Port
Modernisation
|
No.
|
Projects
|
Investment
(INR Cr)
|
|
1.
|
LNG
Import Terminal at Kakinada
|
3,000
|
|
2.
|
Additional
Oil Jetty at Vizag
|
100
|
|
3.
|
Additional
STackyard for GCB at Vizag
|
150
|
|
4.
|
Development
o coastal food export berth at Kakinada
|
150
|
|
5.
|
New
Port Development Vadarevu / Machilipatnam
|
5,000
|
|
|
Total
|
8,400
|
Port
– led Industrilization
|
No.
|
Projects
|
Investment
(INR Cr)
|
|
1.
|
Petrochemical
cluster in Kakinada
|
420
|
|
2.
|
Port-based
Mega food processing park in Kakinada
|
2,479
|
|
3.
|
Power
cluster in AP
|
7,350
|
|
4.
|
Development
of an export based apparel cluster in central AP
|
3,321
|
|
5.
|
Development
of an export based electronic cluster in Tamil Nadu / AP
|
3,542
|
|
6.
|
Cement
cluster in AP
|
735
|
|
|
Total
|
|
Port
Connectivity
|
No.
|
Projects
|
Investment
(INR Cr)
|
|
1.
|
Upgrading
of the existing four lane road connecting to NH-16 at Gajuwaka to Gangavaram
Port in to six lane road in the State of Andhra Pradesh
|
50
|
|
2.
|
Four
laning of Kakinada Anchorage Port Uppada beach road connection upto NH-16 in
East Godavari District of Andhra Pradesh State
|
980
|
|
3.
|
Expressway
from Sanathnagar industrial cluster (Hyderabad) to Vodarevu
|
10,000
|
|
4.
|
Developmnet
of 7.2 Km green field road connecting NH 65 to Machilipatnam Port in the
state of Andhra Pradesh
|
175
|
|
5.
|
Four
ane green field road to Krishnapatnam Port from Naidupeta in the State of
Andhra Pradesh
|
670
|
|
6.
|
Upgrading
existing B.T. Road in to C.c. pavement from Burmah Shell area to security
gate near Sakthi Gas Plant at Kaknada Anchorage Port, AP
|
15
|
|
7.
|
Development
of Greenfield bypass road for better connectivity of Gangavaram port in
Visakhapatnam District (Lanes to be specified)
|
80
|
|
8.
|
Formation
of New by pass parallel road west of NFCL and CFL in Kakinada Port
(Kakinada), AP
|
70
|
|
9.
|
RoB
at Dummalapeta and Old Port Area (Kakinada)
|
80
|
|
10.
|
Upgrading
of existing R&B road from Chilakaru cross (NH-16) to Power Plants
|
300
|
|
11.
|
Development
of 5 km Greenfield road connecting north and south industrial cluser of
Khandaleru Creek near Krishnapatnam port
|
90
|
|
12.
|
Upgrading
of 24 km road to a 4 lane, that connects Nellore city to the Krishnapatnam
port to NH 5 in SPSR Nellore District of AP
|
300
|
|
13.
|
Upgrading
of Manginapudi Beach Road to a 4 lane road to connect to cater to
Machilipatnam
|
60
|
|
14.
|
D3evelopment
of 4 Lane green field road from Machilipatnam North Port to NH-SH-46 in the
State of Andhra Pradesh
|
232
|
|
15.
|
Development
of 4 lane green field road from Machilipatnam South Port to NH-9 in the State
of Andhra Pradesh
|
458
|
|
16.
|
IB
signalling for RV line
|
50
|
|
17.
|
Decongesting
RV line (Vizag & Gangavavaram port) – 2nd line
|
4,200
|
|
18.
|
Connectivity
of Vizag port to NH-16 (Phase II)
|
99
|
|
19.
|
Rail
connectivity between Krishnapatnam and Venkatachalam
|
87
|
|
20.
|
Rail
connectivity between Krishnapatnam to Obulavaripalle
|
1,185
|
|
21.
|
Road
Connectivity from outer Harbour to aPort connectivity junction (B) at Vizag
port
|
14,
|
|
22.
|
Development
of Fly over bridge from Sea-horses junction area to dock area t Vizag Port
|
277
|
|
|
Total
|
20,119
|
Coastal Community Development
|
No.
|
Projects
|
Investment
(INR Cr)
|
|
1.
|
Setting
up logistics and Maritime University at Kakinada
|
300
|
|
2.
|
Developmnet
of fish landing centre in AP - Appikonda
|
39
|
|
3.
|
Proposal
for fisheries growth centre for development of fisheries a Uppada in East
Godavari District, Andhra Pradesh and Majali in Uttaa Kannada, Karnatak
|
40
|
|
|
Total
|
379
|
ODISHA – Rs.28,321 cr
Port Modernization
|
|
Projects
|
Investment ( INR Cr)
|
|
1
|
Development
of IWT Terminal at Paradip Port
|
300
|
|
2
|
Expansion
of the MCHP stackyard for additional coal storage at Paradip
|
150
|
|
3
|
Development
of Outer harbour at Paradip port
|
4,250
|
|
4
|
Conversion
of IOB berth into coal exporting berth at Paradip
|
600
|
|
|
Total
|
5,300
|
Port Connectivity
|
|
Projects
|
Investment
( INR Cr)
|
|
1
|
Pipeline
from Paradip to Hyderabad
|
3,000
|
|
2
|
Doubling
of rail line from Bhadrak to Dharmra Port
|
650
|
|
3
|
New
ICD Development in Bhubaneshwar
|
85
|
|
4
|
Heavy
Haul railways corridor from Talcher to Paradip port
|
6,000
|
|
5
|
Third
line from Jakhapura to Haridaspur
|
150
|
|
6
|
3rd
line from Bhadrak to Nergundi
|
837
|
|
7
|
3rd
and 4th line from Budhapank-Salegaon via Rajatgarh
|
1,500
|
|
8
|
Doubling
of line from Rajatgarh to Barang
|
276
|
|
9
|
Doubling
of line from Sambhalpur to Talcher
|
679
|
|
10
|
Doubling
of line from Titlagarh to Sambhalpur
|
1,351
|
|
11
|
New
Line from Angul to Sukhinda Road
|
679
|
|
12
|
New
Line from Haridaspur to Paradip
|
1,118
|
|
13
|
Third
line from Sukhinda Road to Jakhapura
|
56
|
|
14
|
New
line from Jharsuguda to Barpalli
|
1,000
|
|
15
|
New
line from Talcher to Kharagpur via Baripada
|
5,000
|
|
16
|
New
line from Talcher to Angul
|
500
|
|
17
|
Double
rail track from Gopalpur Port to Chatarpur
|
140
|
|
|
Total
|
23,021
|
WEST BENGAL – Rs.14,268 cr
Port Modernization
|
|
Projects
|
Investment
( INR Cr)
|
|
1
|
LPG
Import Terminal at Eastern ports ( Haldia, Paradip and Dhamra)
|
800
|
|
2
|
Mechanisation
of Berth 3 at Haldia Dock Complex at Haldia
|
150
|
|
3
|
Building
Barge Jetties to Support the Anchorage Operations at Haldia
|
120
|
|
4
|
New
Exclusive Berth outside Dock for Edible Oil and Chemicals at Haldia
|
100
|
|
5
|
Development
of Multipurpose Berth outside the Dock Basin at Haldia
|
200
|
|
6
|
New
Port at Sagar
|
1,160
|
|
|
Total
|
2,530
|
Port-led Industrialization
|
|
Projects
|
Investment
( INR Cr)
|
|
1
|
Development
of an integrated export based leather and footwear cluster in Kolkata(
Bantala)
|
1,880
|
|
|
Total
|
1,880
|
Port Connectivity
|
|
Projects
|
Investment
( INR Cr)
|
|
1
|
Road
connectivity between proposed Port at Sagar Island and Muriganga bridge &
between Muringanga bridge and proposed Rail yard at Kashinagar
|
171
|
|
2
|
Rail
connectivity between proposed Port at Sagar Island and Kashinagar Rail
station
|
270
|
|
3
|
Improvement
of existing road connecting Kolkata Port Trust to NH6 and Kolkata Port Trust
to nearby Industrial Clusters
|
24
|
|
4
|
Expressway
from Panagarh ( Durgapur) to Haldia
|
9000
|
|
5
|
Setting
up of 2nd Railway Line from Durgachak take off point to ‘A’ cabin
at Durgachak at HDC, Haldia
|
100
|
|
6
|
Construction
of RoB cum Flyover at Ranichak level crossing at Kolkatta Port
|
208
|
|
7
|
New
ICD Development in North Bengal ( Darjeeling )
|
85
|
|
|
Total
|
9,858
|
*****
UM/NP